Henry v. Allegheny County

169 A.2d 874, 403 Pa. 272
CourtSupreme Court of Pennsylvania
DecidedApril 17, 1961
DocketAppeal, 90
StatusPublished
Cited by6 cases

This text of 169 A.2d 874 (Henry v. Allegheny County) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry v. Allegheny County, 169 A.2d 874, 403 Pa. 272 (Pa. 1961).

Opinion

Opinion by

Me. Chief Justice Jones,

The County of Allegheny appealed to the court below the viewers’ award of $14,560 in favor of the plaintiffs as damages for a taking by the county of the property of the plaintiffs for highway improvement. The county denied liability on the ground that the statute of limitations was a bar to the plaintiffs’ claim. The mattér was submitted to the court below on a case stated whereon the hearing judge, adopting the county’s contention, entered a compulsory nonsuit which the court en banc later refused to- take off. From the ensuing judgment in favor of the county, the plaintiffs have appealed, their right so to do having been reserved in the case stated.

The material facts, as set forth in the case stated, disclose that on October 26, 1925, the Court of Quarter Sessions of Allegheny County approved the report of a grand jury which authorized and established Bower Hill Road as a 60-foot right of way running through the townships of Mt. Lebanon, Upper St. Clair and Scott. The plan attached to the grand jury report, which was placed of record, showed the property of the plaintiffs’ predecessor in title as abutting on Bower Hill Road for a distance of 100 feet. The plan established center line elevations for the road, inter alia, opposite the easterly and westerly corners of the property here in question and approximately midway between the indicated easterly and westerly elevations. *275 The plan did not provide for any slope easement over or upon the property.

On October 19, 1926, the plaintiffs’ predecessor in title obtained a building permit for the erection of a dwelling house and garage on the property. The rough-in phase of the work of constructing the house and garage was completed by December 19, 1926. Pursuant to a contract let by the County of Allegheny on November 16, 1926, a paved cartway 18 feet wide was constructed in 1927 along the center line of the 60-foot right of way. In constructing the cartway, the contractor raised the center line elevations a number of feet higher than established by the recorded plan attached to the grand jury report approved by the Court of Quarter Sessions in 1925.

No petition for the appointment of viewers to assess damages for the taking was ever presented by plaintiffs’ predecessor in title.

On January 7, 1958, subsequent to the purchase of the property by the plaintiffs, the Commissioners of Allegheny County adopted a resolution providing for the relocation, widening, altering, opening to variable widths, improving and reconstructing of a portion of Bower Hill Boad. This resolution was approved by the Court of Quarter Sessions on January 22, 1958. Beferred to in the resolution and attached thereto was a condemnation plan showing an irregular slope easement of 550 square feet on the plaintiffs’ property abutting on the 60-foot right of way. Pursuant to this resolution the County widened the cartway of Bower Hill Boad from 18 to 44 feet and the Township of Mt. Lebanon entered upon the right of way and constructed sidewalks 7 feet in width together with curbs on either side of the paved roadway. The slope easement rwas utilized to support Bower Hill Boad as widened and improved.

*276 The property line elevations on Bower Hill Road -bounding the front of the plaintiffs’ property immediately following the widening and improvement of the highway in 1958 were approximately the same as the raised center line elevations adopted by the contractor in 1927, when the 18-foot cartway was constructed, and, consequently, were a number of feet higher than the elevations established by the recorded condemnation plan of 1925.

The floor of the plaintiffs’ garage, which, it will be recalled, was constructed in 1926, is at an elevation ;of approximately 8 feet below the grade of Bower Hill Road as constructed pursuant to the widening and improvement resolution of 1958. Prior thereto, access to Bower Hill Road from the garage was had by crossing the unimproved portion of the 60-foot right of way. However, such access is no longer available since the construction work of 1958.

The plaintiffs concede that any claim for damages resulting from the establishment of the 60-foot right of way, provided for in the condemnation plan of 1925, or that may have arisen from the construction of the 18-foot cartway in 1927 at elevations higher than were designated on the condemnation plan of 1925, is barred ■by the statute of limitations. What they do contend for is a right to damages due to the increased elevations above those shown on the plan of 1925 along a portion of the road outside of the previously improved 18-foot cartway and for the taking of 550 square feet of their property for slope easement necessary for the lateral support of Bower Hill Road as widened in 1958.

The court below, citing Strausz v. McKeesport, 316 Pa. 277, 175 Atl. 404 (1934), and Thomas v. Versailles Twp., 155 Pa. Superior Ct. 485, 38 A. 2d 396 (1944), held that the plaintiffs’ predecessor in title, after the grading in 1927 of the 18-foot cartway at elevations above those provided for by the condemnation plan ap *277 proved in 1925, was entitled to compensation for the grading of the entire 60 feet of right of way at the increased elevations and that the statute of limitations therefore bars the plaintiffs’ present claim. The court also held that the slope easement was compensable in 1927 and that the claim for damages therefor is likewise barred by the statute of limitations.

When there has been a taking of a landowner’s property by condemnation, he is entitled to a board of view for the assessment of his damage for the property so appropriated. A “taking” occurs when an entity clothed with the power of eminent domain condemns property in accordance with a statutorily authorized procedure or when such an empowered entity substantially deprives the owner of the beneficial use of his property. Griggs v. Allegheny County, 402 Pa. 411, 414, 168 A. 2d 123 (1961). In the instant case the change in the grade of Bower Hill Road from what the condemnation plan of 1925 provided for was not the subject of any statutorily authorized condemnation procedure until 1958; nor was the owner of the property in question substantially deprived of the beneficial use of his property .because of any change in the elevation of the portion of the 60-foot right of way lying outside of the 18-foot paved cartway, constructed in 1927, until such change was actually made pursuant to the resolution approved by the Court of Quarter Sessions of January 22, 1958. Consequently, no right to petition for the assessment of damages for the taking occasioned by the change in grade of the 60-foot right of way outside of the 18-foot paved cartway accrued to the abutting property owners until 1958.

Neither was the 550 square feet of the plaintiffs’ property which is now being used for the lateral support of Bower Hill Road the subject of a statutorily authorized condemnation proceeding until 1958, nor was the owner of the property substantially deprived *278 of the use thereof until the entry thereupon by the County in 1958. It follows, therefore, that no right existed in the owners to petition for the assessment of damages for the taking of the 550 square feet until 1958.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. Gentles v. City of Philadelphia
Commonwealth Court of Pennsylvania, 2019
Hauser v. Borough of Lehighton
39 Pa. D. & C.3d 347 (Carbon County Court of Common Pleas, 1985)
Pane v. Department of Highways
222 A.2d 913 (Supreme Court of Pennsylvania, 1966)
Commonwealth v. Spear
38 Pa. D. & C.2d 210 (Bucks County Court of Common Pleas, 1965)
Steeb v. Pennsylvania Turnpike Commission
188 A.2d 834 (Superior Court of Pennsylvania, 1963)
Rental of Condemned Property
28 Pa. D. & C.2d 684 (Pennsylvania Department of Justice, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
169 A.2d 874, 403 Pa. 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-v-allegheny-county-pa-1961.