Cleere Drilling Co. v. Dominion Exploration & Production, Inc.

351 F.3d 642, 158 Oil & Gas Rep. 933, 2003 U.S. App. LEXIS 23539, 2003 WL 22708133
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 18, 2003
Docket02-11124
StatusPublished
Cited by31 cases

This text of 351 F.3d 642 (Cleere Drilling Co. v. Dominion Exploration & Production, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleere Drilling Co. v. Dominion Exploration & Production, Inc., 351 F.3d 642, 158 Oil & Gas Rep. 933, 2003 U.S. App. LEXIS 23539, 2003 WL 22708133 (5th Cir. 2003).

Opinion

WIENER, Circuit Judge:

Cleere Drilling Company (“Cleere”) appeals the district court’s bench trial judgment, which rejected Cleere’s claims against Dominion Exploration & Production Inc. (“Dominion”) and held Cleere liable to Dominion for almost $2 million in damages. These damages resulted from the blowout of Kenaf Industries Unit No. 1 Well (the “Well”), which Cleere had contracted to drill for Dominion. Cleere contends that the district court misconstrued various provisions of the standard form International Association of Drilling Contractors (“IADC”) footage drilling contract, July 1998 revision, (the “Contract”), as revised by the parties and entered into by Cleere as contractor and Dominion as operator. Cleere also contends that the district court erred in various findings of fact. We affirm in part, reverse in part, vacate in part, and remand for further proceedings.

*644 I. Facts and Proceedings

This action arises from the blowout and resulting total loss of the Well. Central to the action are issues of responsibility for several categories of resulting losses and damages.

While drilling ahead at a depth of approximately 2500 feet en route to a “contract footage depth” of 3600 feet, the project got into trouble after Cleere’s toolpusher ordered a “short trip,” in which “stands” of drill pipe were pulled out of the hole and run back in to ensure the integrity of the pipe. In the course of this operation, Cleere’s driller “swabbed” the Well at least twice. 1 He completed the removal of the pipe despite observing an increase in the flow of drilling mud from the hole. When the driller realized that a potential well-control situation was developing, he had Cleere’s crew attempt to activate the blowout preventer. They failed to do so, however, because they did not first close a hydraulic bypass valve, a critical prerequisite to the preventer’s effective operation.

Cleere’s toolpusher, who had not been present, came to the drill site promptly after being called and was eventually able to activate the blowout preventer and shut down the Well. Cleere’s efforts to maintain control were ultimately unsuccessful, however, and the well cratered around its casing seven days after the initial loss of control. The Well eventually blew out through several surface fissures approximately 600 to 900 linear feet from the hole, spewing salt water, gas, sand, and chemically treated drilling mud on and around the drill site. As Cleere had neither the equipment nor the experience and expertise to control and kill the Well, Dominion retained the well-control firm of Boots & Coots to do so, at substantial cost to Dominion.

Cleere sued Dominion in state court, and Dominion removed the case to the district court based on diversity of citizenship. Cleere sought to recover for its services under the Contract for work performed both before and after the blowout. Specifically, Cleere sought $192,463, which included (1) $50,180 ($20 x 2,509 ft.) for the “value” of the hole that Cleere had drilled before it lost control of the Well; (2) $77,650 for 10 days and 2 hours “daywork” after it lost control; and (3) approximately $6,500 for other items, including 38 joints of drill pipe and 15 drill collars lost in the hole.

Dominion counterclaimed to recover costs and expenses totaling $1,955,596 comprising (1) $788,332 for controlling the blowout; (2) $861,615 for cleanup of the surface location, (3) $188,417 for restoration of the surface location; (4) $52,000 for settlement of damage claims with the landowner, Kenaf Industries of South Texas L.P. (“Kenaf’); and (5) $65,232 for the differential between Dominion’s cost of drilling a replacement well and the Well price under the Contract.

The district court conducted a bench trial, after which it ruled in favor of Dominion, awarding the entire amount sought and rejecting all of Cleere’s claims. Cleere timely filed a notice of appeal.

II. Analysis

A. Jurisdiction

The district court had jurisdiction by virtue of the diversity of citizenship provi *645 sions of 28 U.S.C. § 1332(a)(1) following Dominion’s removal of the case from the state court in which Cleere had originally filed it. We have appellate jurisdiction pursuant to 28 U.S.C. § 1291.

B. Standard of Review

We review the district court’s interpretation of the Contract de novo, as such an interpretation requires the determination of legal questions. 2 As the district court’s award of compensatory damages presents an issue of fact (absent an error of law), our review of this aspect of the judgment, like all other factual findings of the district court, is for clear error. 3

C. Cleere’s Claims

On appeal, Cleere does not contest the district court’s finding that Cleere’s negligence caused the blowout, so the particular facts surrounding the blowout itself are not at issue. Rather, Cleere views the case as one of contractual allocation of risk that turns primarily on the release and indemnity provisions of the Contract. Cleere maintains that the Contract allocates to Dominion responsibility for much of the damage, irrespective of whether Cleere was negligent or otherwise at fault. Cleere also insists that the district court misconstrued the Contract as a result of misapplying Texas law.

1. Recovery Based on Conversion of the Contract to “Daywork” Status

One important aspect of Cleere’s theory of recovery against Dominion is the contention that, by its own terms, the Contract automatically converted from a “footage” basis to a “daywork” basis. Conversion to daywork basis would mandate different contractual allocations of liability, possibly entitling Cleere to the damages it seeks related to the uncompensated-for work it performed both before and after the blowout occurred, as well as the value of its lost equipment and materials. Cleere argues that the district court erred in holding that, as a matter of law, such a conversion never occurred.

Cleere’s contention that the Contract converted to daywork status is premised on the factual assertion that Cleere encountered several problematic conditions while drilling the Well, including abnormal pressure, loss of circulation, and failure of operator-supplied equipment. The presence of any of these conditions would have converted the Contract to a daywork status and entitled Cleere to collect on its claims for breach of contract. The district court found that none of these conditions occurred, and Cleere’s arguments that they did are not persuasive. Cleere’s definition of “abnormal pressure” contradicts the express language of the Contract and depends entirely on testimony that is not related to the contractual provisions at issue, but to normal pressure in a strict engineering sense. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
351 F.3d 642, 158 Oil & Gas Rep. 933, 2003 U.S. App. LEXIS 23539, 2003 WL 22708133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleere-drilling-co-v-dominion-exploration-production-inc-ca5-2003.