Hertenstein v. Herrman

6 Ohio N.P. 93
CourtOhio Superior Court, Cincinnati
DecidedJuly 1, 1898
StatusPublished

This text of 6 Ohio N.P. 93 (Hertenstein v. Herrman) is published on Counsel Stack Legal Research, covering Ohio Superior Court, Cincinnati primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hertenstein v. Herrman, 6 Ohio N.P. 93 (Ohio Super. Ct. 1898).

Opinion

Smith, J.

The plaintiff, a taxpayer of the city of Cincinnati, having first requested the corporation counsel of -said oity to bring this case and said counsel having refused so to do, has brought the same on his own behalf as a taxpayer, as is provided may be done by sec. 1777 and 1778 of the Revised Statutes of Ohio.

The defendants, August Herrmann, Leopold Markbreit, Maurice J. Freiberg, C. M. Holloway and William B. Melish, constitute the board of trustees known as the “Commissioners of Water Works” of the city of Cincinnati, created by the act of 1895. (92 V. 606), and found in sections 2435-1 to 2435-18 inclusive, of the Revised Statutes.

Said trustees having in contemplation the grading of certain grounds, roads and certain portions of the river bank of the Ohio river, the revetment of certain slopes and the excavation of a certain clear well, as a part of the construction of a water works system for the city of Cincinnati, advertised for bids for said work according to certain plans in their office with the following specifications:

“All bids for the grading, masonry, and construction of roads near California for the water-works for the city of Cincinnati will be compared on the basis of the chief engineer’s approximate estimate of the quantities of work to be done, which is as follows:
1. Stripping........... 3,250 cubic yds.
2. Embankment — Site of Pumping Station 94,600 >) I)
3. Embankment,levee railroad bank, and filter grounds,south of Ebersole Lane.. 133,800
4. Embankment — Relocated part of New Richmond Pike____ 7,600
5. Rolling embankment and macadam..... 52,100 ton-miles,
6. Excavation — Slope of river bank....... 31,000 cubic yds.
7. Excavation for foundations........ 300 a a
8. Excavation for surface ditches........ 50 >) )!
9. 24 - inch cast - iron pipe drains......... 156 lineal ft.
10. 24 - inch vitrified-stone pipe drains... 186 >! !>
[94]*9411. Brick arch masonry 120 cubic yds.
12. Stone masonry in portals of arch culverts ............... 150
13. Stone masonry in head-walls of cast-iron and stone pipe drains........., — 40
14. Concrete............ 194
15. Stone paving in cement............. 7 cubic yds.
16. J Dry paving or rip-17. | rap............... 13,538 ” ”
18. J Sodding or sowing 19. 1 in grass........ 1,292 squares.
20. Macadam in roadway ................ 2,420 cubic yds.

The quantities given above are approximate only, and the board of trustees, “commissioners of waterworks,” reserve the right to increase ur diminish the amount cf any or all classes of work, or to dispense with any of them altogether, as they may deem best in the interest of the city of Cincinnati. ”

•Pursuant to said advertisement the board of trustees received bids which were referred to the engineer for computation, who reported, as was the fact that if riprap and seeding were used O. A. Phelan would be the lowest bidder, his bid under such conditions amounting tc $96,788.60; but if dry paving and sodding were used, the David Folz Asphalt Paving Company would be the lowest bidder, its bid under such conditions amounting to $109,881.80.

The explanation of this peculiar result is found in the fact that items 16 and 17 call for dry paving or riprap, and items 18 and 19 call for sodding or sowing in grass, and that the bid of Phelan was the lowest on the items of riprap and sowing in grass, while the bid of the David Folz Co. was the lowest on the items of dry paving and sodding.

Subsequently the board concluded that it would use a greater quantity of dry paving and sodding than it would use of riprap and sowing m grass, and thereupon awarded the contract to the David Folz Company.

The main contention of the plaintiff is. that the action of the board in-awarding the contract to any one was illegal and void for the reason that the specifications were illegal.

Section 7 of the water-works act provides that:. “Said commissioners in constructing such works or such enlargements, extensions, improvements or additions, shall also have power and authority and be governed in respect of contract as fellows: * * * Said commissioners shall before entoring into any contract, cause plans and specifications, detailed .drawings and forms of bids to be prepared, and careful estimate of cost tc be made; and when adopted by them, they may, in their discretion cause the plans and drawings to be multiplied and printed, by pnotographing, lighographing or other suitable process and the specifications and forms of bids, contracts and bonds to be prepare and have the same printed for distribution among the bidders. ”

It is further provided that: “Said commissioners shall not enter into any contract for work in the construction and completion of said waterworks system, without first causing thirty days’ notice to be given in one or more newspapers of general circulation in such city, that sealed proposls will be received for doing the work or furnishing the materials.”

To assist the board in its work including the drawing of plans and specifications and the making of estimates, the board is authorized:

“To employ such superintendents, engineers, clerks, laborers and other employees, as they may deem necessary and to fix their compensation.”

I believe the proposition to be beyond dispute that the preparation of plans and specifications of the work to be done is a vital condition to the entering inte any contract by the commissioners, with respect to a work of this magnitude.

It is true that my attention has not been directed to any case in which it has been held m Ohio that where the law requires the making of such plans and specifications before the making of a contract that the omission to make such plans and specifications deprives the public authorities of the right to make the contract; but if [95]*95.authority be lacking, the explanation to my mind would be that it was because the proposition was so plain .and self-evident that either the question had not been raised, or if raised, the decision of the question had not been regarded of sufficient importance to be reported.

One or two citations with respect to the obligations generally of the municipal authorities to observe such provisions with respect to the mode of making contraéis will suffice.

In Dillon on Municipal Corporation, sec. 449 (Fourth Edition) it is declared that:

“Respecting the mode in which contracts by corporations should be made, it is important to observe that when, as is sometimes the dase, the mode of contracting is specially and plainly prescribed and limited, that mode is exclusive, and must be pursued or the contract will not bind the corporation; but the courts have sometimes regarded the previsions on this subject as directory.”

But in Campbell v. Cincinnati, 49 Ohio St..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Crane
71 Am. Dec. 776 (Michigan Supreme Court, 1858)
Morris v. Morris
5 Mich. 171 (Michigan Supreme Court, 1858)
New York, Philadelphia & Norfolk Railroad v. Thomas
24 S.E. 264 (Supreme Court of Virginia, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
6 Ohio N.P. 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hertenstein-v-herrman-ohsuperctcinci-1898.