Henslee v. Mobley

230 S.W. 17, 148 Ark. 181, 1921 Ark. LEXIS 54
CourtSupreme Court of Arkansas
DecidedApril 11, 1921
StatusPublished
Cited by13 cases

This text of 230 S.W. 17 (Henslee v. Mobley) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henslee v. Mobley, 230 S.W. 17, 148 Ark. 181, 1921 Ark. LEXIS 54 (Ark. 1921).

Opinions

McCulloch, C. J.

Cotton Plant Road Improvement District No. 1 of Woodruff County was organized for the purpose of improving a public road running west from the corporate limits of the town of Cotton Plant to the Prairie County line. The road was to be drained and graded and covered with a crushed rock base and then topped or surfaced with asphaltum in accordance with the plans and specifications prepared by the engineer of the district and approved by .the State Highway. Commission. ‘ ..........

Appellee, R. Mobley, entered into a contract with the improvement district in August, 1917, to construct the improvement on stipulated terms and prices, and in September, 1917, appellee entered into a subcontract with appellant for the latter to do the work of clearing and grubbing preparatory to the construction of the road, the removal of fences and other obstructions, the grading of the roadbed and hauling, spreading, filling and rolling of the crushed rock used as a base, thus preparing the road for the asphalt top. Appellant was also to haul and place the material for culverts. In other words, appellant contracted to do all the work of constructing the improvement in accordance with the plans and specifications except the work of laying the asphaltum top, which was to be done by appellee himself. The contract between appellant and appellee specified'the terms and prices, and that it was to be done in accordance with the contract of appellee with the improvement .district and under the directions and supervision of the engineer. The contract provided for monthly estimates of the work to be made by the supervising engineer, and payments to be made thereon, retaining fifteen per centum until the completion of the contract, in accordance with a similar provision in appellee’s contract with the improvement district. Appellant proceeded with the work shortly after the execution of the contract and pursued it until the following August when a controversy arose between the parties as to alleged defects in the work done by appellant. The work began at the corporate line of the town of Cotton Plant and proceeded westward by stations numbered from zero upward^ At the time appellant quit work he had completed his work on the road up to and including station 433 and the asphalt had been placed on the road up to and including station 111. The remainder of the work was thereafter completed by ap-pellee. Payments were made to appellant on the estimates, exclusive of the retained percentage, up to the estimate' made on August 6, 1918, for the July work which appellee refused to pay to appellant on the ground that Ms work was defective and not np to the standard specified in the contract. Appellee refused to pay the amount called for in this estimate unless appellant would go hack over the work and remedy the alleged defects. Appellant contended that he had done the work in accordance with the specifications, with the exception of certain minor matters which will he referred to later, and he refused to go back over the work for the purpose of bringing it up to the standard of the contract. His contention was then and is now that the defects in the roadbed were caused by delay of appellee himself in failing to follow up the work and put on the asphalt before the roadbed was worn away by traffic and bad weather. At this point of the controversy appellant did not quit work, but instituted the present action in the circuit court of Woodruff County against appellee to recover the amount due on the estimate for the July work and also for the retained percentage on the work for the months prior thereto. Appellant continued to work until some time in November, 1918, when, on account of lack of funds and the continued refusal of appellee to make payments until appellant should, pursuant to demand, go back over the work and remedy the alleged defects, he quit the job altogether, and the suit also embraced the claim of appellant for work done under the contract subsequent to July, 1918, as well as the amount alleged to be due prior to that time.

It was alleged in the complaint that appellee broke the contract by refusing, without justification, to make payments in accordance with the terms thereof. Appel-lee answered, denying that he had broken the contract, but alleged, on the contrary, that appellant committed the first breach by failing to do his work in accordance with the terms of the contract and in refusing on demand to go back over the work and remedy the defects. Appellee alleged that the defects were caused by the failure on the part of appellant to grade the road up to the height specified in the plans and by failing to lay sufficient rock for the base and to properly roll the same and by failure to cut the ditches as specified. He also alleged that it was the duty of appellant, under the contract, to go back over the work and grade up to the shoulders of the embankment. Appellee presented a counterclaim against appellant for the cost of curing the defects and also for the extra cost of completing the road after appellant quit work. Appellant alleged in his complaint that appellee was insolvent, and at the commencement of the action sued out a writ of garnishment and caused the same to be served on the improvement district.

James & Echols, a firm of merchants at Cotton Plant, filed an intervention in the cause against appellant asking for judgment against the latter in the sum of $1,-175.90 with interest, and interventions were also filed by the Standard Oil Company of Louisiana and the Southern Trust Company of Little Eock, asserting claims against appellee Mobley, and the last-named intervener set forth an assignment to it by appellee of the funds due by the improvement district.

The cause was transferred to the chancery court on motion of appellee, and without objection from any of the other parties. The cause proceeded to final decree in which the claim of appellant against appellee was adjudged in the sum of $7,983.92, 'but the court found that appellant had broken the contract, and that appellee was entitled to a set-off against said amount in the sum of $4,-931.62, leaving a balance due by appellee to appellant of the sum of $3,052.30, for which a personal decree was rendered in favor of appellant against appellee. The court also decreed in favor of James & Echols against appellant for the recovery of its account of $1,175.90, and also rendered decrees in favor of the other inter-veners against appellee. The court also directed the improvement district, as garnishee, to pay into court the sum due by the district to appellee under the contract, and decreed that appellant and said interveners share pro rata in accordance with the amount of their respective claims, in the distribution of said funds.

The court in its recital of the findings in the face of the decree listed the following items as constituting the credits to which appellee was entitled as a counterclaim against appellant’s debt, as follows:

For additional stone to bring up base up to even grade.$1,042.92

For completing grading and open ditches. 3,242.90

For excavation (John Rollers)... 407.92

For clearing and grubbing. 137.14

For fence moving. 89.94

For culverts. 10.80

Appellant Henslee is the only party who is prosecuting an appeal, and the correctness of the court’s finding as to the amount of his claim against appellee is not questioned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bank of America, N.A. v. JB Hanna, LLC
766 F.3d 841 (Eighth Circuit, 2014)
Dongary Holstein Leasing, Inc. v. Covington
732 S.W.2d 465 (Supreme Court of Arkansas, 1987)
TXO Production Corp. v. Page Farms, Inc.
698 S.W.2d 791 (Supreme Court of Arkansas, 1985)
Dierks Lumber & Coal Co. v. Horne
224 S.W.2d 540 (Supreme Court of Arkansas, 1949)
Ross, Disbursing Agent v. Rich
194 S.W.2d 297 (Supreme Court of Arkansas, 1946)
Bull v. Ziegler
54 S.W.2d 283 (Supreme Court of Arkansas, 1932)
Tolbert Bros. Co. v. Molinder
12 S.W.2d 780 (Supreme Court of Arkansas, 1929)
Ætna Casualty & Surety Co. v. Henslee
260 S.W. 414 (Supreme Court of Arkansas, 1924)
Newell Contracting Co. v. Elkins
257 S.W. 54 (Supreme Court of Arkansas, 1923)
C. A. Rees & Co. v. Pace
246 S.W. 491 (Supreme Court of Arkansas, 1923)
Road Improvement District No. 4 v. Southern Trust Co.
239 S.W. 8 (Supreme Court of Arkansas, 1922)
Cosby v. Hurst
231 S.W. 194 (Supreme Court of Arkansas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
230 S.W. 17, 148 Ark. 181, 1921 Ark. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henslee-v-mobley-ark-1921.