Hoerstman General Contracting, Inc v. Hahn

711 N.W.2d 340, 474 Mich. 66
CourtMichigan Supreme Court
DecidedMarch 23, 2006
DocketDocket 126958
StatusPublished
Cited by78 cases

This text of 711 N.W.2d 340 (Hoerstman General Contracting, Inc v. Hahn) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoerstman General Contracting, Inc v. Hahn, 711 N.W.2d 340, 474 Mich. 66 (Mich. 2006).

Opinion

KELLY, J.

This case calls on us to decide whether an accord and satisfaction existed between the parties. The Court of Appeals found that it did not. We disagree and rule that the parties reached an accord and satisfaction. Therefore, we reverse the decision of the Court of Appeals and remand the case to the trial court for entry of judgment in favor of defendants.

SUBSTANTIVE FACTS AND PROCEDURAL HISTORY

This case centers on a contract to remodel and reconstruct a lakeside residence in Edwardsburg, *68 Michigan, 1 made between plaintiff, Hoerstman General Contracting, Inc., and defendants Juanita and Ronald Hahn, the owners. Unfortunately, several unforeseen events during construction caused significant delay and cost overruns. When plaintiff did not meet the expected deadline to complete the work, Ronald Hahn informed plaintiffs owner that he wanted the job finished no matter the expense. Plaintiff agreed to work under these conditions if Ronald agreed to pay the extra costs. Ronald made it clear that he was not concerned with the price.

Plaintiff followed Ronald’s oral instructions on changes to the project. These were not minor modifications. They included moving walls and tearing up concrete floors. According to plaintiff, a later-compiled written list of the oral changes to the contract covered over ten pages. Despite these significant alterations, Ronald refused to agree in writing to any changes to the existing contract.

Defendants acknowledged that they owed more than the original bid price and paid plaintiff $125,000. But plaintiff claimed defendants owed an additional $32,750. In an apparent attempt to settle the dispute, plaintiff sent a letter to defendants asking for $16,910.79. Plaintiff indicated that it would provide the lien waiver and close the account in exchange for payment of the amount requested.

Defendants did not pay the $16,910.79. Instead, they replied with a letter in which they calculated the balance due at $5,144.79. They included with the letter their check for that amount. They wrote “final payment” on the check. In the letter, they indicated that *69 they believed that their payment of $5,144.79 closed the account. The letter provided:

If we send you a check for $5144.79 we will consider this account closed and will not expect discussion of the other * items.[ 2 ] We will then expect the lein [sic] waiver to he sent. If this is not acceptable, we will have to resort to arbitration per attorney [sic].

Plaintiff sought legal advice. Its attorney crossed out the words “final payment” on the check and advised plaintiff to deposit it. Plaintiff followed this advice, credited defendants’ account in the amount of $5,144.79, and did not close the account.

When defendants made no additional payments, plaintiff brought suit seeking damages and foreclosure of its construction lien. Defendants counterclaimed for amounts they believed they had overpaid. In their answer to plaintiff’s complaint, defendants asserted the affirmative defense of accord and satisfaction. After a bench trial, the court awarded plaintiff approximately $26,000 after setting off $5,800 on defendants’ counterclaim. The court did not explicitly rule on the issue of accord and satisfaction.

Both parties appealed to the Court of Appeals. The Court of Appeals ruled that the words “final payment” on the check were not sufficient to inform plaintiff that acceptance of the check discharged the entire claim. Hoerstman Gen Contracting, Inc v Hahn, unpublished opinion per curiam of the Court of Appeals, issued June 15, 2004 (Docket No. 244507). This Court granted leave to appeal limited to whether an accord and satisfaction occurred in this case. 472 Mich 898 (2005).

*70 STANDARD OF REVIEW

The existence of an accord and satisfaction may be decided as a question of law if the facts of the case are undisputed and not open to opposing inferences. Urben v Pub Bank, 365 Mich 279, 286; 112 NW2d 444 (1961). During oral argument, the parties conceded that the relevant facts here are not in dispute. Therefore, the case presents a question of law which we review de novo. Anzaldua v Band, 457 Mich 530, 533; 578 NW2d 306 (1998).

ACCORD AND SATISFACTIONS

An accord and satisfaction is an affirmative defense 3 grounded in contract principles. An accord is a contract and requires a meeting of the minds of those who enter into it. Fritz v Marantette, 404 Mich 329, 334; 273 NW2d 425 (1978), quoting Gitre v Kessler Products Co, *71 387 Mich 619, 624; 198 NW2d 405 (1972). A satisfaction is the discharge of the debt occurring after acceptance of the accord. 4

Cases in which an accord and satisfaction defense is relevant involve a good-faith dispute about an unliquidated amount owing under a contract. One party makes a tender in satisfaction of the claim (an accord). The other accepts or rejects the accord. If the second party accepts the tender, there is both an accord and a satisfaction. See Nationwide Mut Ins Co v Quality Builders, Inc, 192 Mich App 643, 647; 482 NW2d 474 (1992), citing Shaw v United Motors Products Co, 239 Mich 194; 214 NW 100 (1927).

In this Court’s handling of common-law accord and satisfaction, two lines of cases developed. The first holds that whether there was a sufficient meeting of the minds for an accord and satisfaction is a question for the jury. 5 The second holds that the required meeting of the minds is implied as a matter of law by the acceptance of the offer. The fact that the recipient altered or crossed out the accord is irrelevant. 6

*72 As in this case, the affirmative defense of accord and satisfaction often involves the use of a check. A check is a negotiable instrument entered into between the maker and the payee. Huler v Nasser, 322 Mich 1, 6; 33 NW2d 637 (1948). As will be demonstrated later, when the Legislature enacted MCL 440.3311, it followed the second line of cases. This effectively repudiates any application of the first line of cases to accord and satisfactions involving negotiable instruments, leaving MCL 440.3311 to control all accord and satisfactions involving negotiable instruments.

UCC PREEMPTION IN CASES INVOLVING NEGOTIABLE INSTRUMENTS

In 1964, the Michigan Legislature enacted the Uniform Commercial Code. In 1993, the Legislature added to Article 3 of the UCC a provision governing accord and satisfaction. Article 3 is known as the “Uniform Commercial Code-Negotiable Instruments.” MCL 440.3101.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacqueline Davis v. Betmgm LLC
Michigan Supreme Court, 2025
Angus v. Flagstar Bank, FSB
E.D. Michigan, 2025
Lisa Kemerer v. State of Michigan
Michigan Court of Appeals, 2024
Erica Ruth Fisher v. Chakira Lekeish Calcote
Michigan Court of Appeals, 2023
People of Michigan v. Alexander James Horton
Michigan Court of Appeals, 2023
Dean McMaster v. Dte Energy Company
Michigan Supreme Court, 2022
In Re Von Greiff Estate
Michigan Supreme Court, 2022
Vhs of Michigan Inc v. Jay Juan-Jarmaine Jones
Michigan Court of Appeals, 2022
Hollie a Bastin v. Januarius Kim Welch
Michigan Court of Appeals, 2021
Rafaeli LLC v. Oakland County
Michigan Supreme Court, 2020
Dean McMaster v. Dte Energy Company
Michigan Court of Appeals, 2020
in Re Von Greiff Estate
Michigan Court of Appeals, 2020
Ali Bazzi v. Sentinel Insurance Company
919 N.W.2d 20 (Michigan Supreme Court, 2018)
Perlin v. Time Inc.
237 F. Supp. 3d 623 (E.D. Michigan, 2017)
Moeller v. American Media, Inc.
235 F. Supp. 3d 868 (E.D. Michigan, 2017)
DIALLO v. LaROCHELLE
310 Mich. App. 411 (Michigan Court of Appeals, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
711 N.W.2d 340, 474 Mich. 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoerstman-general-contracting-inc-v-hahn-mich-2006.