Hoel-Steffen Construction Co. v. State

35 Ill. Ct. Cl. 108, 1982 Ill. Ct. Cl. LEXIS 18
CourtCourt of Claims of Illinois
DecidedJune 25, 1982
DocketNo. 77-CC-1114
StatusPublished
Cited by2 cases

This text of 35 Ill. Ct. Cl. 108 (Hoel-Steffen Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoel-Steffen Construction Co. v. State, 35 Ill. Ct. Cl. 108, 1982 Ill. Ct. Cl. LEXIS 18 (Ill. Super. Ct. 1982).

Opinion

Roe, C. J.

This claim arises from a contract between Hoel-Steffen Construction Co., Claimant, and the Illinois Capital Development Board. Claimant is a corporation engaged in the business of constructing various types of commercial buildings as a general contractor. On February 15, 1974, Claimant entered into a contract with the Capital Development Board (CDB) to construct a one-story building at the Wabash Valley College in Mt. Carmel, Illinois. Prior to the entering of this agreement, the CDB furnished several documents to Hoel-Steffen Construction Co. upon which Hoel-Steffen was to base its bid. The differences of interpretation of these documents, which make up part of the contract agreement, is the basis of the dispute.

Most of the claim is based on several instances in which Claimant says it was authorized by the CDB to do extra work not included in the original contract. Claimant charges that it has performed the work and has not been compensated. Respondent argues that all of the work done by Claimant was either contained in the original contract price or performed without authorization. There is no dispute as to the quality of the work.

Originally CDB furnished Claimant with specifications, supplemental drawing details and two addenda and actual architectural drawings for the project so as to make its bid. The two addenda clarified parts of the drawings and specifications. Also submitted as part of the contractual documents was a document entitled “General Supplementary Conditions of the Contract for Construction.” This is a standard form prepared by the American Institute of Architects and generally defines in contract terms the rights and obligations of all parties. It further provides that the contract documents consist of “the agreement, the Conditions of the Contract (General, Supplementary and other Conditions), the drawings, the Specifications, all Addenda issued prior to execution of the contract, and all Modifications thereto.”

I

On August 6, 1975, architects issued to Claimant a field order directing Claimant to do two items of extra work. The second item on the order directed Claimant to provide adapter frames for light fixtures in a certain area so as to accommodate existing fixtures at the job. The whole field order was “subject to an equitable adjustment in the contract amount and/or performance.” Claimant was paid for the first item but not for the adapters. Claimant states that the adapters became necessary to correct an error in the shop drawings. According to Mr. Williams, vice president of Claimant, the original light fixtures did not fit into the ceiling design because of a lack of coordination between the architect and the prime electrical contractor and therefore the adapters had to be installed. Claimant argues that the error was caused by negligence on the part of the architect.

It is the generally accepted rule of law that the rights and obligations of the parties to a contract are determined from the plain, unambiguous wording of the contract. (Touhy v. Twentieth Century-Fox Film Corp. (1969), 69 Ill. App. 3d 508, 387 N.E.2d 862.) Sections 4.13.3 and 4.13.4 of the General and Supplementary Conditions state:

“By approving and submitting shop drawings and samples the (claimant) therefore represents that he has determined and verified all field measurement, field construction criteria, materials, catalong numbers and similar data or will do so, and that he has checked and coordinated each shop drawing and sample with the requirements of the work and contract documents.” (Emphasis added)

Furthermore, section 4.13.5 provides that, “The Architect will review and approve shop drawings and samples . . . only for conformance with the design concept of the project with the information given in the Contract Documents. The Architect’s approval of a separate item shall not indicate approval of an assembly in which the items function.” (Emphasis added). The shop drawings which contained a description of the light fixtures were approved by Claimant, and it was therefore the responsibility of Claimant to coordinate these fixtures with the type of ceiling. Mr. Williams testified that it was his understanding the parties had orally agreed that the architect had the final responsibility. However, there is no evidence to support this. In fact, Respondent’s refusal to pay for the adapters after it had paid for the first item in the field order indicates such a lack of agreement. No oral modification of the clear terms of a contract will be valid without the consent of both parties to the contract. Hulcher v. Adcock (1960), 25 Ill. App. 2d 255, 166 N.E.2d 168; Faith v. Martoccio (1974), 21 Ill. App. 3d 999, 316 N.E.2d 164.

II

The second area of dispute concerns $4,400.00 worth of expenses incurred by Claimant for plumbing work five feet outside the building lines. The confusion arose because of an addendum sent from the CDB to Claimant before the actual bids were submitted. The addendum states that the plumbing and fire protection work had already been bid, that the low bidder for the plumbing and fire protection work was H & H Plumbing and that the bid was $65,356.00. A notation following states:

“H & H Plumbing price includes $7,800.00 for plumbing and fire protection work 5'00" outside of the building lines. This work is under the General Construction contract as stated in the Site Utilities §02550. H & H mistakingly (sic) included this in their base price.”

Respondent asks us to read only the underlined portion of the statement. However, the addendum must be read in its entirety and in the context in which it occurs.

According to Mr. Williams, the purpose of an addendum as it is commonly used in the construction industry is to inform the general contractor, before he submits his final bid, as to additions or deletions in the contract. Before Claimant received this addendum, it was prepared to submit a bid which included the plumbing work five feet outside the building lines. After it received the addendum, Claimant assumed that this was to inform Claimant of a deletion. Had Respondent not sent the addendum, Claimant clearly would have submitted a bid sufficient to include this work. Respondent argues that Claimant should have written into its bid that it was deleting section 02550. While this would have clarified matters, the initial confusion was caused by Respondent. If Respondent had simply indicated that section 02550 is still under the general construction contract and should be bid, or that $7,800.00 should be deducted from H & H Plumbing’s bid for work five feet outside the building lines, there would have been no confusion. The contract and addendum were prepared by Respondent, and any ambiguities are to be construed against Respondent. Epstein v. Yoder (1979), 72 Ill. App. 3d 966, 391 N.E.2d 267.

Respondent also argues that it should not be required to pay Claimant since it has already paid H & H Plumbing $7,800.00 for the same work. This argument is inconsistent with Respondent’s position.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R. W. Dunteman Co. v. State
52 Ill. Ct. Cl. 33 (Court of Claims of Illinois, 1999)
New Life Development Corp. v. State
45 Ill. Ct. Cl. 65 (Court of Claims of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ill. Ct. Cl. 108, 1982 Ill. Ct. Cl. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoel-steffen-construction-co-v-state-ilclaimsct-1982.