Brown v. D2S Resources, Inc.

656 P.2d 946, 61 Or. App. 8, 1982 Ore. App. LEXIS 4262
CourtCourt of Appeals of Oregon
DecidedDecember 22, 1982
DocketA7911-05264, CA A22645
StatusPublished
Cited by6 cases

This text of 656 P.2d 946 (Brown v. D2S Resources, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. D2S Resources, Inc., 656 P.2d 946, 61 Or. App. 8, 1982 Ore. App. LEXIS 4262 (Or. Ct. App. 1982).

Opinion

*10 JOSEPH, C. J.

Brown sought to foreclose a construction lien on property owned by D2S Resources, Inc., (D2S) for the reasonable value of labor and material used in partially performing agreements to make certain improvements in a subdivision under development by D2S. 1 D2S asserted several affirmative defenses and counterclaimed for damages for the cost of repairing Brown’s allegedly defective work. The trial court dismissed the counterclaims, entered judgment for Brown and ordered the lien foreclosed. D2S appeals.

In March, 1979, Brown contracted with D2S to install sanitary and storm sewers and a water system in a new residential subdivision in Gresham. The contract price for the installation of the sanitary sewer system was $38,905.50, for the installation of the storm sewer, $21,933, and for the water system improvements, $12,639.50. While that work was underway, Brown agreed to construct streets in the subdivision for $59,406.60. Payment under each contract was to be for “Monthly progress by the tenth of the month progressive.” All work was to be done in accordance with D2S’ plans and specifications and was to have the approval of the city and the local water district.

Brown began work on March 3, 1979. On March 23, 1979, he billed D2S for:

“Sanitary sewer 90% complete $35,014.95
Storm sewer 50% complete 10,966.50
$45,981.45”

That bill was paid in full in April, 1979. Before completion of the sewer and water systems, Brown began back-filling the excavations for the project. The reason for doing that was disputed at trial. Brown testified that he covered the work at the request of D2S’ president, who had told him that the company did not have the money to pay Brown for the work that he had done and that having the project in a *11 “good-looking position” would facilitate further financing. At trial, D2S’ president did not recall making the request.

On June 22, 1979, Brown billed D2S again:

“Street const. Item # 6 90% complete $ 7,200.00
“ “ “ # 1 150 yards 1.575.00
Water system 80% complete 10.111.50
Storm sewer system 95% complete 20,836.35
Sanitary sewer 95% complete 36.905.50
Temporary road rock * * * 9.375.00
$86,003.35
Less [previously paid invoice] 45.981.45
$40,021.90”

Brown testified that he did not return to work on the project after June 22, 1979, because he had not been paid for the work that he had done. He filed a lien in July, 1979, and an amended lien in August, 1979, giving D2S credit for a $5,000 payment made in July. He began suit to foreclose the lien on November 2, 1979.

In September, 1979, D2S decided to complete the project itself. It discovered that much of the work it had assumed that Brown had done on the sewer and water lines had not in fact been done. D2S met with Brown in December, 1979, and he then agreed to complete the sanitary sewer system for $2,000 and to complete a manhole for $700. He also agreed to give D2S a $5,000 “credit” because of the installation of two sewer lines at an improper grade.

Brown started to correct the grade defects and to complete the sewers in January, 1980, but quit because of bad weather. 2 D2S completed the project that winter, despite increased costs due to wet weather, because “[i]t was definitely cheaper to finish the job at that time than to wait until the summertime and waste 12 or $15,000 of interest.” Costs to complete were also increased, because D2S had to re-excavate to locate the areas where the work was incomplete. D2S, however, did not first attempt to ascertain from Brown what work needed to be done. In March, 1980, D2S paid Brown $1,200 from the proceeds of a lot sale.

*12 On April 29, 1980, Brown filed an amended complaint for $28,821.90, alleged to be the reasonable value of labor and materials used in the sewer and water projects. That amount did not include the $5,000 “credited” to D2S. D2S’ affirmative defenses alleged that Brown had breached the contracts by failing to complete the projects in accordance with the plans and specifications or in a workmanlike manner. The counterclaims for damages for the cost of repairing the work improperly done totalled $56,531.91. The trial court dismissed the counterclaims, awarded Brown a $26,719.83 judgment and decreed foreclosure of the lien.

In its first assignment of error, D2S argues that the trial court erred in granting judgment in Brown’s favor, because the evidence was legally insufficient to support the judgment. It claims, in essence, that there was no proof as to the reasonableness of the charges for labor and material used by Brown. However, D2S did not raise that issue at trial. If a party in a civil case, whether in law or equity, has not asserted the legal insufficiency of the evidence in the trial court, he may not do so on appeal. Falk v. Amsberry, 290 Or 839, 626 P2d 362 (1981); Baldwin v. Miller, 44 Or App 371, 606 P2d 629, rev den 289 Or 45 (1980); but see ORS 19.125(3).

In its second assignment, D2S argues that the trial court erred in “failing to find that Brown had breached his agreements and in not granting judgment in favor of D2S on its counterclaim.” However, D2S’ position at trial was that there was no issue of breach of contract on Brown’s part for having left the project and that the decisive issue was whether Brown’s work was defective. Moreover, even if Brown had breached, that would not preclude recovery in quantum meruit. A breaching party may recover the reasonable value of his work to the extent that it has benefited the non-breaching party, who may of course counterclaim for any damages suffered as a result of the breach. Welch v. Webb, 47 Or App 771, 615 P2d 391 (1980). The basic issue is whether D2S is entitled to damages for the cost of repair. The counterclaims for damages are actions at law, and we review them accordingly. McClory v. Gay, 45 Or App 561, 608 P2d 1213 (1980); ORS 87.070(2); ORCP 2.

*13 Neither party disputes the fact that Brown’s work did not conform to the plans and specifications insofar as certain things were not done that were shown on the plans to be done. Several lines, manholes and “T” joints were not installed, lines were not grouted and channeled, several sewer lines did not meet catch-basins and some manholes were not adjusted to the proper height. The nature of the work done by D2S after Brown had left the project, however, was disputed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peiffer v. Hoyt
63 P.3d 1273 (Court of Appeals of Oregon, 2003)
Ying Loi Ho v. Presbyterian Church of Laurelhurst
840 P.2d 1340 (Court of Appeals of Oregon, 1992)
Millsap v. Eugene Care Center, Inc.
682 P.2d 795 (Court of Appeals of Oregon, 1984)
Falcon Holdings, Ltd. v. Isaacson
675 P.2d 501 (Court of Appeals of Oregon, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
656 P.2d 946, 61 Or. App. 8, 1982 Ore. App. LEXIS 4262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-d2s-resources-inc-orctapp-1982.