Heiskell v. H. C. Enterprise, Inc.

429 S.W.2d 71, 244 Ark. 857, 1968 Ark. LEXIS 1433
CourtSupreme Court of Arkansas
DecidedMay 13, 1968
Docket5-4478
StatusPublished
Cited by4 cases

This text of 429 S.W.2d 71 (Heiskell v. H. C. Enterprise, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heiskell v. H. C. Enterprise, Inc., 429 S.W.2d 71, 244 Ark. 857, 1968 Ark. LEXIS 1433 (Ark. 1968).

Opinions

J. Free Jones, Justice.

This appeal is from a judgment of the Pulaski County Circuit Court and arises from litigation growing out of the construction of the Little Rock Public Library building because of defect in tbe construction of concrete floors. H. C. Enterprise, Inc. was the general contractor for the construction of the building; J. N. Heiskell et al, constituted the Library Board of Trustees, and Guy Swaim and James C. Well-boim, d/b/a Swaim, Allen, Wellborn '& Associates, were the architects for the building.

In order to permit work on the various levels of the building to proceed without damage to finished floors, the plans and specifications prepared by the Architects called for the concrete floors to be poured in two separate slabs or layers. The base slab, containing coarse aggregate, was to be poured in forms and was to be from four to five inches thick. The base slab was designed to have poured on top of it the second layer, containing fine aggregate, and to be one and one-half inches thick. These two slabs or layers will hereafter be referred to as “base slab” and “fill slab.” The fill slab is designated “fill or mortar setting bed” in the specifications, and was to receive a vinyl tile finish floor covering. The defect giving rise to this litigation occurred between the two slabs of concrete.

The base slab was first poured by the Contractor and about 18 months later the fill slab was poured. After both slabs were poured, the fill slab started cracking and separating from the base slab and it was found that the fill slab had not bonded with, or adhered to, the base slab, and it became necessary to remove and replace the fill slab. An intensive investigation was conducted to determine the cause of the difficulty, which included reports by several testing laboratories employed by various parties.

Finally, in August of 1962, the Architects gave specific written instructions to the Contractor describing the manner of removal and replacement of the fill slab in the affected area. The Contractor replied in October of 1962, that a record of all labor, material and equipment costs was being kept on a time and material basis and as the original base slab and fill slab were installed in a workmanlike manner, this constituted a change in the work and requested a written change order under the contract. The Architects responded in November 1962, that in light of the laboratory testing reports, they felt the obligation of replacing the fill was on the Contractor and refused to issue a change order, requesting that the Contractor proceed under Article 19 of the contract whereby the Contractor must replace all work condemned as not in conformance with the contract, and that if this was not proceeded with immediately, an appeal would be made to the Contractor’s bonding company.

The Contractor proceeded with replacement of the fill without further correspondence until August 1965, at which time he requested and was refused payment for the work by the Architects.

Since the litigation involved the pouring and finishing of the two slabs, the specifications pertaining to them are fully set out as follows:

“Interior Slabs to Heceive Fill or Mortar Setting Bed shall be finished by tamping the concrete with special tools to force the coarse aggregate away from the surface, and screeding with straight edges to bring the surface to the required finish plane.
“Interior Slabs — that are to receive a finish floor covering (this -does not include ceramic tile covering) shall be finished by tamping the concrete with special tools to force the coarse aggregate away from the surface, then screeding and floating with straight edges to bring the surface to the required finish level. While the concrete is still green but sufficiently hardened to bear a man’s weight without deep imprint, it shall be wood floated to a true and even plane with no coarse aggregate visible. Sufficient pressure shall be used on the wood floats to bring moisture to the surface. After the surface moisture has disappeared, surfaces shall he steel-trowelled to a smooth, even impervious finish, free from trowel marks. After the cement has set enough to ring the trowel the surface of all slabs shall he given a second steel trowelling to a burnished finish. Where fill is applied and will receive a floor covering (not ceramic tile) fill shall be finished smooth in like manner.”

On January 14, 1966, the Contractor requested arbitration of its right to compensation under the contract, and the Library Board denied the request. The Contractor then brought suit against the directors for the additional cost of labor and materials in taking up and replacing the fill slab and the Architects were made third parties defendant.

Appellants argue that the plans and specifications called for a bonding of the two slabs by implication, and that the failure to secure a bond was the result of improper workmanship and failure of the Contractor to follow the plans and specifications. Appellee contends that the plans and specifications do not call for a bond and that the plans and specifications were followed explicitly in a good workmanship manner. All the parties seem to recognize that the trouble arose from the failure of the two slabs of concrete to bond with each other; that this resulted in the cracking of the fill slab and that it was necessary to remove and replace the fill slab. The Architects contended that the Contractor was negligent in pouring, curing, and finishing the concrete, and the Contractor contended that he poured, cured, and finished the concrete according to the plans and specifications prepared by the Architects and under the visual observation of the Architects. It was the Contractor’s contention that the fault lay in the plans and specifications prepared by the Architects and in the direct instructions of the Architects during the course of construction.

A jury trial resulted in a judgment in favor of the 'Contractor against the Trustees for $50,201.50 with judgment over in favor of the Trustees against the architects for the same amount.

The Architects and the Trustees are joint appellants here and they rely on the following points for reversal:

“Under the terms of the contract, the contractor cannot recover against the owner.
There is no competent evidence that the plans and specifications were deficient in any manner.
The undisputed evidence shows that the original work was not performed by the contractor in accordance with the plans and specifications.
The contractor is estopped to claim compensation and has waived any claim.
The Court erred in refusing to declare a mistrial when insurance was improperly brought to the attention of the jury.
The Court erred in admitting certain exhibits and testimony concerning change orders.”

As to point one, it is not disputed that the contract provides for changes in the work to be approved in writing prior to their execution. Appellee admits that this provision was not complied with, but argues that strict compliance with this provision was waived by appellants through course of conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodward v. Blythe
462 S.W.2d 205 (Supreme Court of Arkansas, 1971)
Heiskell v. H. C. Enterprise, Inc.
429 S.W.2d 71 (Supreme Court of Arkansas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
429 S.W.2d 71, 244 Ark. 857, 1968 Ark. LEXIS 1433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heiskell-v-h-c-enterprise-inc-ark-1968.