932 P.2d 139 (1997)
131 Wash.2d 373

Larry HILLIS and Veralene Hillis, husband and wife, Respondents,
v.
STATE of Washington, DEPARTMENT OF ECOLOGY; Mary Riveland, Director of the Department of Ecology; and Pat Spurgin, Central Regional Director of the Department of Ecology, Appellants.

No. 63399-1.

Supreme Court of Washington, En Banc.

Argued October 24, 1996.
Decided March 6, 1997.

*141 Cairncross & Hempelmann, P.S., Terrance I. Danysh, Patrick D. Brown, Seattle, amicus curiae on behalf of Coordinated Appellate Group.

Christine Gregoire, Attorney General, Jay J. Manning, Asst., Mark C. Jobson, Asst., Olympia, for Appellants.

Lathrop, Winbauer, Harrel & Slothower, F. Steven Lathrop, Ellensburg, for respondents.

*140 GUY, Justice.

The Washington State Department of Ecology asks this Court to reverse a trial court order which orders it to immediately investigate the plaintiffs' applications to appropriate public groundwater. Ecology also challenges the order because it effectively forbids Ecology from conducting assessments of the state's watersheds and because it invalidates certain policy and priority decisions made by that agency. We reverse the order in part and affirm it in part.

Facts

Larry and Veralene Hillis (Hillis) plan to build a residential development on 97 acres of land in Kittitas County. The initial subdivision application was approved by the county on the condition that Hillis install a "Group A" water system which requires a groundwater withdrawal permit from the Department of Ecology (Ecology). In 1992, Hillis filed nine applications for water rights. Because of Ecology's delay in processing the applications, the Kittitas County Board of *142 Commissioners allowed Hillis to use two "Group B"[1] community water systems for the first phase of the development until the water right for a Group A system could be obtained. A water right permit is not required for withdrawal of public water in an amount not exceeding 5,000 gallons per day for single or group domestic uses or other specific purposes. RCW 90.44.050. However, the record reflects that the Hillis applications for water seek far in excess of that amount. Hillis still wishes to provide water to the entire development using a Group A water permit.

In October 1994, Hillis sought a writ of mandamus from the superior court asking the court to order Ecology to conduct an investigation and decide whether to issue the water permits. Hillis argued that Ecology had a statutory duty under the water code, RCW 90.03, to conduct investigations on applications for the appropriation of public waters and that it had failed to fulfill that duty in a timely manner.

Ecology replied that the central regional office of the Water Resources Program of the Department of Ecology had over 2,000 pending applications for water rights in that region and that 1,178 of those applications had been filed before the Hillis applications. Statewide, there are about 5,000 applications filed asking for the appropriation of public water. Ecology showed that the 1993 Legislature had cut the budget of the water permitting program by 63 percent and that Ecology had therefore been forced to drastically reduce the number of water permitting staff. Ecology submitted evidence about the complex geohydrologic conditions which exist in the Kittitas Valley and the high degree of prior appropriation of the surface and groundwater in the Yakima River drainage basin. Ecology also presented evidence that many protests had been filed opposing the Hillis applications on the grounds that the Hillis's proposed use of water could have negative impacts on local wells used for domestic water.

The trial court found that, historically, Ecology had processed groundwater right applications generally in the order in which they were received. (This finding of fact is challenged on appeal.) The court found that in the last several years Ecology has faced problems of an increased volume of water right applications, insufficient staff to process the applications, and other factors which caused a tremendous backlog. These factors include a growing recognition of the connection between groundwater and surface water, 10 years of drought conditions, and population growth accentuating the demand for services. The court found that in response to increased demands, Ecology started processing groundwater applications in "batches" grouped together in geographic areas to allow it to conduct one investigation, make one determination of water availability, and then to make a series of permit decisions based on that investigation.

The trial court found that in 1994, when the Legislature's mandated budget cuts became effective, Ecology's water right application backlog worsened to 2,000 applications in the central region with the Hillis applications in the approximate middle of that backlog. The court found that Ecology reassessed its ability to deliver services to fulfill its duties after the budget cuts and directed the water resource program to process water right applications by water basin under set priority criteria. Ecology ranked the state's 62 watersheds[2] in order of priority for conducting the watershed assessments. The court found that Ecology will not process or investigate any nonemergency applications in any watershed until a basin assessment is completed, or unless it believes there is sufficient groundwater in an area or there are a number of applications pending within the same hydrogeologic area.

Ecology also set criteria to determine priorities for processing of applications. The Kittitas County Commissioners (at the urging of Hillis) declared a groundwater emergency and requested Ecology to process all applications in that county. Ecology has not *143 acted on that request. The court found that, based on existing funding levels and the priorities for basin assessments, the Hillis applications will not be investigated for another five years, which will be eight years from the date of application. The trial court also found that Ecology had not followed the rule-making process of the Administrative Procedure Act as it pertains to Ecology's duty to investigate pursuant to RCW 90.03.290.

The trial court issued a "writ of mandamus."[3] The writ (1) orders Ecology to "immediately investigate" all of the Hillis's pending water applications and approve or deny them, (2) orders Ecology to consider hydrogeologic information supplied by Hillis, (3) orders Ecology not to undertake any watershed or basin assessments in advance of the investigation and timely processing of all pending groundwater applications, and (4) invalidates all of Ecology's priorities regarding pending applications, the decision to conduct watershed assessments, and the order of conducting those assessments. The writ also denies the Hillis's request for attorney fees.

We granted direct review. Ecology argues that the trial court's order violates the rights of senior water right applicants, intrudes on the funding decisions of the Legislature, and interferes with the administrative discretion of Ecology to implement the water resource statutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ron Fode v. Dep't of Ecology
Court of Appeals of Washington, 2025
PacifiCorp v. Watson
W.D. Washington, 2024
City of Tacoma v. Dep't of Ecology
Court of Appeals of Washington, 2023
Chandra N. Hampson, V. Seattle School District No. 1
Court of Appeals of Washington, 2023
Hired Hands, Llc v. Dept Of L & I, State Of Wa
Court of Appeals of Washington, 2020
Loyal Pig, LLC v. Dep't of Ecology
Court of Appeals of Washington, 2020
Center For Environmental Law & Policy v. State Of Washington
444 P.3d 622 (Court of Appeals of Washington, 2019)
Timothy Nelson, V Department Of L&i State Of Wa
Court of Appeals of Washington, 2017
Greensun Group Llc. v. City Of Bellevue
Court of Appeals of Washington, 2016
PacifiCorp v. Washington Utilities & Transportation Commission
376 P.3d 389 (Court of Appeals of Washington, 2016)
Robert Sudar v. Dept. Of Fish And Wildlife
Court of Appeals of Washington, 2015
Robert Sudar v. Fish & Wildlife Commission
347 P.3d 1090 (Court of Appeals of Washington, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
932 P.2d 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hillis-v-state-dept-of-ecology-wash-1997.