Hidroelectrica Santa Rita S.A. v. Corporacion AIC, SA

119 F.4th 920
CourtCourt of Appeals for the Eleventh Circuit
DecidedOctober 16, 2024
Docket23-12519
StatusPublished
Cited by1 cases

This text of 119 F.4th 920 (Hidroelectrica Santa Rita S.A. v. Corporacion AIC, SA) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hidroelectrica Santa Rita S.A. v. Corporacion AIC, SA, 119 F.4th 920 (11th Cir. 2024).

Opinion

USCA11 Case: 23-12519 Document: 27-1 Date Filed: 10/16/2024 Page: 1 of 15

[PUBLISH] In the United States Court of Appeals For the Eleventh Circuit

____________________

No. 23-12519 Non-Argument Calendar ____________________

HIDROELECTRICA SANTA RITA S.A., a Guatemalan company, Petitioner-Appellee, versus CORPORACION AIC, SA, a Guatemalan company,

Respondent-Appellant. ____________________

Appeal from the United States District Court for the Southern District of Florida D.C. Docket No. 1:21-cv-23807-RNS USCA11 Case: 23-12519 Document: 27-1 Date Filed: 10/16/2024 Page: 2 of 15

2 Opinion of the Court 23-12519

Before WILSON, LUCK, and TJOFLAT, Circuit Judges. TJOFLAT, Circuit Judge: Corporación AIC, S.A. (“AICSA”) appeals the District Court’s order granting the petition of Hidroeléctrica Santa Rita S.A. (“HSR”) to confirm and enforce an arbitration award. After careful review, we affirm the District Court’s order. I. Background AICSA and HSR are companies incorporated under the laws of Guatemala. HSR engaged AICSA for the full turnkey, design, engineering, procurement, construction, start-up, and commis- sioning of a new hydroelectric power plant. The power plant would be located on the Icbolay River in Cobán, a municipality in Guatemala. To govern their transaction and outline their obliga- tions, AICSA and HSR entered into the Engineering, Procurement, and Construction Agreement (the “EPC Contract”). The EPC Contract requires disputes between the parties to be resolved through arbitration. The local indigenous community did not support the con- struction of the power plant. Members of the community blocked access to the construction site and threatened those working on it. Citing force majeure, HSR issued a notice to AICSA to suspend work under the EPC Contract. And HSR later issued a notice of termination for convenience of the EPC Contract. USCA11 Case: 23-12519 Document: 27-1 Date Filed: 10/16/2024 Page: 3 of 15

23-12519 Opinion of the Court 3

HSR initiated arbitration proceedings under the EPC Con- tract to resolve several disputes arising from the project’s termina- tion. HSR sought payment from AICSA of advance payments, damages, fees, and expenses. AICSA in turn sought a dismissal of HSR’s claims, and payments from HSR relating to damages, costs, payments to its subcontractor, fees, and expenses. Moreover, AICSA requested the joinder of a third party, Novacom, S.A. (“No- vacom”), to the arbitration proceedings. AICSA had subcontracted Novacom to perform work on the power plant, and the termina- tion of work under the EPC Contract negatively affected Nova- com. Novacom sought a declaration that it was entitled to monies advanced to it by HSR and AICSA as well as payment from HSR of certain damages. The parties submitted briefs to the arbitral tribunal (the “Tri- bunal”) to resolve their disputes. In its first ruling, the Tribunal concluded Novacom could not join the arbitration. In the Final Award, the Tribunal held that AICSA is entitled to retain $2,429,627.08 and €703,290.00 for work completed pursuant to the EPC Contract. AICSA, however, was required to return to HSR $7,017,231.52 and €435,168.00, plus interest. And, pertinent to this appeal, the Tribunal dismissed AICSA’s claims that HSR breached the EPC Contract due to HSR’s alleged engagement in bribery schemes. The Tribunal further issued a “Decision and Addendum” in response to applications by AICSA and HSR to correct and inter- pret the Final Award. In this Decision and Addendum, the Tribunal USCA11 Case: 23-12519 Document: 27-1 Date Filed: 10/16/2024 Page: 4 of 15

4 Opinion of the Court 23-12519

clarified its mandate in the Final Award that AICSA “keep the Ad- vance Payment Bonds in place.” The Bonds were required by the EPC Contract to secure HSR’s advance payments to AICSA. But because the issuers of the Bonds considered them to have expired, HSR claimed that AICSA breached the Final Award by refusing to procure new Bonds as security for HSR’s advance payments. The Tribunal clarified the Final Award’s injunction that AICSA “keep in place” the Bonds as meaning AICSA must provide new bonds should any issuer consider the original Bonds to have lapsed. Dissatisfied with the Tribunal’s decision, AICSA initiated an action in the District Court seeking to vacate the arbitral award on the basis that the Tribunal had exceeded its powers. Corporacion AIC, S.A. v. Hidroelectrica Santa Rita S.A., No. 19-20294-CIV, 2020 WL 4478424, at *1 (S.D. Fla. Aug. 4, 2020). The District Court de- nied the petition and motion to vacate because Eleventh Circuit precedent foreclosed AICSA’s claim that a party to an arbitration under the Convention on the Recognition and Enforcement of For- eign Arbitral Awards (the “New York Convention”) could challenge an arbitration panel’s decision on the exceeding powers ground de- lineated in § 10(a)(4) of the Federal Arbitration Act (the “FAA”). Id. at *1–2; see 9 U.S.C. § 10(a)(4). A panel of this Court, constrained by Eleventh Circuit precedent, affirmed the District Court’s deter- mination. Corporacion AIC, SA v. Hidroelectrica Santa Rita S.A. (Hi- droelectrica I), 34 F.4th 1290, 1292 (11th Cir. 2022). But we granted AICSA’s petition for an en banc rehearing and then reversed the District Court, holding that in a New York Convention case where the arbitration seat is in the United States, or where United States USCA11 Case: 23-12519 Document: 27-1 Date Filed: 10/16/2024 Page: 5 of 15

23-12519 Opinion of the Court 5

law governs the arbitration conduct, Chapter 1 of the FAA provides the grounds for vacatur of the arbitral award. Corporación AIC, SA v. Hidroeléctrica Santa Rita S.A. (Hidroelectrica II), 66 F.4th 876, 890 (11th Cir. 2023). We then vacated the District Court’s judgment and remanded the action to the District Court to determine whether the Tribunal’s award should be vacated under the exceed- ing powers ground of § 10(a)(4) of the FAA. Id. Finally reaching the merits of AICSA’s claim that the Tribu- nal exceeded its powers, the District Court granted HSR’s petition to confirm the arbitral award. AICSA timely appealed, and we now must determine whether the Tribunal exceeded its powers. II. Standard of Review “We review the denial of a motion to vacate and the confir- mation of international arbitration awards de novo.” Grupo Unidos por el Canal, S.A. v. Autoridad del Canal de Panama, 78 F.4th 1252, 1261 (11th Cir. 2023) (first citing Técnicas Reunidas de Talara S.A.C. v. SSK Ingeniería y Construcción S.A.C., 40 F.4th 1339, 1343 (11th Cir. 2022); and then citing Gianelli Money Purchase Plan & Tr. v. ADM Inv. Servs., Inc., 146 F.3d 1309, 1311 (11th Cir. 1998)). “[W]e accept the district court’s findings of fact to the extent they are not clearly errone- ous.” Scott v. Prudential Sec., Inc., 141 F.3d 1007, 1014 (11th Cir. 1998), overruled in part on other grounds by Hall St. Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 128 S. Ct. 1396 (2008).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
119 F.4th 920, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hidroelectrica-santa-rita-sa-v-corporacion-aic-sa-ca11-2024.