Hoffman v. King

36 N.W. 25, 70 Wis. 372, 1888 Wisc. LEXIS 62
CourtWisconsin Supreme Court
DecidedJanuary 10, 1888
StatusPublished
Cited by15 cases

This text of 36 N.W. 25 (Hoffman v. King) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoffman v. King, 36 N.W. 25, 70 Wis. 372, 1888 Wisc. LEXIS 62 (Wis. 1888).

Opinion

Cassoday, J.

The mill at which the lumber was sawed was situated on ITog island, so called. It had the capacity of manufacturing about 12,000 feet of lumber per day. To aid in handling the lumber thus manufactured, there was a car track constructed, extending out from the mill some four or five hundred feet, and elevated from two to seven feet above the ground. Along one side of this track, and perpendicular to it, skids were placed, upon which the lumber contracted for was to be piled or delivered by the plaintiff when removed from the car. Such delivery was to be made as fast as the lumber could be sawed by the [376]*376mill from the date of the contract until March 15, 1832, and as much later as would admit of practical hauling to the railroad station on sleighing, frozen ground, or ice. The railroad stations at Meadow Yalley and Mill Grove, mentioned in the contract, were each some six or seven miles distant from the mill in question. From the mill to either of those stations there were none other than corduroy roads over a marsh or marshes, available only when frozen hard. It was over such road or roads that the defendant hauled from the mill to such stations, or one of them, the 359,421 feet of the lumber mentioned. It is conceded that upon that lumber the defendant had paid the plaintiff the first in-stalment of $3.50 per thousand feet, amounting to $1,267.25, and that the other instalment of $3.25 per thousand feet would not, by the terms of the contract, become due thereon until after the delivery on the skids by the plaintiff of the entire million feet of lumber called for by the contract.

It appears from the evidence that whenever there was a thaw, so as to make it impracticable to draw the lumber to the railroad station over the corduroy roads, the defendant allowed it to accumulate, more or less, on the skids along the track running out from the mill. Thus, it is said that some time in January, or the fore part of February, 1882, and when there was only about 50,000 feet upon the skids, it was so accumulated at certain points along the track as to make it necessary on the part of the plaintiff to stop the mill for a few hours and pile the lumber back further from the track; and that the same was substantially repeated a week or two afterwards. No rescission of the contract, however, was attempted or is claimed by reason of either of those accumulations. But about March 6, 1882, such lumber was again allowed to accumulate upon such skids, until it reached about 200,000 feet, when, it is claimed, the mill was necessarily stopped for a few days, and the same was piled back further from the track, by the procurement [377]*377of the plaintiff, at an expense of forty or fifty dollars. ¥e find in the bill of exceptions considerable evidence on the part of the defense to the effect that on the day the mill shut down, to wit, Monda}7 morning, March 6, 1882, some half a dozen men went to the mill, on the part of the defendant, to remove the lumber back from the skids, but that the plaintiff refused to allow them to do so, and insisted that the lumber was his, and that the defendant should have no more of it; and that there was then among the lumber so accumulated on the skids from thirty to forty thousand feet of culls not included in the contract. The plaintiff’s evidence is to the effect that there were no culls among such accumulations; but he concedes, in effect, that after he had so removed the lumber back into the yard, and before the commencement of this action,' the defendant came to him and offered to pay him up if he wrould let him have the lumber upon the contract, which he declined to do.

The defendant never received any portion of this 200,000 feet, and of course the lumber here replevied includes no part of it. On the contrary, it stands confessed by the plaintiff, that he forbade the defendant from removing any portion of it unless he would first pay the expense and damage consequent upon such failure to remove; Avhereas the defendant claims that he was prevented from removing such lumber by the plaintiff himself, and besides was excused from such removal under the decision on the former appeal (58 Wis. 314), by reason of the mixture with it of inferior lumber by the plaintiff. The defendant never received any of the lumber contracted for, except the 359,421 feet mentioned, which the defendant had hauled from the mill to the railroad station. It is conceded that a very large portion of the lumber thus contracted for was never delivered upon the skids, nor sawed by the plaintiff. This action is only to recover 175,984 feet of the lumber which the defendant had thus hauled to the railroad station. It [378]*378is based wholly upon the alleged right of a partial rescission of the contract. Whether there had ever been any such rescission by agreement of the parties, — -that is to say, by the refusal of the defendant, with the consent of the plaintiff, to receive anj' more lumber on the contract,— was fully and fairly submitted to the jury with instructions to find for the plaintiff if it had; and their verdict in favor of the defendant is, in effect, that he never so refused, and consequently there was no such agreement, and hence no such rescission. It is difficult to perceive how the jury, upon the evidence, could have found otherwise, since the plaintiff himself, in effect, concedes that the defendant at all times insisted to him that he must have the lumber.

The fact thus determined'by the jury is one deemed of special significance on the question of rescission by the more recent English cases. Thus Lord Coleeidg-e, G. L, said, as the result of conflicting- cases, “that the true question is whether the acts and conduct of the party evince an intention no longer to be bound by the contract.” Freeth v. Barr, L. R. 9 C. P. 213. In a more recent case, Jessel, M. E., said that “ there is no absolute rule which can be laid down in express terms as to whether a breach of contract on the one side has exonerated the other from performance of his part of the contract.” . He then reiterates the rule above quoted from the chief justice, and adds, “that makes it a question of evidence.” Mersey S. & I. Co. v. Naylor, L. R. 9 Q. B. Div. 057. The same rule -was sanctioned in the same case on appeal in the House of Lords. L. R. 9 App. Cas. 438, 439. In such submission to the jury they were, in effect, charged that “the only question they should consider was whether there was such rescission by such mutual agreement of the parties.”

This brings us to the question whether there was any error in the court holding, as a matter of law, that there had been no valid rescission of the contract by reason of [379]*379the defendant’s breach of the stipulation therein to keep the lumber from accumulating upon the skids. The rule laid down by Lord Mansfield, O. L, and often quoted approvingly, is, “that the dependence or independence of covenants was to be collected from the evident sense and meaning of the parties, and that however transposed they' might be in the deed their precedency must depend on the order of time in which the intent of the transaction requires their performance.” Jones v. Barkley, 2 Doug. 691. To the same effect, Bettini v. Gye, L. R. 1 Q. B. Div. 181; Tipton v. Feitner, 20 N. Y. 425; Cadwell v. Blake, 6 Gray, 407. Applying that rule here, and we find that the plaintiff was, from day to day, and as fast as sawed, to assort and deliver the “ merchantable pine lumber ” upon the skids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Case v. Beyer
125 N.W. 947 (Wisconsin Supreme Court, 1910)
Jung Brewing Co. v. Konrad
118 N.W. 548 (Wisconsin Supreme Court, 1908)
Barker & Stewart Lumber Co. v. Edward Hines Lumber Co.
137 F. 300 (U.S. Circuit Court for the District of Western Wisconsin, 1905)
Phelps v. Mineral Springs Heights Co.
1904 WI 218 (Wisconsin Supreme Court, 1904)
Racine Shoe Manufacturing Co. v. Badger Manufacturing Co.
100 N.W. 1044 (Wisconsin Supreme Court, 1904)
McVity v. E. D. Albro Co.
90 A.D. 109 (Appellate Division of the Supreme Court of New York, 1904)
Reindl v. Heath
91 N.W. 734 (Wisconsin Supreme Court, 1902)
Kaukauna Electric Light Co. v. City of Kaukauna
89 N.W. 542 (Wisconsin Supreme Court, 1902)
Ludington v. Patton
86 N.W. 571 (Wisconsin Supreme Court, 1901)
Crossen v. Murphy
49 P. 858 (Oregon Supreme Court, 1897)
American Building & Loan Ass'n v. Rainbolt
67 N.W. 493 (Nebraska Supreme Court, 1896)
Sheehy v. Duffy
61 N.W. 295 (Wisconsin Supreme Court, 1894)
McConnell v. Hughes
53 N.W. 149 (Wisconsin Supreme Court, 1892)
Becker v. Trickel
50 N.W. 406 (Wisconsin Supreme Court, 1891)
McDonald v. Bryant
40 N.W. 665 (Wisconsin Supreme Court, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
36 N.W. 25, 70 Wis. 372, 1888 Wisc. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoffman-v-king-wis-1888.