Dean McMaster v. Dte Energy Company

CourtMichigan Court of Appeals
DecidedJuly 2, 2020
Docket339271
StatusUnpublished

This text of Dean McMaster v. Dte Energy Company (Dean McMaster v. Dte Energy Company) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dean McMaster v. Dte Energy Company, (Mich. Ct. App. 2020).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

DEAN McMASTER, UNPUBLISHED July 2, 2020 Plaintiff-Appellant,

v No. 339271 Oakland Circuit Court DTE ENERGY COMPANY, LC No. 15-147414-NO

Defendant, ON REMAND and

DTE ELECTRIC COMPANY,

Defendant-Appellee, and

FERROUS PROCESSING AND TRADING COMPANY d/b/a FERROUS PROCESSING AND TRADING CO,

Defendant.

Before: JANSEN, P.J., and METER and STEPHENS, JJ.

PER CURIAM.

This case is before us on remand from our Supreme Court “for application of the law of ordinary negligence and for consideration of the issues raised by the parties on the question of the defendant’s legal duty.”1 Again, we affirm the trial court’s grant of summary disposition to defendant DTE.

I. BACKGROUND

1 McMaster v DTE Electric Company, ___ Mich ___; 933 NW2d 42 (2019).

-1- Our previous opinion summarized the facts of this case as follows:

DTE contracted with Ferrous Processing & Trading Company (“Ferrous”) to have containers of scrap picked up from DTE facilities and taken to Ferrous’ salvage yard. Ferrous subcontracted with P&T Leasing Company (“P&T”) to pick up the scrap containers and deliver them to Ferrous. Plaintiff was employed by P&T as a driver. This case arises out of injuries sustained by plaintiff when a large steel pipe rolled out of a container and struck him in the leg resulting in the amputation of his leg.

On the morning of October 14, 2015 plaintiff arrived at DTE’s Belle River Power Plant to pick up a container of demolition scrap and deliver it to Ferrous’ salvage yard. Plaintiff inspected the container prior to hauling it away and observed a large industrial blue steel pipe inside the container. The pipe was parallel to and up against the back door of the container. Plaintiff could have requested that a DTE crane operator relocate or remove the pipe from the container but did not do so. Plaintiff used his truck’s hydraulics to lift the container onto his trailer, secured the container to his truck and departed the Belle River Power Plant for the Ferrous facility in Pontiac. Upon plaintiff’s arrival at the Ferrous salvage yard, he took the truck to be weighed, then drove to the inspection area to meet with the Ferrous road inspector. The inspector told plaintiff where to take the container and plaintiff drove to the specified dumping location. Once he arrived at the specified location, he got out of the truck and walked backed to where the container was secured to his flat-bed trailer. Plaintiff kept the truck engine running because it also controlled the hydraulic system that was necessary to lift the container up to the 35-40 degree angle needed to dump the container. He cracked the container door partially open to see if any materials would fall out. When nothing fell out, he felt it was safe to continue and proceeded to open the door all of the way so that the materials could be dumped out. However, before plaintiff was able to dump out the contents of the container, the Ferrous road inspector had second thoughts about where this particular load should be dumped and he and another Ferrous employee decided that it should be taken to another area in the facility. Plaintiff and the two Ferrous employees talked for about 5-10 minutes about where the container should be dumped while standing behind the wide open door of the container with the truck’s engine running. Once the decision had been made as to where to take the container, plaintiff proceeded to return to his truck in order to shut off the hydraulics so that he could take the container to another area as instructed. As plaintiff walked to the driver side of the truck, the blue pipe rolled out of the container and struck plaintiff in the leg resulting in amputation of his leg.

Plaintiff filed suit against defendants DTE and Ferrous alleging negligence against both. Both defendants answered, denying liability and moving for summary disposition under MCR 2.116(C)(10) asserting that they did not owe plaintiff any duty of care and that plaintiff was not able to meet his burden of proof as to causation. The trial court held a hearing on both motions for summary disposition on January 4, 2017 and while it denied the motion brought by Ferrous, it granted DTE’s motion concluding that there was neither evidence of a breach of duty nor

-2- proximate causation. Ferrous and the plaintiff subsequently entered into a stipulated order of dismissal on June 28, 2017. The instant appeal against defendant DTE followed. [McMaster v DTE Electric Company, unpublished opinion per curiam of the Court of Appeals, entered November 8, 2018 (Docket No. 339271).]

II. SUMMARY DISPOSITION

A. STANDARD OF REVIEW

“This Court reviews the grant or denial of summary disposition de novo to determine if the moving party is entitled to judgment as a matter of law.” Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999).

A motion under MCR 2.116(C)(10) tests the factual sufficiency of the complaint. In evaluating a motion for summary disposition brought under this subsection, a trial court considers affidavits, pleadings, depositions, admissions, and other evidence submitted by the parties, MCR 2.116(G)(5), in the light most favorable to the party opposing the motion. Where the proffered evidence fails to establish a genuine issue regarding any material fact, the moving party is entitled to judgment as a matter of law. MCR 2.116(C)(10), (G)(4). [Id. at 120].

Issues of statutory interpretation are also reviewed de novo. Ford Motor Credit Co v Detroit, 254 Mich App 626, 628; 658 NW2d 180 (2003).

B. ANALYSIS

“To establish a prima facie case of negligence, plaintiff must prove four elements: (1) a duty owed by the defendant to the plaintiff, (2) a breach of that duty, (3) causation, and (4) damages.” Finazzo v Fire Equip Co, 323 Mich App 620, 635; 918 NW2d 200 (2018).

1. DUTY

“Contractors have a common-law duty to perform their work with ordinary care so as not to unreasonably endanger employees of other subcontractors or anyone else lawfully on the worksite.” Id. at 634. We previously decided that plaintiff, as an employee of a sub-contractor, was owed the duty of reasonable care. McMaster v DTE Energy Co, unpublished per curiam opinion of the Court of Appeals, issued Nov 8, 2018 (Docket No. 339271), p 2. See Clark v Dalman, 379 Mich 251, 262; 150 NW2d 755 (1967) (“The general duty of a contractor to act so as not to unreasonably endanger the well-being of employees of either subcontractors of inspectors, or anyone else lawfully on the site of the project, is well settled.”) We revisit that holding on remand as directed.

The defendant argues that the common law duty which was owed to plaintiff under the common law was abrogated by the passage of MCL 480.11a. Under MCL 480.11a, Michigan adopted the federal Motor Carrier Safety Regulations as provided by 49 CFR 392.9. DOT v Initial Transport, Inc, 276 Mich App 318, 323; 740 NW2d 720 (2007), rev’d in part on other grounds 481 Mich 862 (2008). The relevant portion of 49 CFR 392.9 states:

-3- (a) General. A driver may not operate a commercial motor vehicle and a motor carrier may not require or permit a driver to operate a commercial motor vehicle unless— (1) The commercial motor vehicle’s cargo is properly distributed and adequately secured . . . * * *

(b) [T]he driver of a truck or truck tractor must—

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Velez v. Tuma
821 N.W.2d 432 (Michigan Supreme Court, 2012)
Dawe v. Dr Reuven Bar-Levav & Associates, Pc
780 N.W.2d 272 (Michigan Supreme Court, 2010)
Wold Architects and Engineers v. Strat
713 N.W.2d 750 (Michigan Supreme Court, 2006)
Hoerstman General Contracting, Inc v. Hahn
711 N.W.2d 340 (Michigan Supreme Court, 2006)
Ford Motor Credit Co. v. City of Detroit
658 N.W.2d 180 (Michigan Court of Appeals, 2003)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Clark v. Dalman
150 N.W.2d 755 (Michigan Supreme Court, 1967)
Department of Transportation v. Initial Transport Inc.
740 N.W.2d 720 (Michigan Court of Appeals, 2007)
Detroit City Council v. Mayor of Detroit
770 N.W.2d 117 (Michigan Court of Appeals, 2009)
David Finazzo v. Fire Equipment Company
918 N.W.2d 200 (Michigan Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Dean McMaster v. Dte Energy Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dean-mcmaster-v-dte-energy-company-michctapp-2020.