HCS Renewable Energy v. Deltro Elec.
Opinion
IN THE COURT OF APPEALS
TWELFTH APPELLATE DISTRICT OF OHIO BROWN COUNTY
HCS RENEWABLE ENERGY, LLC, :
Appellee, : CASE NO. CA2024-04-003
: OPINION
- vs - 1/21/2025 :
DELTRO ELECTRIC, LTD., et al., :
Appellants. :
CIVIL APPEAL FROM BROWN COUNTY COURT OF COMMON PLEAS Case No. 20210685
Porter Wright Morris & Arthur LLP, and Tami Hart Kirby, for appellee.
Carlile Patchen & Murphy LLP, and Michael J. King and Bryan M. Pritikin, for appellant, Deltro Electric, Ltd.
Shumaker, Loop & Kendrick, LLP, and David P. Strup for appellants, PCL Construction Services, Inc., Federal Insurance Company, Travelers Casualty and Surety Company of America, Berkshire Hathaway Specialty Insurance Company, and Liberty Mutual Insurance Company.
PIPER, J.
{¶ 1} Appellant, Deltro Electric, Ltd. ("Deltro"), appeals the decision of the Brown County Court of Common Pleas granting appellee, HCS Renewable Energy, LLC's ("HCS"), combined motion to enforce settlement, or, alternatively, judgment on its claim on the bond securing the lien amount owed to it by Deltro. For the reasons outlined below,
we affirm the common pleas court's decision.
Facts and Procedural History
{¶ 2} On December 9, 2021, HCS filed a complaint for money damages against Deltro, along with Federal Insurance Company ("FIC"), Travelers Casualty and Surety Company of America ("Travelers"), Berkshire Hathaway Specialty Insurance Company ("Berkshire"), and Liberty Mutual Insurance Company ("Liberty," collectively with FIC, Travelers, and Berkshire, "Sureties"), alleging claims against Deltro for breach of contract, unjust enrichment/quantum meruit, promissory estoppel, action on account, and a violation of Ohio's prompt payment act. HCS' complaint also alleged a claim on the bond that the common pleas court had previously approved to discharge the mechanic's lien against Deltro related to HCS' work covered by the lien from April 1, 2021 through June 12, 2021 in the sum of $785,932.21.
{¶ 3} The claims arose from services provided by HCS on a construction project located in Brown County, Ohio commonly known as the Hillcrest Solar Project whose general contractor was the non-party PCL Construction Services, Inc. ("PCL"). There is no dispute that Deltro was the electrical contractor for the project pursuant to a contract between Deltro and PCL. There is also no dispute that HCS provided labor and/or materials to Deltro for the project pursuant to a contract between Deltro and HCS.
{¶ 4} On August 28, 2023, the parties reached the material terms of a settlement agreement, whereby HCS was to accept payment of the lien amount ($785,932.21) from Deltro as full and complete settlement of their respective dispute. This agreement was made via email between the parties' respective counsel, wherein Deltro's then counsel advised HCS' counsel that the full lien amount being "offered" was the maximum that it would agree to pay, within 60 days, to which HCS' counsel responded, "My client will accept payment of the lien amount as full and complete settlement." Deltro, however,
later refused to pay anything within the agreed upon 60-day timeframe and instead advised HCS that it was no longer able to go forward with any settlement that they may have previously agreed to.
{¶ 5} On January 18, 2024, HCS filed a combined motion to enforce settlement, or, alternatively, judgment on its claim on the bond securing the lien amount owed to it by Deltro. Approximately two weeks later, on January 31, 2024, counsel for Deltro moved to withdraw as Deltro's counsel. The record indicates that Deltro's counsel moved to withdraw due to Deltro failing to pay counsel's legal fees and, as counsel later explained, "because I'm a witness in this matter, with regard to whether there's a settlement or not." The record also indicates that Deltro's counsel was instructed by the common pleas court to advise Deltro that it "had to get separate counsel because of me being a witness," which Deltro's counsel did, "and they did not obtain counsel."
{¶ 6} On February 28, 2024, the trial court held a hearing on both HCS' combined motion to enforcement settlement, or, alternatively, judgment on its claim on the bond and Deltro's counsel's motion to withdraw. During this hearing, and hearing no objection, the common pleas court granted Deltro's counsel's motion to withdraw. The common pleas court then accepted arguments from the parties, following which the common pleas court issued its decision finding:
The Court finds clearly and convincingly there was a settlement in this case. And there was an agreement to pay money. And, the amount was agreed upon. And apparently somebody got cold feet after the settlement was negotiated.
The Court is going to find that there was a settlement. And it's gonna order that the settlement be enforced.
The Court is going to grant judgment on the Bond. You guys can fight it out later, if that's what you chose to do. But when you Bond out a Mechanic's Lien and the judgment is given, and the Lien isn't – and the money isn't paid, the Sureties are responsible.
So, unless my understanding of the law in Ohio got up and flew away somewhere, and I don't think it did, that will be the Order of the Court.
{¶ 7} Later that day, once the hearing concluded, the common pleas court issued an entry granting Deltro's counsel's motion to withdraw as Deltro's counsel. Thereafter, on April 9, 2024, the common pleas court issued an entry granting HCS' combined motion to enforcement settlement, or, alternatively, judgment on its claim on the bond. In so doing, the common pleas court noted its finding that HCS had proven, by clear and convincing evidence, that a settlement agreement had been reached between HCS and Deltro for Deltro to pay HCS the sum of $785,932.21 and that Deltro had breached that settlement agreement by failing to have yet paid said amount to HCS despite previously agreeing to do so. The common pleas court therefore held that judgment should be entered to HCS against Deltro in the amount of $785,932.21 and that HCS shall recover from Sureties if Deltro did not pay said amount to HCS within ten days.1 Deltro's Appeal and Single Assignment of Error
{¶ 8} On April 18, 2024, Deltro filed a notice of appeal. Following briefing, on December 11, 2024, the matter was submitted to this court for consideration. Deltro's appeal now properly before this court for decision, Deltro has raised one assignment of error for review.
{¶ 9} THE TRIAL COURT COMMITTED REVERSIBLE ERROR BY GRANTING APPELLEE'S COMBINED MOTION TO ENFORCE SETTLEMENT, OR IN THE ALTERNATIVE, JUDGMENT ON ITS CLAIM ON THE BOND, WITHOUT HOLDING AN EVIDENTIARY HEARING AND WITHOUT ALLOWING APPELLANT A REASONABLE OPPORTUNITY TO ENGAGE REPLACEMENT COUNSEL.
1. The common pleas court's judgment was subsequently stayed pending this appeal.
{¶ 10} In its single assignment of error, Deltro argues the common pleas court erred by granting HCS' motion to enforcement settlement, or, alternatively, judgment on its claim on the bond. To support this claim, Deltro raises three issues for this court to consider, all three of which we will discuss after setting forth this court's standard of review.
Standard of Review
{¶ 11} "A settlement agreement is viewed as a particularized form of a contract."
Carnahan v. London, 2005-Ohio-6684, ¶ 7. A settlement agreement is a binding contract "designed to terminate a claim by preventing or ending litigation." Clermont Cty. Transp. Improvement Dist. v. Smolinski, 2015-Ohio-3176, ¶ 9 (12th Dist.). "Settlement agreements are highly favored in the law." R&L Carriers, Inc. v. Emergency Response & Training Solutions, Inc., 2019-Ohio-3539, ¶ 30 (12th Dist.). "The standard applicable to a motion to enforce a settlement may present a mixed question of law and fact." Smolinski, 2015-Ohio-3176 at ¶ 10.
Free access — add to your briefcase to read the full text and ask questions with AI
2025 Ohio 138 (HCS Renewable Energy v. Deltro Elec.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.