HERRING-MALBIS I, LLC v. Temco, Inc.

37 So. 3d 158, 2009 Ala. Civ. App. LEXIS 537, 2009 WL 3517580
CourtCourt of Civil Appeals of Alabama
DecidedOctober 30, 2009
Docket2080296
StatusPublished
Cited by2 cases

This text of 37 So. 3d 158 (HERRING-MALBIS I, LLC v. Temco, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HERRING-MALBIS I, LLC v. Temco, Inc., 37 So. 3d 158, 2009 Ala. Civ. App. LEXIS 537, 2009 WL 3517580 (Ala. Ct. App. 2009).

Opinion

PITTMAN, Judge.

Herring-Malbis I, LLC; Eastern Shore Centre I, LLC; and Eastern Shore Centre II, LLC (collectively “Herring-Malbis”) appeal from an order of the Baldwin Circuit Court awarding an attorney fee to TEMCO, Inc. (“TEMCO”), pursuant to Ala.Code 1975, § 8-29-1 et seq., usually referred to as the Prompt Payment Act. 1 We reverse the trial court’s order awarding an attorney fee to TEMCO.

TEMCO sued Herring-Malbis in May 2006, alleging that TEMCO was owed money “pursuant to the terms and conditions of’ contract documents signed by the parties, which included a construction contract and a standard American Institute of Architects contract, titled “AIA Document A201 — 1997” (“the AIA contract”), that was incorporated into the parties’ agreement by reference in the construction contract. TEMCO’s original complaint sought damages in the amount of $486,303 plus interest and costs under several alternative theories of relief, including breach of contract, open account, account stated, work and labor done, and enforcement of mechanic’s lien. Herring-Malbis moved for an order compelling alternative dispute resolution under the terms of the AIA contract, and the motion was granted by the circuit court. The circuit court, referring to TEMCO’s original complaint, ordered that “said claims are due to be referred to alternative dispute resolution.”

Pursuant to the AIA contract, the parties first attempted to resolve their dispute *162 through mediation, and when that failed, they arbitrated their dispute through the American Arbitration Association. The arbitration hearing was held on February 19 and 20, 2008. Six days before the commencement of the hearing, on February 13, 2008, TEMCO filed in the circuit court a motion to amend its original complaint. The motion averred that the purposes of amending the complaint were to incorporate “all of the claims and ... [d]e-fendant[s] which have been included in the mediation and arbitration process heretofore and which will be presented to the Arbitrator at the forthcoming arbitration hearing” and “to add a claim under the Prompt Payment Act ... for reasonable attorneys’ fees and expenses pursuant to said statute.” The motion further posited that the Prompt Payment Act claim “in no way affects the issues to be presented to the Arbitrator but[ ] rather is a matter to be presented to [the circuit cjourt in the event that the Arbitrator enters an award in favor of TEMCO.” No action was taken on the motion prior to the arbitration hearing.

In accordance with procedural rules of the American Arbitration Association, TEMCO then presented a demand letter, and Herring-Malbis presented an answering statement and counterclaim, to the arbitrator. In its demand letter, TEMCO itemized its claims for relief and included a request for accumulated interest, but it omitted mention of any claim for an award of an attorney fee and any mention of particular theories of relief, including any right to relief under the Prompt Payment Act. The demand letter did specify that TEMCO’s principal claim was that it was due relief under the construction contract.

After the hearing, the arbitrator rendered a decision that TEMCO was owed most of what it claimed. 2 The arbitrator also specified that each party would be responsible for its own attorney fees. The arbitration-award letter concluded by stating that “[a]ll claims not expressly granted herein are hereby[] denied,” thereby denying TEMCO its request for an award of accumulated interest on any of its claims. TEMCO and Herring-Malbis then filed briefs concerning whether the arbitrator’s award should be modified by deleting the reference to attorney fees and by awarding TEMCO the accumulated interest it sought. No changes to the award were made by the arbitrator. Herring-Malbis timely tendered payment to TEMCO in satisfaction of the arbitration award.

Then, in April 2008, after the arbitration hearing had been held, Herring-Malbis filed in the circuit court a response in opposition to TEMCO’s February 13 motion to amend its original complaint. The circuit court granted TEMCO’s motion to amend and overruled Herring-Malbis’s objections. TEMCO then filed its amended complaint in May 2008, after which Herring-Malbis moved to dismiss that com *163 plaint. The circuit court denied the latter motion, and, following a stipulation by the parties as to the amount of a reasonable attorney fee and a further agreement of the parties to allow the circuit court to rule on the matter -without a hearing, the circuit court entered an order awarding the stipulated attorney fee to TEMCO, “pursuant to the Prompt Payment Act,” in November 2008.

The amended complaint ultimately filed by TEMCO did not assert a separate claim requesting only attorney fees, pursuant to the Prompt Payment Act, in the manner that its motion to amend had suggested TEMCO had intended to do and in the manner that the circuit court’s order of November 2008 had purported to award. Rather, TEMCO asserted the Prompt Payment Act as another alternative legal theory under which TEMCO sought complete relief. Under Count 10 of the amended complaint, TEMCO incorporated the remainder of the complaint and demanded relief as to all of its claims against all defendants, which then totaled $561,412.70, specifically including interest, costs, expenses, and attorney fees.

In this case, the standard of appellate review is de novo. First, the pertinent facts are undisputed, see, e.g., Reynolds v. Colonial Bank, 874 So.2d 497, 501-02 (Ala.2003) (citing cases). Further, the circuit court received no testimony; instead, it based its judgment on pleadings, exhibits, briefs, and the stipulation of the parties, see, e.g., Tate v. Kennedy, 578 So.2d 1079, 1081 (Ala.1991).

At the outset of our analysis, we note that one pertinent issue — the nature and substance of the issues actually litigated before, and submitted to, the arbitrator for decision — is not readily amenable to appellate review because the appellate record contains no transcript of the two-day arbitration hearing nor any other evidence of what transpired at that hearing, and the circuit court did not review any such evidence. The demand letter written by TEMCO as a formality required by American Arbitration Association rules in order to initiate the arbitration process did not mention attorney fees or the Prompt Payment Act, but that omission does not conclusively establish that neither matter was discussed at the hearing. TEMCO asserts in its appellate brief that neither matter was discussed at the arbitration hearing, but its statements in its brief are not evidence that may be considered on appeal. R.P. Indus., Inc. v. S & M Equip. Co., 896 So.2d 460, 468 (Ala.2004) (citing Cooper v. Adams, 295 Ala. 58, 61, 322 So.2d 706, 708 (1975)).

Having noted the limitations of the appellate record, we turn to general principles of applicable law. Because arbitration is largely a matter of contract, the arbitrability of a particular dispute, such as a party’s entitlement to an attorney-fee award, is determined by the parties’ agreement as well as by the scope of the issues expressly submitted to the arbitrator. See Ex parte Messer, 797 So.2d 1079, 1084-85 (Ala.2001); Lee L. Saad Constr. Co. v. DPF Architects, P.C.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duerr v. Duerr
104 So. 3d 229 (Court of Civil Appeals of Alabama, 2012)
Mosley v. Builders South, Inc.
41 So. 3d 806 (Court of Civil Appeals of Alabama, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
37 So. 3d 158, 2009 Ala. Civ. App. LEXIS 537, 2009 WL 3517580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herring-malbis-i-llc-v-temco-inc-alacivapp-2009.