ENSCO Offshore v. Cantium

CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 11, 2025
Docket24-30508
StatusUnpublished

This text of ENSCO Offshore v. Cantium (ENSCO Offshore v. Cantium) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ENSCO Offshore v. Cantium, (5th Cir. 2025).

Opinion

Case: 24-30508 Document: 67-1 Page: 1 Date Filed: 12/11/2025

United States Court of Appeals for the Fifth Circuit United States Court of Appeals ____________ Fifth Circuit

FILED No. 24-30508 December 11, 2025 ____________ Lyle W. Cayce Clerk ENSCO Offshore, L.L.C.,

Plaintiff—Appellee,

versus

Cantium, L.L.C.,

Defendant—Appellant. ______________________________

Appeal from the United States District Court for the Eastern District of Louisiana USDC No. 2:24-CV-371 ______________________________

Before Elrod, Chief Judge, Higginbotham, and Ramirez, Circuit Judges. Per Curiam: * In this breach of contract action, Cantium, LLC appeals the district court’s entry of summary judgment in favor of ENSCO Offshore, LLC, based on its finding that the parties mutually waived recovery of consequential damages, including for “gross negligence and/or willful misconduct,” in the contract. We AFFIRM.

_____________________ * This opinion is not designated for publication. See 5th Cir. R. 47.5. Case: 24-30508 Document: 67-1 Page: 2 Date Filed: 12/11/2025

No. 24-30508

I A In a Master Offshore Drilling Services Contract executed on May 9, 2022, ENSCO agreed to provide Cantium drilling services for its offshore oil and gas wells, including the Kings Hill well near the coast of Louisiana. ENSCO began work in November 2022. The operations were expected to take around 250 days but lasted 397 days. The contract required Cantium to pay ENSCO’s invoices for its services within thirty days of receipt. From November 2022 to July 2023, ENSCO sent Cantium monthly invoices, which it paid timely. Beginning in August 2023, however, Cantium failed to pay ENSCO’s invoices. In September 2023, the Kings Hill well was “lost,” 1 but ENSCO redrilled the well. Cantium did not pay any of ENSCO’s invoices for work performed between August 2023 and December 2023. On February 9, 2024, ENSCO sued Cantium for the unpaid invoices, asserting claims for breach of contract, quantum meruit, and promissory estoppel. Cantium counterclaimed for breach of contract and declaratory judgment, alleging that it was entitled to consequential damages due to ENSCO’s gross negligence and willful misconduct that caused delays. It sought over $22.8 million for the loss of the Kings Hill well, and over $4.5 million in other costs, including spread costs. B ENSCO moved for partial summary judgment on Cantium’s breach of contract claim, arguing that the parties had mutually waived all claims for consequential losses, including spread costs, in Section 15.21 of the drilling _____________________ 1 A well is “lost” when unexpected fluids cause it to lose integrity and collapse.

2 Case: 24-30508 Document: 67-1 Page: 3 Date Filed: 12/11/2025

contract. 2 It claimed that under Section 15.6, Cantium’s sole remedy for the lost Kings Hill well was redrilling. 3 Cantium responded that Section 15.21 did _____________________ 2 Section 15.21, in relevant part, states:

15.21. LIMITATION ON CLASSES OF DAMAGES. Operator and Contractor mutually waive and release, on behalf of themselves and their respective group, all of the following claims for damages arising out of this Contract, whether such claims are made in connection with an indemnity specified in this Section 15, a breach of any obligation under this Contract or any other claim: (A) Consequential loss under applicable law (whether direct or indirect) and all of the following (whether or not considered consequential loss under applicable law): (1) Lost profits. (2) Loss of production, including production of petroleum or petroleum products. (3) Loss of prospective economic advantage or benefit. (4) Loss of business opportunity. (5) Costs of persons hired by either party to provide vessels, materials, and services or work in support of the services, including those costs that are sometimes referred to as “spread costs[,]” but not including incremental costs incurred by Operator for the benefit of Contractor and at Contractor’s request, such as fuel or other logistical support that Operator is not explicitly required to provide under this Contract. 3 Section 15.6 states:

15.6. DAMAGE TO HOLE, STRATA, FORMATION OR RESERVOIR. Notwithstanding anything to the contrary in this Contract including Sections 15.2 and 15.4, if damage to, loss of, or impairment of any property right in or to the well, hole, strata, formation or reservoir, on which the services are being performed, Operator (A) releases Contractor Group from claims by Operator for that damage or loss, and (B) indemnifies Contractor Group against that damage or loss and against claims against any member of Contractor Group by any member of Operator Group for that damage or loss. This Section 15.5 does not,

3 Case: 24-30508 Document: 67-1 Page: 4 Date Filed: 12/11/2025

not apply due to ENSCO’s gross negligence or willful misconduct, citing Section 15.16. 4 The district court granted ENSCO’s motion and dismissed Cantium’s counterclaims. Cantium timely appealed. II We review the district court’s grant of summary judgment de novo. Earnest v. Palfinger Marine USA, Inc., 90 F.4th 804, 808 (5th Cir. 2024). Summary judgment is proper “if the movant shows there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Catalyst Strategic Advisors, L.L.C. v. Three Diamond Cap. Sbc, L.L.C., 93 F.4th 870, 874 (5th Cir. 2024) (quoting Fed. R. Civ. P. 56(a)). “Whether there is a plain meaning to a contract or whether an ambiguity exists is a legal question also subject to de novo interpretation.” In re Speedcast Int’l Ltd., 76 F.4th 372, 376 (5th Cir. 2023) (citation modified); see also Thibodeaux v. Vamos Oil & Gas Co., 487 F.3d 288, 293 (5th Cir. 2007).

_____________________ however, relieve Contractor from its obligation to redrill a well at the redrill rate as provided in Section 9.1(F) when such rate is applicable, which shall be Operator’s sole and exclusive remedy. 4 Section 15.16 states:

15.16. Notwithstanding anything to the contrary in this Agreement, Operator shall have no obligation under this Agreement to defend, protect, indemnify and hold harmless Contractor Group for any losses as a result of any member of Contractor Group senior supervisory personnel’s gross negligence and/or willful misconduct arising out of the performance or non-performance of any obligation and/or of services under this Contract or any Service Order.

4 Case: 24-30508 Document: 67-1 Page: 5 Date Filed: 12/11/2025

III Cantium argues that the district court erred because the waiver of damages in Sections 15.6 and 15.21 is subject to an exception in Section 15.16 for gross negligence or willful misconduct. We disagree. Because this appeal turns on interpreting a maritime contract, general contract principles from federal admiralty law apply. Barrios v. Centaur, L.L.C., 121 F.4th 515, 518 (5th Cir. 2024). We must discern the parties’ intent based on the language of the contract. East v. Premier, Inc., 98 F. App’x 317, 320 (5th Cir. 2004). The relevant provisions should be read as a whole, and words given their plain meaning, unless the contract is ambiguous. La. Land & Expl. Co. v. Offshore Tugs Inc., 23 F.3d 967, 969 (5th Cir. 1994); see also Foster Wheeler Energy Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East v. Premier, Inc.
98 F. App'x 317 (Fifth Circuit, 2004)
Foster Wheeler Energy Corp. v. an Ning Jiang MV
383 F.3d 349 (Fifth Circuit, 2004)
Thibodeaux v. Vamos Oil & Gas Co.
487 F.3d 288 (Fifth Circuit, 2007)
Breaux v. Halliburton Energy Services
562 F.3d 358 (Fifth Circuit, 2009)
Todd Shipyards Corp. v. Turbine Service, Inc.
467 F. Supp. 1257 (E.D. Louisiana, 1978)
Golden Spread Cooperative v. Emerson Process Manag
954 F.3d 804 (Fifth Circuit, 2020)
Royal Insurance Co. of America v. Southwest Marine
194 F.3d 1009 (Ninth Circuit, 1999)
Golden Spread Coop., Inc. v. Emerson Process Mgmt.
360 F. Supp. 3d 494 (N.D. Texas, 2019)
Coastal Iron Works, Inc. v. Geophysical
783 F.2d 577 (Fifth Circuit, 1986)
Inmarsat Global v. SpeedCast Intl
76 F.4th 372 (Fifth Circuit, 2023)
Palfinger Marine U S A v. Shell Oil
90 F.4th 804 (Fifth Circuit, 2024)
Catalyst Strategic v. Three Diamond
93 F.4th 870 (Fifth Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
ENSCO Offshore v. Cantium, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ensco-offshore-v-cantium-ca5-2025.