Hellman v. Farrelly

132 A.D. 151, 116 N.Y.S. 809, 1909 N.Y. App. Div. LEXIS 1454
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 7, 1909
StatusPublished
Cited by1 cases

This text of 132 A.D. 151 (Hellman v. Farrelly) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hellman v. Farrelly, 132 A.D. 151, 116 N.Y.S. 809, 1909 N.Y. App. Div. LEXIS 1454 (N.Y. Ct. App. 1909).

Opinion

Ingraham, J.:

Upon the first trial of this action the court dismissed tbe complaint upon tbe pleadings and upon tbe plaintiff’s opening. On appeal to this court the judgment entered upon such dismissal was reversed and a new trial ordered (Hellman v. City Trust, Safe Deposit & Surety Co., 111 App. Div. 876). We there held that: “In tbe circumstances disclosed it evidently appeared to be to tbe interest of tbe surety to have the provision with respect to reserving part of the amount earned waived, and likewise with respect to the time of performance; ” that “ having consented to these modifications at tbe instance of its principal, and tbe plaintiff having acted [152]*152thereon manifestly to his prejudice, if the consent and waiver were now to be repudiated, the defendant is estopped from contending that these modifications with respect to performance discharge it from all liability.” Upon the new trial before a referee judgment was awarded to the plaintiff. The referee found that on the 7th of December, 1898, the plaintiff entered into a contract in writing with one Blake, a copy of which is annexed to the amended complaint, and that by that contract Blake undertook to-excavate the rock upon certain real property for a price fixed which was based upon the estimated amount of rock to be excavated as 23,823 cubic yards and that the sum of one dollar and twenty cents per cubic yard was a proper sum to pay for such excavation, and that Blake as principal and the City Trust, Safe Deposit and Surety Company of Philadelphia as surety executed a bond conditioned Upon the performance of the conditions and covenants by Blake on bis part to be performed under said contract ; that the plaintiff made various payments to Blake as the work progressed; that from the inception of the work-performed under said contract by Blake, the said City Trust, Safe Deposit and Surety Company of Philadelphia knew that the sums periodically paid by the plaintiff to Blake were ascertained and computed by the plaintiff from the certificates of the engineer by multiplying the number of cubic yards specified in said certificates by the sum of one dollar and twenty cents and that such several certificates did not specify the amount earned by said Blake during the periods covered by them respectively in money, and that early in the progress of said work the said corporation specifically requested the said Heilman to continue making such payments to Blake for each cubic yard excavated and removed as shown by the certificates of the said surveyors-; that at the time of making such request the said corporation knew that there was a question whether the amount of material to be excavated had not been underestimated, and it made such request with the full knowledge that payments at that rate might result in the advancement to Blake for the time being of a larger proportion of the contract price than had actually been earned by him, hut in the belief that if such payments were made to the said Blake it might enable him to assemble the plant and employ the labor essential to the carrying out of such contract on Ms part; that, “the time of the performance of said contract on the part of Law[153]*153rence E. Blake, as provided by its terms, was with the full knowledge and approval and consent of the City Trust, Safe Deposit and Surety Company of Philadelphia, extended from time to time, and-at the request of the City Trust, Safe Deposit and Surety Company, and with the consent of this plaintiff, said Lawrence E. Blake was permitted to and requested to continue performance of said contract on his part for the benefit of all concerned, and did with the acquiescence, knowledge and consent of said company continue to perform the same until on or about the twelfth day of May, 1900.” . He further found that Blake, on or. about the 12th of May, 1900, wholly abandoned-performance of said contract and refused and neglected to proceed therewith and to supply a sufficiency of materials or workmen to complete the same and to continue its progress, and thereupon the City Trust, Safe Deposit and Surety Company and Blake were notified of said default by the plaintiff and of the plaintiff’s intention to complete the same; that the plaintiff then entered into a contract to complete the same, which was submitted for approval by the City Trust, Safe Deposit and Surety Company of Philadelphia before the work was done thereunder, and said work was completed pursuant to its terms without objection on the part of the said the City Trust, Safe Deposit and Surety Company of Philadelphia, and that the cost of that work under said contract was $38,844.76, or $10,344.76 in excess of the contract price, which is an amount in excess of the bond given by the defendant, winch was $10,000and, as a conclusion of law, that the plaintiff performed all the terms and conditions under said contract on his part to be done and performed, except in so far as performance of the conditions thereof was waived by the said the City Trust, Safe Deposit and Surety Company, and judgment was awarded to the plaintiff against the trust company for the sum of $10,000.

The opinion of the referee, I think, satisfactorily disposes of all the points raised by the defendant upon this appeal. It is a mistake to assume that ■ the liability of the defendant is based upon a . modification of the original contract between plaintiff and Blake. By the contract Blake undertook to do this work for the sum of $28,500. Tliis'contract was not based upon the amount of rock to be excavated. The bond given by the defendant was on condition [154]*154that Blake should duly and faithfully perforin and fulfill all conditions of said contract on his part to be kept and performed, and should keep harmless and protect the obligee (plaintiff) from and against all loss by reason of the non-fulfillment by Blake of the covenants contained in the said contract to be performed by him as aforesaid. The bond also contains a provision that; it is issued upon the express condition that all the covenants and agreements contained in the said contract made by the said obligee and on his part to be kept and performed for the protection of the said obligee and of said surety, should be strictly kept and performed by the said obligee. By the contract the plaintiff was required to make certain payments upon the certificate of the engineers as the work progressed, reserving fifteen per cent of the amount of each certificate until the work was .fully performed, which sum was to be paid to Blake when the certificate that the entire work was fully completed was submitted. If. the plaintiff had refused to pay the various sums that became due from time to time there would have been a breach of the contract which would have discharged, the surety. There is nothing in the contract to show that a payment in excess of the amount required to be paid to Blake was a breach of a covenant or agreement made by the plaintiff for his protection or for that of the surety, but if such covenant was within this provision of the bond, then payments made to Blake by the plaintiff at the express request of the surety and to enable Blake to carry out the contract would not discharge the surety. The plaintiff was justified in construing the contract and making the payments as requested by Blake and the surety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
132 A.D. 151, 116 N.Y.S. 809, 1909 N.Y. App. Div. LEXIS 1454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hellman-v-farrelly-nyappdiv-1909.