Hellbusch v. Rheinholdt

550 P.2d 1199, 275 Or. 307, 1976 Ore. LEXIS 792
CourtOregon Supreme Court
DecidedJune 17, 1976
StatusPublished
Cited by7 cases

This text of 550 P.2d 1199 (Hellbusch v. Rheinholdt) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hellbusch v. Rheinholdt, 550 P.2d 1199, 275 Or. 307, 1976 Ore. LEXIS 792 (Or. 1976).

Opinion

*309 BRYSON, J.

Plaintiff brought this suit to foreclose a mechanic’s lien on defendants’ dwelling for the balance due on the construction contract. Defendants appeal from a decree in favor of plaintiff. We review de novo.

In November, 1972, defendants contacted plaintiff regarding the construction of a home for them in Bend, Oregon. They had no plans or specifications. By March of 1973 defendants had a designer prepare the plans and elevation drawings but no specifications. In the latter part of May, 1973, defendants asked plaintiff "to get started on the foundation on a cost plus basis.” Defendants did not submit specifications for materials or fixtures and plaintiff could not submit a firm price. The parties did not execute a written contract, and none was prepared.

Plaintiff claims there was an oral contract to build on "cost plus.” Defendants claim there was an oral contract to build for a fixed price of $49,798.45. This price is based on plaintiff’s "Contractor’s Estimate Sheet” submitted to defendants so they could apply for a construction loan. Subsequently, plaintiff, at defendants’ request, prepared a form, "Description of Materials.” The estimate is itemized in a scanty manner on a printed form and obviously does not include all building items contemplated by the parties, and particularly defendants.

The Contractor’s Estimate Sheet, on which defendants claim a fixed contract price for construction, concludes as follows:

"TOTAL COST $49798.45
PROFIT -
COMPLETE BID -”

Neither the Contractor’s Estimate Sheet nor the description of materials form is signed by the parties.

*310 Plaintiff testified:

"A * * * We really never came to a full itemized spec list, specification sheet [description of materials].
its}: * * * *
"A * * * But he didn’t have it spec’d out. He didn’t have fixture numbers, he didn’t have carpet, he didn’t have all these items that I would need to know, what type of finished lumber goes into it, all these things that are hard to — hard to bid a house unless you have them.
"And since I did not have those, I continually — when he would bring me a new item that he wanted to add or a change in the house, and we work out a — an approximate cost of what this would be in addition to what we had originally been working with. And over a period of this two or three months, we — we just kept— the house kept growing. And I never did come to a final figure.”

As the house was built, defendants continued to make numerous minor and major changes. The defendants didn’t have the funds to pay plaintiff’s final billing and the lien was filed, based on an oral contract to build on a cost-plus basis, showing:

"Labor and Materials in construction of home $60686.85
Less payments made 42789.57
Costs: Preparation of Lien Notice 5.00
Balance Due Claimant: 17902.28”

This suit to foreclose followed.

The defendants contend the court erred "in formulating a cost plus contract between the parties.” The court’s letter opinion found:

"The principle [sic] bone of contention is whether this was a 'cost plus’ contract or a contract for a firm price of $50,000. The evidence satisfies the court that the parties contracted for construction on a 'cost plus’ basis. All the circumstances of their dealings are completely inconsistent with a firm price contract — e.g. lack of a written contract, no provision for change orders, defendant’s free access to plaintiff’s sub-contractors and defendant’s incursions into the day-to-day decisions of construction. *311 Further, defendant’s own admissions establish his understanding of the nature of the contract as being one of 'cost plus.’
"Although the parties did, in my view have a meeting of the minds as to the nature of the contract, they did leave an ambiguity by stating 'cost plus’ without further definition. * * * Although there was some discrepancy in the witnesses testimony as to what percentage 'plus’ was, in addition to cost, all the witnesses agreed inferentially, the percentage would be at least five percent — the approximate amount added to cost by the plaintiff.”

The plaintiff testified that his original understanding of the contract was cost plus 10 percent, which would have amounted to approximately $6,000. However, before the filing of the lien he reduced his claim to cost plus 5 percent, or a profit of $3,000, in order to reach a settlement with the defendants, when defendants’ loan would not cover the total construction cost of the dwelling as completed. Plaintiff testified:

"A And I chose at the final moments to get the thing settled up to drop my thing [cost-plus percentage] to $3,000.”

The ambiguity in the oral contract was the amount of percentage to be applied as "cost plus” in arriving at plaintiff’s profit. Certainly the parties did not contemplate that plaintiff would build the house for defendants at no profit. The evidence shows the defendants asked plaintiff to excavate and construct the foundation at "cost plus.” Mr. Betts, a subcontractor, and Mr. Kearns, who inspected the house, both testified that Mr. Rheinholdt told them that plaintiff was building the house for him on a cost plus basis. Defendants argue that the percentage of profit to be applied cannot be determined by custom and usage.

"Usage may be important in three different aspects:
"(1) To aid in the interpretation of the meaning of the express language of an agreement, or the meaning of the parties’ other manifestations of intention;
"(2) To annex terms to the agreement in accordance with the usage, provided they are consistent with the *312 express language or other manifestations of intention, though they may contradict or vary implications which otherwise would be drawn from the written or oral expression of the parties. * * *
"(3) To make inapplicable to an agreement rules of law otherwise applicable.” 5 Williston, Law of Contracts 1-4, § 648 (Jaeger 3d ed 1961). (Footnotes omitted.)
"The terms 'usage’ and 'custom’ are commonly used interchangeably, though there is a recognized distinction in the meaning of the two words. Usage is a fact and not opinion or rule of law. It may be defined as habitual or customary practice among a certain class of people, or in a trade, a neighborhood or a large geographical area. Thus, the courts have said that when a usage 'has become uniform in an actively commercial community, that should be warrant enough for supposing that it answers the needs of those who are dealing upon the faith of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VTech Communications, Inc. v. Robert Half, Inc.
77 P.3d 1154 (Court of Appeals of Oregon, 2003)
In Re Porter
890 P.2d 1377 (Oregon Supreme Court, 1995)
Parsons v. Henry
672 P.2d 717 (Court of Appeals of Oregon, 1983)
Brown v. D2S Resources, Inc.
656 P.2d 946 (Court of Appeals of Oregon, 1982)
Roelle v. Griffin
651 P.2d 147 (Court of Appeals of Oregon, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
550 P.2d 1199, 275 Or. 307, 1976 Ore. LEXIS 792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hellbusch-v-rheinholdt-or-1976.