HERLITZ CONST. CO., INC. v. Matherne

476 So. 2d 1037
CourtLouisiana Court of Appeal
DecidedOctober 10, 1985
Docket84-612
StatusPublished
Cited by5 cases

This text of 476 So. 2d 1037 (HERLITZ CONST. CO., INC. v. Matherne) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HERLITZ CONST. CO., INC. v. Matherne, 476 So. 2d 1037 (La. Ct. App. 1985).

Opinion

476 So.2d 1037 (1985)

HERLITZ CONSTRUCTION CO., INC. (Hotel Investors of New Iberia—Assignee & Appellant), Plaintiff-Appellant,
v.
Gregory MATHERNE, et al., Defendant-Appellee.

No. 84-612.

Court of Appeal of Louisiana, Third Circuit.

October 10, 1985.

*1038 Marvin L. Jeffers, Baton Rouge, for plaintiff-appellant.

Deutsch, Kerrigan & Stiles, Frederick R. Bott, New Orleans, Breazeale, Sachse & Wilson, Henry D. Salassi, Baton Rouge, Roy, Forrest & Lopresto, Matthew J. Hill, New Iberia, for defendant-appellee.

Before STOKER, DOUCET and KNOLL, JJ.

KNOLL, Judge.

Herlitz Construction Co., Inc. (hereafter Herlitz), the assignee of Hotel Investors of New Iberia, Inc. (hereafter Hotel Investors), appeals the dismissal of its claim for damages against Gregory P. Matherne, AIA Architect, Inc. and Gregory P. Matherne (hereafter collectively referred to as Matherne), and Matherne's errors and omissions insurer, Insurance Company of North America. The trial court ruled that Hotel Investors, Herlitz's assignor, was contributorily negligent which was imputable to Herlitz.

Herlitz assigns for our review two specifications of error: (1) whether Hotel Investor's actions constituted contributory negligence sufficent to deny Herlitz recovery; and (2) if Hotel Investors was negligent, whether such contributory negligence was the proximate cause of its damages. We affirm.

FACTS

The present case, which is one of numerous lawsuits filed by Hotel Investors, was a lengthy trial. All controversies, other than this suit, have been disposed of by stipulated judgment, compromise, or otherwise. We have been favored by the learned trial judge's excellent reasons for judgment thoroughly setting forth the facts, which we incorporate herein:

"Hotel was interested in constructing a Ramada Inn in New Iberia similar to one constructed by Herlitz and financed by New Orleans [Federal] at Port Allen. Representatives of Hotel contacted Herlitz concerning this and Herlitz agreed to modify plans and specifications from Port Allen to fit the New Iberia site and situation and employed Matherne to do this work. Matherne performed these services employing Levy-Kraemer, mechanical engineer, to do that aspect of the work since it had done the mechanical work on the Port Allen project. All plans and specifications bore Matherne's seal, were furnished by him to Herlitz and Hotel, and showed in the legend of each that the work was done by Matherne for Herlitz.

"Hotel used these plans and specifications to obtain a permanent financing commitment from New Orleans [Federal] of $1,700,000.00 at 12% interest. The total commitment was later increased due to the addition of a `convention center' to the hotel project. Interim financing was obtained using the same plans from Louisiana National Bank. Construction contracts were entered into between Hotel and Herlitz and construction got under way in October of 1978.

"In early January, 1979, Herlitz's superintendent on the job site discovered a discrepancy between the architectural and electrical drawings on the one hand and the mechanical drawings on the other affecting numerous rooms. The drawings were transposed in relation to each other. He immediately called this to the attention of Herlitz and Matherne. Matherne instructed him to proceed according to the architectural drawings and not the mechanical which, had these instructions been acted upon, would have resulted in the plumbing subcontractor having to redo some plumbing work which had been `roughed in' in Building B prior to the pouring of the slab (which had not yet occurred) and to rebuild an unspecified amount of plumbing which had been prefabricated by it but not yet installed. Sometime later, Matherne changed his mind considering it would be best for all concerned to follow the mechanical plan and not the architectural and electrical plan and he so informed Herlitz's superintendent after discussing *1039 it with him. He then wrote Herlitz and Hotel advising of this decision.

"Matherne then revised the architectural plans to conform with the mechanical plan which resulted, among other things, in moving the entry door in a number of rooms from one side of the room to the other so that one entered the affected guest rooms at the side of the room near the head of the bed rather than near the foot of the bed as is the normal motel configuration. Hotel was advised by Matherne of the change in mid-January, 1979 through its representative Mr. Mancuso who was also advised by Matherne to obtain approval of the change from the permanent lender. This was not done.

"This change had no adverse effect upon the marketability of the affected rooms or the asthenic [sic] quality of the exterior of the hotel.

"Matherne considered the change minor. Ramada Inn executives were of the opinion the change was not significant.

"Although Matherne released all of the drawings from his office as his own work to the owner and contractor, he did not compare the mechanical and architectural plans to each other. Had he done so, he would have seen the discrepancy between them. It was his duty to supervise the work of the mechanical engineers and to be certain that their work did not conflict with the architectural plans. That is what architects in the area do.

"Had Herlitz or any of its employees experienced in dealing with building plans made a comparison of the architectural and mechanical drawings they too should have noted the discrepancy. It was in fact noted by Herlitz [sic] superintendent when he physically observed some plumbing work in the ground preparatory to pouring the slab in Building B. Something about it did not look proper and he then went and compared what was in place with the architectural drawing and noticed the transition [sic]. He then looked at the mechanical drawing and found that the plumbing in place was in accord with the mechanical drawing.

"Matherne's plans also called for the installation of a television cable conduit and outlet on a specified wall in each guest room. For reasons never fully explained, except for a letter from the electrical subcontractor to Herlitz stating that it did not `pickup TV outlets and conduits feeding them' Matherne concluded after construction was substantially completed that this conduit was not in place. In fact, it is and has always been in place in exact accordance with his plans and specifications. The purpose of the letter from the subcontractor to Herlitz was apparently to advise that this item had not been included by it in its bid.

"After discussion with the owner, contractor (who should have known the conduit was in place) and television cable company, Matherne determined that the television cable should be run through the telephone cable conduit on the opposite wall from whether [sic] it was intended to be, thence across the floor under the carpet to the proper wall. The television cable company required that its cable be protected where it crossed the floor by a rigid conduit. It was so installed resulting in a ridge in the carpet across the floor of each affected room. Matherne issued the necessary change order to accomplish this. Mr. DeBlanc, Hotel's Secretary-Treasurer, approved the change.

"The construction contract between Hotel and Herlitz was prepared by Matherne.

"Matherne was paid by Herlitz on a time basis out of funds paid by Louisiana National Bank, the interim lender, to Herlitz from the interim loan made by Louisiana National Bank to Hotel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daimlerchrysler Serv. v. Sec., Dep. of Rev.
970 So. 2d 616 (Louisiana Court of Appeal, 2007)
Cypress Oilfield Contr. v. McGoldrick Oil
525 So. 2d 1157 (Louisiana Court of Appeal, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
476 So. 2d 1037, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herlitz-const-co-inc-v-matherne-lactapp-1985.