Hecate Energy Greene County 3 LLC v. FERC

72 F.4th 1307
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 7, 2023
Docket21-1192
StatusPublished
Cited by2 cases

This text of 72 F.4th 1307 (Hecate Energy Greene County 3 LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Submitted October 18, 2022 Decided July 7, 2023

No. 21-1192

HECATE ENERGY GREENE COUNTY 3 LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC., INTERVENOR

Consolidated with 21-1274

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

William M. Rappolt and Mark F. Sundback were on the briefs for petitioner.

Matthew R. Christiansen, General Counsel, Federal En- ergy Regulatory Commission, Robert H. Solomon, Solicitor, and Matthew W.S. Estes, Attorney, were on the brief for re- spondent. 2

C. Dixon Wallace III, John Lee Shepherd, Jr., Ted J. Mur- phy, and Brian M. Zimmet were on the brief for intervenor New York Independent System Operator, Inc. in support of respond- ent.

Before: MILLETT, WALKER and CHILDS, Circuit Judges.

Opinion for the Court filed by Circuit Judge WALKER.

WALKER, Circuit Judge: Because electricity-transmission grids are expensive and difficult to build, grid operators can be natural monopolists. To ensure that consumers do not pay mo- nopoly prices, Congress requires transmission operators to charge reasonable rates. And tariffs containing those rates must be filed with the Federal Energy Regulatory Commission before they are levied on generators.

Here, a generator, Hecate Energy, accuses a transmission- grid operator, the New York Independent System Operator, of charging a rate that it had not filed with FERC. Hecate com- plains that the System Operator’s filed tariff was not detailed enough. So it says it was surprised when the System Operator charged it $10 million in grid-upgrade costs to connect its power plant to the grid. 1

FERC rejected that argument, finding that the tariff put Hecate on notice. Unsatisfied, Hecate petitioned this court for judicial review. Because we agree with FERC that the System

1 Curious readers might wonder how “Hecate” is pronounced. It’s “HEK-a-tee,” like the Greek goddess of magic, not “HEK-ut,” like the ruler of the witches in Shakespeare’s Macbeth. 3 Operator’s tariff had enough detail to fairly inform Hecate, we deny Hecate’s petitions for review. 2

I

A

To supply power to consumers, electricity generators (like Hecate) must connect to the transmission grid. Transmission- grid operators set the terms under which generators connect to the grid. Those terms are contained in a document called a tar- iff.

But transmission operators do not have a free hand in set- ting the terms in the tariff. Under the Federal Power Act, “[a]ll rates and charges” and “all rules and regulations affecting . . . such rates” must be “just and reasonable.” 16 U.S.C. § 824d(a). Plus, transmission operators must “file . . . all rates and charges” with FERC. Id. § 824d(c). Because the terms for connecting to the grid are “rules . . . affecting . . . such rates,” they must be filed. Id. § 824d(a).

This case concerns the scope of that requirement. How detailed must the tariff be?

2 Hecate filed two petitions for review in this court. It filed the first petition after FERC did not act on its rehearing request within thirty days. See 16 U.S.C. § 825l(a) (rehearing request is “deemed to have been denied” if FERC does not act on it “within thirty days”). It filed the second petition after FERC eventually addressed Hecate’s re- hearing arguments. We address both petitions here. 4 B

Hecate is a power-plant developer. It plans to build a solar facility in New York. To sell electricity, it must connect its facility to New York’s interstate-transmission grid.

That grid is managed by the System Operator. The System Operator is “an independent regional transmission organization that operates, but does not own, the power transmission system in New York state.” 3 New York Regional Interconnect, Inc. v. FERC, 634 F.3d 581, 583 (D.C. Cir. 2011).

Following rules set out in a tariff filed with FERC, the Sys- tem Operator processes generators’ grid-connection requests. It first assigns a queue position to each request. Then it con- ducts an “interconnection study” to determine the impact the connection will have on the grid. If the proposed connection requires grid upgrades, the owner of the new connection must pay for them. If it refuses, it cannot connect to the grid.

In line with that process, the System Operator gave Hecate a queue position and performed an interconnection study for Hecate’s solar facility. To figure out Hecate’s impact on the grid, the System Operator first developed a “base case” — that is, a model of the expected strain on the grid without the power from Hecate’s facility. The base case reflects information about existing and planned connections to the grid.

The base case includes information about so-called “non- jurisdictional projects.” Nonjurisdictional projects are small,

3 Agreements between New York’s transmission owners and the Sys- tem Operator empower it to operate the transmission grid. See Cen- tral Hudson Gas & Electric Corp., 83 FERC ¶ 61,352, at 62,405, 62,413 (1998) (describing that relationship). 5 local electricity generators, not subject to FERC’s jurisdiction. See 16 U.S.C. § 824(b)(1). They connect to the grid following different rules, often set by the transmission-grid owner — here, Central Hudson. 4

For Hecate’s interconnection study, the System Operator included six nonjurisdictional projects in its base case. Includ- ing those projects meant that Hecate’s connection was pro- jected to require grid upgrades. So the System Operator found that Hecate was required to pay $10 million in upgrade costs.

C

Unwilling to pay, Hecate challenged the System Opera- tor’s decision before FERC. Hecate argued that the System Operator’s tariff did not give Hecate notice that the six nonju- risdictional projects would be included in its interconnection study.

Hecate contended that the tariff should have included in- formation about Central Hudson’s practices for reporting non- jurisdictional projects to the System Operator. Under its “in- clusion rule,” Central Hudson reports projects when they are “firm.” JA 28-29. Central Hudson views a project as “firm” once its owner has signed an interconnection agreement and paid at least twenty-five percent of its costs. Hecate claimed that under the Federal Power Act, that rule is a “practice[ ] . . .

4 FERC may regulate only interstate electricity transmission. With some exceptions, it does “not have jurisdiction . . . over facilities used in local distribution.” 16 U.S.C. § 824(b)(1). And it may not regulate the retail sale of electricity, which is reserved to the states. Id. § 824(a). That means that transmission owners or regional regu- lators set the rules under which purely local generators connect to the grid without input from FERC. 6 affecting . . . rates and charges” that should have been stated in the tariff. 16 U.S.C. § 824d(c).

FERC rejected that argument. It found that the System Operator’s tariff did give notice that it would include nonjuris- dictional projects in its interconnection analysis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Hudson Gas & Electric Corporation v. FERC
138 F.4th 531 (D.C. Circuit, 2025)
Husky Marketing and Supply Company v. FERC
105 F.4th 418 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
72 F.4th 1307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hecate-energy-greene-county-3-llc-v-ferc-cadc-2023.