[Cite as HCS Renewable Energy v. Deltro Elec., 2025-Ohio-138.]
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO
BROWN COUNTY
HCS RENEWABLE ENERGY, LLC, :
Appellee, : CASE NO. CA2024-04-003
: OPINION - vs - 1/21/2025 :
DELTRO ELECTRIC, LTD., et al., :
Appellants. :
CIVIL APPEAL FROM BROWN COUNTY COURT OF COMMON PLEAS Case No. 20210685
Porter Wright Morris & Arthur LLP, and Tami Hart Kirby, for appellee.
Carlile Patchen & Murphy LLP, and Michael J. King and Bryan M. Pritikin, for appellant, Deltro Electric, Ltd.
Shumaker, Loop & Kendrick, LLP, and David P. Strup for appellants, PCL Construction Services, Inc., Federal Insurance Company, Travelers Casualty and Surety Company of America, Berkshire Hathaway Specialty Insurance Company, and Liberty Mutual Insurance Company.
PIPER, J.
{¶ 1} Appellant, Deltro Electric, Ltd. ("Deltro"), appeals the decision of the Brown
County Court of Common Pleas granting appellee, HCS Renewable Energy, LLC's
("HCS"), combined motion to enforce settlement, or, alternatively, judgment on its claim
on the bond securing the lien amount owed to it by Deltro. For the reasons outlined below, Brown CA2024-04-003
we affirm the common pleas court's decision.
Facts and Procedural History
{¶ 2} On December 9, 2021, HCS filed a complaint for money damages against
Deltro, along with Federal Insurance Company ("FIC"), Travelers Casualty and Surety
Company of America ("Travelers"), Berkshire Hathaway Specialty Insurance Company
("Berkshire"), and Liberty Mutual Insurance Company ("Liberty," collectively with FIC,
Travelers, and Berkshire, "Sureties"), alleging claims against Deltro for breach of contract,
unjust enrichment/quantum meruit, promissory estoppel, action on account, and a
violation of Ohio's prompt payment act. HCS' complaint also alleged a claim on the bond
that the common pleas court had previously approved to discharge the mechanic's lien
against Deltro related to HCS' work covered by the lien from April 1, 2021 through June
12, 2021 in the sum of $785,932.21.
{¶ 3} The claims arose from services provided by HCS on a construction project
located in Brown County, Ohio commonly known as the Hillcrest Solar Project whose
general contractor was the non-party PCL Construction Services, Inc. ("PCL"). There is
no dispute that Deltro was the electrical contractor for the project pursuant to a contract
between Deltro and PCL. There is also no dispute that HCS provided labor and/or
materials to Deltro for the project pursuant to a contract between Deltro and HCS.
{¶ 4} On August 28, 2023, the parties reached the material terms of a settlement
agreement, whereby HCS was to accept payment of the lien amount ($785,932.21) from
Deltro as full and complete settlement of their respective dispute. This agreement was
made via email between the parties' respective counsel, wherein Deltro's then counsel
advised HCS' counsel that the full lien amount being "offered" was the maximum that it
would agree to pay, within 60 days, to which HCS' counsel responded, "My client will
accept payment of the lien amount as full and complete settlement." Deltro, however,
-2- Brown CA2024-04-003
later refused to pay anything within the agreed upon 60-day timeframe and instead
advised HCS that it was no longer able to go forward with any settlement that they may
have previously agreed to.
{¶ 5} On January 18, 2024, HCS filed a combined motion to enforce settlement,
or, alternatively, judgment on its claim on the bond securing the lien amount owed to it by
Deltro. Approximately two weeks later, on January 31, 2024, counsel for Deltro moved
to withdraw as Deltro's counsel. The record indicates that Deltro's counsel moved to
withdraw due to Deltro failing to pay counsel's legal fees and, as counsel later explained,
"because I'm a witness in this matter, with regard to whether there's a settlement or not."
The record also indicates that Deltro's counsel was instructed by the common pleas court
to advise Deltro that it "had to get separate counsel because of me being a witness,"
which Deltro's counsel did, "and they did not obtain counsel."
{¶ 6} On February 28, 2024, the trial court held a hearing on both HCS' combined
motion to enforcement settlement, or, alternatively, judgment on its claim on the bond and
Deltro's counsel's motion to withdraw. During this hearing, and hearing no objection, the
common pleas court granted Deltro's counsel's motion to withdraw. The common pleas
court then accepted arguments from the parties, following which the common pleas court
issued its decision finding:
The Court finds clearly and convincingly there was a settlement in this case. And there was an agreement to pay money. And, the amount was agreed upon. And apparently somebody got cold feet after the settlement was negotiated.
The Court is going to find that there was a settlement. And it's gonna order that the settlement be enforced.
The Court is going to grant judgment on the Bond. You guys can fight it out later, if that's what you chose to do. But when you Bond out a Mechanic's Lien and the judgment is given, and the Lien isn't – and the money isn't paid, the Sureties are responsible.
-3- Brown CA2024-04-003
So, unless my understanding of the law in Ohio got up and flew away somewhere, and I don't think it did, that will be the Order of the Court.
{¶ 7} Later that day, once the hearing concluded, the common pleas court issued
an entry granting Deltro's counsel's motion to withdraw as Deltro's counsel. Thereafter,
on April 9, 2024, the common pleas court issued an entry granting HCS' combined motion
to enforcement settlement, or, alternatively, judgment on its claim on the bond. In so
doing, the common pleas court noted its finding that HCS had proven, by clear and
convincing evidence, that a settlement agreement had been reached between HCS and
Deltro for Deltro to pay HCS the sum of $785,932.21 and that Deltro had breached that
settlement agreement by failing to have yet paid said amount to HCS despite previously
agreeing to do so. The common pleas court therefore held that judgment should be
entered to HCS against Deltro in the amount of $785,932.21 and that HCS shall recover
from Sureties if Deltro did not pay said amount to HCS within ten days.1
Deltro's Appeal and Single Assignment of Error
{¶ 8} On April 18, 2024, Deltro filed a notice of appeal. Following briefing, on
December 11, 2024, the matter was submitted to this court for consideration. Deltro's
appeal now properly before this court for decision, Deltro has raised one assignment of
error for review.
{¶ 9} THE TRIAL COURT COMMITTED REVERSIBLE ERROR BY GRANTING
APPELLEE'S COMBINED MOTION TO ENFORCE SETTLEMENT, OR IN THE
ALTERNATIVE, JUDGMENT ON ITS CLAIM ON THE BOND, WITHOUT HOLDING AN
EVIDENTIARY HEARING AND WITHOUT ALLOWING APPELLANT A REASONABLE
OPPORTUNITY TO ENGAGE REPLACEMENT COUNSEL.
1. The common pleas court's judgment was subsequently stayed pending this appeal.
-4- Brown CA2024-04-003
{¶ 10} In its single assignment of error, Deltro argues the common pleas court
erred by granting HCS' motion to enforcement settlement, or, alternatively, judgment on
its claim on the bond.
Free access — add to your briefcase to read the full text and ask questions with AI
[Cite as HCS Renewable Energy v. Deltro Elec., 2025-Ohio-138.]
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO
BROWN COUNTY
HCS RENEWABLE ENERGY, LLC, :
Appellee, : CASE NO. CA2024-04-003
: OPINION - vs - 1/21/2025 :
DELTRO ELECTRIC, LTD., et al., :
Appellants. :
CIVIL APPEAL FROM BROWN COUNTY COURT OF COMMON PLEAS Case No. 20210685
Porter Wright Morris & Arthur LLP, and Tami Hart Kirby, for appellee.
Carlile Patchen & Murphy LLP, and Michael J. King and Bryan M. Pritikin, for appellant, Deltro Electric, Ltd.
Shumaker, Loop & Kendrick, LLP, and David P. Strup for appellants, PCL Construction Services, Inc., Federal Insurance Company, Travelers Casualty and Surety Company of America, Berkshire Hathaway Specialty Insurance Company, and Liberty Mutual Insurance Company.
PIPER, J.
{¶ 1} Appellant, Deltro Electric, Ltd. ("Deltro"), appeals the decision of the Brown
County Court of Common Pleas granting appellee, HCS Renewable Energy, LLC's
("HCS"), combined motion to enforce settlement, or, alternatively, judgment on its claim
on the bond securing the lien amount owed to it by Deltro. For the reasons outlined below, Brown CA2024-04-003
we affirm the common pleas court's decision.
Facts and Procedural History
{¶ 2} On December 9, 2021, HCS filed a complaint for money damages against
Deltro, along with Federal Insurance Company ("FIC"), Travelers Casualty and Surety
Company of America ("Travelers"), Berkshire Hathaway Specialty Insurance Company
("Berkshire"), and Liberty Mutual Insurance Company ("Liberty," collectively with FIC,
Travelers, and Berkshire, "Sureties"), alleging claims against Deltro for breach of contract,
unjust enrichment/quantum meruit, promissory estoppel, action on account, and a
violation of Ohio's prompt payment act. HCS' complaint also alleged a claim on the bond
that the common pleas court had previously approved to discharge the mechanic's lien
against Deltro related to HCS' work covered by the lien from April 1, 2021 through June
12, 2021 in the sum of $785,932.21.
{¶ 3} The claims arose from services provided by HCS on a construction project
located in Brown County, Ohio commonly known as the Hillcrest Solar Project whose
general contractor was the non-party PCL Construction Services, Inc. ("PCL"). There is
no dispute that Deltro was the electrical contractor for the project pursuant to a contract
between Deltro and PCL. There is also no dispute that HCS provided labor and/or
materials to Deltro for the project pursuant to a contract between Deltro and HCS.
{¶ 4} On August 28, 2023, the parties reached the material terms of a settlement
agreement, whereby HCS was to accept payment of the lien amount ($785,932.21) from
Deltro as full and complete settlement of their respective dispute. This agreement was
made via email between the parties' respective counsel, wherein Deltro's then counsel
advised HCS' counsel that the full lien amount being "offered" was the maximum that it
would agree to pay, within 60 days, to which HCS' counsel responded, "My client will
accept payment of the lien amount as full and complete settlement." Deltro, however,
-2- Brown CA2024-04-003
later refused to pay anything within the agreed upon 60-day timeframe and instead
advised HCS that it was no longer able to go forward with any settlement that they may
have previously agreed to.
{¶ 5} On January 18, 2024, HCS filed a combined motion to enforce settlement,
or, alternatively, judgment on its claim on the bond securing the lien amount owed to it by
Deltro. Approximately two weeks later, on January 31, 2024, counsel for Deltro moved
to withdraw as Deltro's counsel. The record indicates that Deltro's counsel moved to
withdraw due to Deltro failing to pay counsel's legal fees and, as counsel later explained,
"because I'm a witness in this matter, with regard to whether there's a settlement or not."
The record also indicates that Deltro's counsel was instructed by the common pleas court
to advise Deltro that it "had to get separate counsel because of me being a witness,"
which Deltro's counsel did, "and they did not obtain counsel."
{¶ 6} On February 28, 2024, the trial court held a hearing on both HCS' combined
motion to enforcement settlement, or, alternatively, judgment on its claim on the bond and
Deltro's counsel's motion to withdraw. During this hearing, and hearing no objection, the
common pleas court granted Deltro's counsel's motion to withdraw. The common pleas
court then accepted arguments from the parties, following which the common pleas court
issued its decision finding:
The Court finds clearly and convincingly there was a settlement in this case. And there was an agreement to pay money. And, the amount was agreed upon. And apparently somebody got cold feet after the settlement was negotiated.
The Court is going to find that there was a settlement. And it's gonna order that the settlement be enforced.
The Court is going to grant judgment on the Bond. You guys can fight it out later, if that's what you chose to do. But when you Bond out a Mechanic's Lien and the judgment is given, and the Lien isn't – and the money isn't paid, the Sureties are responsible.
-3- Brown CA2024-04-003
So, unless my understanding of the law in Ohio got up and flew away somewhere, and I don't think it did, that will be the Order of the Court.
{¶ 7} Later that day, once the hearing concluded, the common pleas court issued
an entry granting Deltro's counsel's motion to withdraw as Deltro's counsel. Thereafter,
on April 9, 2024, the common pleas court issued an entry granting HCS' combined motion
to enforcement settlement, or, alternatively, judgment on its claim on the bond. In so
doing, the common pleas court noted its finding that HCS had proven, by clear and
convincing evidence, that a settlement agreement had been reached between HCS and
Deltro for Deltro to pay HCS the sum of $785,932.21 and that Deltro had breached that
settlement agreement by failing to have yet paid said amount to HCS despite previously
agreeing to do so. The common pleas court therefore held that judgment should be
entered to HCS against Deltro in the amount of $785,932.21 and that HCS shall recover
from Sureties if Deltro did not pay said amount to HCS within ten days.1
Deltro's Appeal and Single Assignment of Error
{¶ 8} On April 18, 2024, Deltro filed a notice of appeal. Following briefing, on
December 11, 2024, the matter was submitted to this court for consideration. Deltro's
appeal now properly before this court for decision, Deltro has raised one assignment of
error for review.
{¶ 9} THE TRIAL COURT COMMITTED REVERSIBLE ERROR BY GRANTING
APPELLEE'S COMBINED MOTION TO ENFORCE SETTLEMENT, OR IN THE
ALTERNATIVE, JUDGMENT ON ITS CLAIM ON THE BOND, WITHOUT HOLDING AN
EVIDENTIARY HEARING AND WITHOUT ALLOWING APPELLANT A REASONABLE
OPPORTUNITY TO ENGAGE REPLACEMENT COUNSEL.
1. The common pleas court's judgment was subsequently stayed pending this appeal.
-4- Brown CA2024-04-003
{¶ 10} In its single assignment of error, Deltro argues the common pleas court
erred by granting HCS' motion to enforcement settlement, or, alternatively, judgment on
its claim on the bond. To support this claim, Deltro raises three issues for this court to
consider, all three of which we will discuss after setting forth this court's standard of
review.
Standard of Review
{¶ 11} "A settlement agreement is viewed as a particularized form of a contract."
Carnahan v. London, 2005-Ohio-6684, ¶ 7. A settlement agreement is a binding contract
"designed to terminate a claim by preventing or ending litigation." Clermont Cty. Transp.
Improvement Dist. v. Smolinski, 2015-Ohio-3176, ¶ 9 (12th Dist.). "Settlement
agreements are highly favored in the law." R&L Carriers, Inc. v. Emergency Response &
Training Solutions, Inc., 2019-Ohio-3539, ¶ 30 (12th Dist.). "The standard applicable to
a motion to enforce a settlement may present a mixed question of law and fact."
Smolinski, 2015-Ohio-3176 at ¶ 10.
{¶ 12} "If the question involves the question of whether the requirements of a
contract have been met, the question is one of law." Fowler v. Smith, 2003-Ohio-6257, ¶
18 (12th Dist.). "We review questions of law de novo." BST Ohio Corp. v. Wolgang,
2021-Ohio-1785, ¶ 14. "If, however, the agreement's terms are in dispute, the issue of
whether the court should enforce the agreement is reviewed under an abuse of discretion
standard." Fowler. "The term 'abuse of discretion' means that the trial court's judgment
is 'unreasonable, arbitrary or unconscionable.'" Ray v. Bd. of Union Twp. Trs., 2007-
Ohio-3001, ¶ 10 (12th Dist.), quoting Blakemore v. Blakemore, 5 Ohio St.3d 217, 219
(1983).
Deltro's First Issue
{¶ 13} Deltro initially argues the trial court erred by failing to hold an "evidentiary
-5- Brown CA2024-04-003
hearing" on HCS' combined motion to enforcement settlement, or, alternatively, judgment
on its claim on the bond, and by "adopting settlement terms that were not supported by
competent credible evidence." However, as noted by the Ohio Supreme Court, an
evidentiary hearing is only necessary where the meaning of terms of a settlement
agreement are disputed, or where there is a dispute that contests the existence of a
settlement agreement. Rulli v. Fan Co., 79 Ohio St.3d 374, 1997-Ohio-380, syllabus.
{¶ 14} The record in this case indicates that at no time prior to this appeal did Deltro
ever contest the existence of a binding settlement agreement between itself and HCS
that obligated Deltro to pay HCS the lien amount of $785,932.21 as a full and complete
settlement of their respective claims against one another. "The burden of establishing
the existence and terms of a settlement agreement rests on the party asserting its
existence." Foor v. Columbus Real Estate Pros.com, 2013-Ohio-2848, ¶ 24 (5th Dist.).
HCS did that in this case as the record contains evidence establishing clear, previously
undisputed terms of the respective parties' agreement to settle their dispute by having
Deltro pay HCS the sum of $785,932.21 within 60 days. Therefore, finding no merit to
any of the arguments advanced by Deltro herein, Deltro's first issue lacks merit and is
denied.
Deltro's Second Issue
{¶ 15} Deltro next argues that it was error for the common pleas court to proceed
with a "hearing" on HCS' combined motion to enforcement settlement, or, alternatively,
judgment on its claim on the bond, after granting Deltro's counsel's motion to withdraw,
thereby leaving Deltro unrepresented and without counsel. Deltro, however, never
objected or otherwise raised any issue with the hearing on HCS' combined motion going
forward after its counsel's motion to withdraw had been granted by the common pleas
court. Deltro also never moved the common pleas court for a continuance so that it could
-6- Brown CA2024-04-003
procure new counsel. Deltro, in fact, failed to take any action at all to obtain new counsel
even after being advised that procuring new counsel would be necessary for Deltro to
proceed in this case.
{¶ 16} Under these circumstances, we can see no error in the common pleas court
holding the aformentioned "hearing" on HCS' combined motion to enforce settlement, or,
alternatively, judgment on its claim on the bond, after granting Deltro's counsel's motion
to withdraw. To hold otherwise would be improper given it is well established that
common pleas courts have the inherent power to manage their own dockets and the
progress of the proceedings in their own respective courts. Paramount Parks, Inc. v.
Admiral Ins. Co., 2008-Ohio-1351, ¶ 37 (12th Dist.). Therefore, finding no merit to any of
the arguments advanced by Deltro herein, Deltro's second issue also lacks merit and is
Deltro's Third Issue
{¶ 17} Deltro finally argues the common pleas court erred by entering judgment on
the bond. This is because, according to Deltro, genuine issues remain regarding its
underlying counterclaim against HCS. However, as the record indicates, Deltro never
objected to HCS' right to obtain judgment on the bond. Moreover, as the trial court
correctly determined, the bond stood in place of HCS' mechanic's lien, and if the amount
owed on the lien was not paid to HCS by Deltro within ten days, the Sureties would be
responsible to pay the lien amount to HCS. This was not an error. Therefore, finding no
merit to any of the arguments advanced by Deltro herein, Deltro's third and final argument
likewise lacks merit and is denied.
Conclusion
{¶ 18} For the reasons outlined above, and finding no merit to any of the
arguments raised by Deltro herein, including those not expressly discussed within this
-7- Brown CA2024-04-003
opinion, Deltro's challenge to the trial court's decision granting HCS' combined motion to
enforce settlement, or, alternatively, judgment on its claim on the bond securing the lien
amount owed to it by Deltro is denied.
{¶ 19} Judgment affirmed.
BYRNE, P.J., and HENDRICKSON, J., concur.
-8-