Heidtman Steel Products, Inc. v. Faurecia Automotive Seating, Inc.

919 F. Supp. 2d 928, 2013 WL 358171, 2013 U.S. Dist. LEXIS 12970
CourtDistrict Court, N.D. Ohio
DecidedJanuary 2, 2013
DocketCase No. 3:10CV575
StatusPublished
Cited by1 cases

This text of 919 F. Supp. 2d 928 (Heidtman Steel Products, Inc. v. Faurecia Automotive Seating, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heidtman Steel Products, Inc. v. Faurecia Automotive Seating, Inc., 919 F. Supp. 2d 928, 2013 WL 358171, 2013 U.S. Dist. LEXIS 12970 (N.D. Ohio 2013).

Opinion

ORDER

JAMES G. CARR, Senior District Judge.

This is a breach of contract case in which plaintiff/counter-defendant, Heidtman Steel Products, Inc. (Heidtman), claims defendant/counter-plaintiff, Faurecia Automotive Seating, Inc. (Faurecia), failed to pay money due under the parties’ contract. Faurecia counterclaimed, alleging Heidtman also breached the contract and that it is entitled to an appropriate setoff.

Pending is Heidtman’s motion to dismiss Faurecia’s counterclaims (Doc. 70). For the reasons that follow, I deny the motion.

Jurisdiction exists under 28 U.S.C. § 1332.

Background

Heidtman obtained cold and hot rolled steel from steel plants and sold it to third parties, whom the parties denominate as “stampers.” Under separate contracts between the stampers and Faurecia, the stampers fabricated the steel into parts which Faurecia incorporated in car seats which Faurecia, in turn, provided to General Motors, Ford, and Chrysler.

The contract at issue in this case between Heidtman and Faurecia required Heidtman to sell steel to the stampers at a fixed price from April 1, 2009, to December 31, 2009. However, because steel prices often fluctuate significantly in short time periods, Heidtman and Faurecia agreed to correct for the difference in the contract’s fixed price for the stampers and the actual price Heidtman had to pay for steel during the contract’s duration. If Heidtman paid less for the steel than the fixed price, it would pay Faurecia the difference. If Heidtman paid more, Faurecia would pay Heidtman the difference.1 The parties called these payments “true-ups.”

The contract provided Heidtman, Faurecia, and the stampers with protection from steel-price market fluctuations. By entering into the contract, Heidtman would avoid losing money if steel pnces increased, and, vice versa, Faurecia avoided [930]*930overpaying if prices decreased. Although the stampers were not parties to the contract, it also benefitted them. With it in place, the stampers knew they would pay Heidtman a fixed price for steel and would resell their product to Faurecia at a fixed price. They also knew they had a reliable supplier of steel so they could meet Faurecia’s need to meet its production timetable with the auto manufacturers. Thus, the contract facilitated the manufacturing process by allowing the parties and stampers to realize profits independent on the steel market.2

Heidtman delivered steel to the stampers from April to August, 2009. In September and October, however, Heidtman failed to make its shipments. It resumed delivery, and made timely steel shipments to the stampers in November and December, 2009.

Heidtman sued, alleging Faurecia failed to pay true-ups for November and December. Faurecia acknowledged it did not pay Heidtman $142,817 in true-ups. However, Faurecia filed a counterclaim alleging that Heidtman failed to provide steel to the stampers in September and October, and the damages from Heidtman’s breach of contract-offset Faurecia’s unpaid true-ups.

Heidtman filed a motion for summary judgment arguing that, because Faurecia admitted it did not pay the true-ups, no issues remained and it was entitled to judgment on that claim. I denied the motion without prejudice in recognition that Heidtman may be liable to Faurecia for failing to deliver steel in September and October. (Doc. 69, p. 6).

Heidtman also sought summary judgment on Faurecia’s counterclaim, which alleged Heidtman failed to deliver the steel to the stampers. Heidtman argued the contract fell outside Article 2 of the Uniform Commercial Code, and, thus, Faurecia could not recover damages for the increased cost of replacement steel and parts Faurecia bought from other suppliers after Heidtman’s non-delivery. Heidtman also argued that, because Article 2 does not apply, Faurecia retains no further remedies under the contract. (Doc. 69, p. 6).

I held that Article 2 does not apply to the parties’ contract because Faurecia merely served as a facilitator of the Heidtman-stampers contracts for the sale of goods. I therefore rejected Heidtman’s Article 2 defenses. I suggested, without deciding, that Faurecia may retain common law remedies and Heidtman common law defenses.3

Heidtman filed this motion to dismiss, arguing Faurecia retains no remedies under the contract and has therefore failed to state a claim entitling it to relief. (Doc. 70).

Standard of Review

A claim survives a motion to dismiss under Fed.R.Civ.P. 12(b)(6) if it “contain[s] [931]*931sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009). “The plausibility standard is not akin to a ‘probability requirement,’ but it asks for more than a sheer possibility that a defendant has acted unlawfully.” Id. A complaint’s “[fjactual allegations must be enough to raise a right to relief above the speculative level, on the assumption that all of the complaint’s allegations are true.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555-556, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007).

A complaint is insufficient “if it tenders naked assertions devoid of further factual enhancement.” Iqbal, supra, 556 U.S. at 678, 129 S.Ct. 1937 (citing Twombly, supra, 550 U.S. at 557, 127 S.Ct. 1955) (internal quotation omitted).

I must “construe the complaint in the light most favorable to the plaintiff.” Inge v. Rock Fin. Corp., 281 F.3d 613, 619 (6th Cir.2002). A plaintiff, however, must provide “more than labels and . conclusions, and a formulaic' recitation of the elements of a cause of action will not do.” Twombly, supra, 550 U.S. at 555, 127 S.Ct. 1955; see also Iqbal, supra, 556 U.S. at 678, 129 S.Ct. 1937 (“Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice.”).

Discussion

I first address Heidtman’s argument that Article 2 of the Uniform Commercial Code precludes Faurecia’s common law remedies as a matter of law. I conclude that it does not. I then examine the language of the parties’ contract to determine whether it unambiguously restricts Faurecia’s remedy to termination of the contract. I conclude that the contract is ambiguous: reasonably read, it could be interpreted as allowing Faurecia to recover remedies for its additional costs in obtaining replacement steel under the contract; it could also be read to preclude such recovery. Because the contract is ambiguous, its interpretation presents a question of fact. Faurecia has, therefore, pled a plausible claim for relief under the contract, and I deny Heidtman’s motion to dismiss.

1. Faurecia’s Potential Remedies

Heidtman argues that, although Article 2 does not apply to the parties’ contract, Faurecia may only seek remedies under the UCC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
919 F. Supp. 2d 928, 2013 WL 358171, 2013 U.S. Dist. LEXIS 12970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heidtman-steel-products-inc-v-faurecia-automotive-seating-inc-ohnd-2013.