Hearns Concrete Construction Co. v. City of Ypsilanti

241 F. Supp. 2d 803, 2003 U.S. Dist. LEXIS 932, 2003 WL 169349
CourtDistrict Court, E.D. Michigan
DecidedJanuary 23, 2003
DocketCIV.02-72796
StatusPublished
Cited by5 cases

This text of 241 F. Supp. 2d 803 (Hearns Concrete Construction Co. v. City of Ypsilanti) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hearns Concrete Construction Co. v. City of Ypsilanti, 241 F. Supp. 2d 803, 2003 U.S. Dist. LEXIS 932, 2003 WL 169349 (E.D. Mich. 2003).

Opinion

MEMORANDUM OPINION AND ORDER

ANNA DIGGS TAYLOR, District Judge.

I.

The Plaintiff, Hearns Concrete (“Hearns”), is the owner of land located at 212 N. Lincoln Street in Ypsilanti, Michigan, consisting of two lots, 82 and 83. In early 1999, a site plan was submitted to the City of Ypsilanti Planning Commission (the “Commission”) by Hearns. The proposed expansion of the business was to include the addition of offices to the front of the garage structure located on lot 82. On June 29,1999, this site plan was denied because it would constitute a “non-conforming use.”

On December 15, 1999, the plaintiff submitted a revised site plan, which proposed office use only on lot 83. On April 19, 2000, the Commission approved the revised plan, subject to certain conditions which were an attempt to mitigate the conflict over the land uses. On May 16, 2000, a letter of approval was sent from the Commission to Hearns. The letter mandated that the Plaintiff would need to: (1) obtain a building permit within six months or the approval would expire; and (2) begin construction within two years following the approval date and diligently pursue completion. 1 (emphasis added). On August 10, 2000, pursuant to § 122-128 of the City of Ypsilanti Zoning Ordinance, Hearns was issued a building permit.

Plaintiff performed construction work on the project that included clearing the site, construction of the foundations, construction of a masonry wall, and setting up of roof trusses. Hearns contends that the construction work was diligently pursued “to the extent permitted by weather conditions.”

Numerous site visits were performed by the City. 2 Based on the October 10, 2001 observations, correspondence was allegedly forwarded to the Plaintiff on October 17, 2001, indicating that, pursuant to the City’s Zoning Ordinance, Plaintiff had until April 19, 2002, to complete the project *807 which had begun on April 19, 2000. 3 Hearns asserts that this correspondence was never received.

The next site inspection was performed on February 14, 2002. According to the Defendants, the site appeared to be unchanged from April 25, 2001. On April 10, 2002, the City made a further inspection, at which time the inspector stated that the same lack of progress existed, and, in addition, the site was said to “constitute a nuisance.”

On April 23, 2002, a registered letter was sent to Hearns indicating that the site plan had expired and that a new plan needed to be submitted for approval. The letter indicated that, as of April 19, 2002, no further work on the site could be conducted until the required approvals were allegedly sought, and obtained, anew. In addition to the notice of the expiration of the site plan which was contained in this letter, it is further alleged that Hearns was also informed of a possible remedy (submission of a revised plan) at a meeting between Plaintiff, Ed Koryzno (City Manager) and Nathan Voght (City Planner), on April 29, 2002. There is contention as to whether the roof trusses and roof construction had begun prior to the Plaintiff being informed in writing (April 23, 2002) and in person (April 29, 2002) that the site plan had expired.

On May 4, 2002, pursuant to the Michigan Building Code (the “Code”), a stop work order was issued. The Code - provides:

Upon notice from the enforcing agency, work on any building or structure that is being done contrary to the code or in a dangerous or unsafe manner shall immediately cease. Notice shall be in accord with section 12 of the act. A person who is served with a stop work order, except for work that the person is directed to perform to remove a violation or unsafe condition is subject to the penalty provisions prescribed in § 23 of the act. R 408.30411.

Hearns continued to work after the stop work order was issued, and he did not appeal the stop work order to • the Construction Board of Appeals, as provided for in the State Construction Act and the Michigan Building Code. Instead, Hearns filed this suit, along with an Ex Parte Motion for Temporary Restraining Order and Motion for Preliminary Injunction, on or about June 14, 2002, in State Court. Those motions were heard on June 19, 2002, by Judge Melinda Morris, who set aside the stop work order and enjoined the City from preventing the Plaintiff from continuing construction. On July 9, 2002, the Defendants sought removal to this Court pursuant to 28 U.S.C. §§ 1331,1441, 1443 and 1446.

In this action, Hearns has alleged eight counts, among them a number of federal claims, including violation of his due process rights, and one count pursuant to 42 U.S.C. § 1983, alleging racial discrimination.

II.

The Defendants, in the motion to Dismiss which is now before this court, have challenged the subject matter jurisdiction of the Court based upon the sine qua non of ripeness.

“The ripeness doctrine protects federal courts from engaging in speculation or wasting their resources through the re *808 view of potential or abstract disputes ... [The] Court must resolve whether there is sufficient injury to meet Article Ill’s requirement of a case or controversy and, if so, whether the claim is sufficiently mature, and the issues sufficiently defined and concrete, to permit effective decision making by the court.” Digital Properties, Inc. v. City of Plantation, 121 F.3d 586 (11th Cir.1997).

The necessity of ripeness is clear; yet, whether a case or controversy is “sufficiently mature” is at times a matter of case specific determination.

In the instant controversy, the Defendants have argued the proposition that the Commission’s decision to issue a stop work order is not immediately reviewable by this Court because the Plaintiff has failed to obtain “a final decision.” 4 The first leg upon which the Defendants’ position stands is Williamson County Regional Planning Comm’n v. Hamilton Bank of Johnson City, 473 U.S. 172, 105 S.Ct. 3108, 87 L.Ed.2d 126 (1985). In Williamson County, the Supreme Court stated that:

“[A] claim that the application of government regulations effects a taking of a property interest is not ripe until the governmental entity charged with implementing the regulations has reached a final decision regarding the application of the regulations to the property at issue.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
241 F. Supp. 2d 803, 2003 U.S. Dist. LEXIS 932, 2003 WL 169349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hearns-concrete-construction-co-v-city-of-ypsilanti-mied-2003.