Helmerich & Payne International Drilling Co. v. Swift Energy Co.

180 S.W.3d 635, 2005 WL 2548417
CourtCourt of Appeals of Texas
DecidedDecember 1, 2005
Docket14-04-00541-CV
StatusPublished
Cited by43 cases

This text of 180 S.W.3d 635 (Helmerich & Payne International Drilling Co. v. Swift Energy Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Helmerich & Payne International Drilling Co. v. Swift Energy Co., 180 S.W.3d 635, 2005 WL 2548417 (Tex. Ct. App. 2005).

Opinion

OPINION

KEM THOMPSON FROST, Justice.

This is a contract construction case arising out of a dispute between parties to a *637 drilling contract. The contractor argues that, under its unambiguous terms, the drilling contract allocates responsibility for the loss in question to the operator. The operator relies on a line of federal cases that seek to give effect to both indemnity provisions and covenants to name another party as an additional insured. Faced with cross-motions for summary judgment, the trial court ruled in favor of the operator and rendered summary judgment against the contractor on the operator’s breach-of-contract claim. We conclude that, even if Texas were to adopt the line of cases upon which the operator relies, these cases do not apply to the drilling contract in this case. Because the unambiguous language of the drilling contract allocates responsibility for this loss to the operator, we reverse the trial court’s judgment and render judgment granting the contractor the declaratory relief it sought in its petition and denying the operator recovery on its counterclaim. We also remand this case to the trial court for further proceedings regarding the contractor’s attorney’s fees request.

I. Factual and ProceduRal Background

The contractor, appellant Helmerich & Payne International Drilling Co. (“H & P”), and the operator, appellee Swift Energy Company (“Swift”), are parties to a Daywork Drilling Contract, dated July 27, 2000 (the “Drilling Contract”). The Drilling Contract initially covered the Kana # 1-H well in Fayette County, Texas. In December 2000, the parties agreed by letter that the terms and conditions of the Drilling Contract (with the exception of certain rates) would apply when H & P drilled the Post # 1 well in Goliad County, Texas. During H & P’s operations at the Post # 1 well, drilling fluids spilled into the surrounding field. Swift had this spill cleaned up, incurring $155,078.86 in total costs relating to the spill (“Costs”). The Drilling Contract requires H & P to maintain a Comprehensive General Liability (“CGL”) insurance policy that includes Swift as an additional insured. H & P maintained a CGL policy issued by American Home Assurance Company (the “CGL Policy”). Swift made a claim for the Costs as an additional insured under the CGL Policy. American Home responded to the claim by agreeing that Swift had additional-insured status under the CGL Policy; however, American Home concluded it owed nothing because the claim fell within the $750,000 deductible per occurrence for pollution claims under the CGL Policy.

H & P refused to reimburse Swift for the Costs. Instead, H & P filed this suit as a declaratory-judgment action to determine its rights and obligations under the Drilling Contract. In its petition, H & P seeks a judgment declaring that the Drilling Contract allocates responsibility for all claims and damages resulting from the flow or spill of drilling fluids in the incident in question to Swift, that the Drilling Contract precludes Swift from recovering the Costs, and that Swift must defend and indemnify H & P in any action to recover the Costs. H & P also sought its reasonable and necessary attorney’s fees under Chapters 87 and 38 of the Texas Civil Practice and Remedies Code.

Swift filed a counterclaim against H & P for breach of contract based on H & P’s alleged failure to honor its purported obligation to reimburse Swift for the Costs. Swift also sought declaratory relief in this regard, as well as reasonable and necessary attorney’s fees under Chapters 37 and 38 of the Texas Civil Practice and Remedies Code.

H <& P and Swift filed cross-motions for summary judgment. The trial court granted Swift’s motion and denied H & P’s motion. The trial court rendered a final *638 judgment awarding Swift actual damages of $154,193.86, plus attorney’s fees, court costs, and prejudgment and postjudgment interest. H & P now challenges that judgment and asks this court to reverse and render judgment granting H & P’s motion for summary judgment.

II.STANDARD OF REVIEW

A summary-judgment movant must establish its right to summary judgment by conclusively proving all elements of the movant’s claim or defense as a matter of law. See Tex.R. Civ. P. 166a(c); Havlen v. McDougall, 22 S.W.3d 343, 345 (Tex.2000). When both parties move for summary judgment, each party must carry its own burden, and neither can prevail because of the failure of the other to discharge its burden. 1 INAC Corp. v. Underwriters at Lloyd’s, 56 S.W.3d 242, 247 (Tex.App.-Houston [14th Dist.] 2001, no pet.). Because each party was a movant, the burden for each was the same: to establish entitlement to a summary judgment by conclusively proving all the elements of the claim or defense as a matter of law. Id. When both sides move for summary judgment and the trial court grants one motion and denies the other, the appellate court must review all summary-judgment evidence, determine all issues presented, and render the judgment that the trial court should have rendered. FM Props. Operating Co. v. City of Austin, 22 S.W.3d 868, 872 (Tex.2000). This court reviews the summary-judgment evidence using familiar standards of review. See Dolcefino v. Randolph, 19 S.W.3d 906, 916 (Tex.App.-Houston [14th Dist.] 2000, pet. denied).

III.Issue Presented

In a single issue on appeal, H & P asserts the trial court erred in granting Swift’s motion for summary judgment and in denying H & P’s motion for summary judgment. H & P asserts, among other things, that under the unambiguous language of paragraph 14 of the Drilling Contract, Swift assumed all responsibility for the Costs, agreed to release and indemnify H & P for the Costs, and agreed that the provisions of paragraph 14.11 would take precedence over the provisions of paragraph 13 to the extent of any conflict.

IV.Analysis

The parties’ arguments implicate several provisions of the Drilling Contract. The top of the first page of the Drilling Contract states, “THIS AGREEMENT CONTAINS PROVISIONS RELATING TO INDEMNITY, RELEASE OF LIABILITY, AND ALLOCATION OF RISK.” (emphasis in original). Paragraph 14 of the Drilling Contract contains the following relevant provisions:

RESPONSIBILITY FOR LOSS OR DAMAGE, INDEMNITY, RELEASE OF LIABILITY AND ALLOCATION OF RISK:
[[Image here]]
14.11 Pollution and Contamination: Notwithstanding anything to the contrary contained herein, except the provisions of Paragraphs 10 and 12, it is understood and agreed by and between *639 [H & P] and [Swift] that the responsibility for pollution and contamination shall be as follows:
(a) Unless otherwise provided herein, [H &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vermillion FC, LP v. 1776 Energy Partners
Court of Appeals of Texas, 2021
Abdullatif v. Ali Choudhri & Mokaram Latif W. Loop, Ltd.
561 S.W.3d 590 (Court of Appeals of Texas, 2018)
Fairfield Industries, Inc. v. EP Energy E&P Co.
531 S.W.3d 234 (Court of Appeals of Texas, 2017)
Queen v. RBG USA Inc.
495 S.W.3d 316 (Court of Appeals of Texas, 2016)
Garden Ridge, L.P. v. Clear Lake Center, L.P.
Court of Appeals of Texas, 2015
KIT Projects, LLC v. PLT Partnership
479 S.W.3d 519 (Court of Appeals of Texas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
180 S.W.3d 635, 2005 WL 2548417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helmerich-payne-international-drilling-co-v-swift-energy-co-texapp-2005.