HCS Renewable Energy v. Deltro Elec.

2025 Ohio 138
CourtOhio Court of Appeals
DecidedJanuary 21, 2025
DocketCA2024-04-003
StatusPublished

This text of 2025 Ohio 138 (HCS Renewable Energy v. Deltro Elec.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HCS Renewable Energy v. Deltro Elec., 2025 Ohio 138 (Ohio Ct. App. 2025).

Opinion

[Cite as HCS Renewable Energy v. Deltro Elec., 2025-Ohio-138.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

BROWN COUNTY

HCS RENEWABLE ENERGY, LLC, :

Appellee, : CASE NO. CA2024-04-003

: OPINION - vs - 1/21/2025 :

DELTRO ELECTRIC, LTD., et al., :

Appellants. :

CIVIL APPEAL FROM BROWN COUNTY COURT OF COMMON PLEAS Case No. 20210685

Porter Wright Morris & Arthur LLP, and Tami Hart Kirby, for appellee.

Carlile Patchen & Murphy LLP, and Michael J. King and Bryan M. Pritikin, for appellant, Deltro Electric, Ltd.

Shumaker, Loop & Kendrick, LLP, and David P. Strup for appellants, PCL Construction Services, Inc., Federal Insurance Company, Travelers Casualty and Surety Company of America, Berkshire Hathaway Specialty Insurance Company, and Liberty Mutual Insurance Company.

PIPER, J.

{¶ 1} Appellant, Deltro Electric, Ltd. ("Deltro"), appeals the decision of the Brown

County Court of Common Pleas granting appellee, HCS Renewable Energy, LLC's

("HCS"), combined motion to enforce settlement, or, alternatively, judgment on its claim

on the bond securing the lien amount owed to it by Deltro. For the reasons outlined below, Brown CA2024-04-003

we affirm the common pleas court's decision.

Facts and Procedural History

{¶ 2} On December 9, 2021, HCS filed a complaint for money damages against

Deltro, along with Federal Insurance Company ("FIC"), Travelers Casualty and Surety

Company of America ("Travelers"), Berkshire Hathaway Specialty Insurance Company

("Berkshire"), and Liberty Mutual Insurance Company ("Liberty," collectively with FIC,

Travelers, and Berkshire, "Sureties"), alleging claims against Deltro for breach of contract,

unjust enrichment/quantum meruit, promissory estoppel, action on account, and a

violation of Ohio's prompt payment act. HCS' complaint also alleged a claim on the bond

that the common pleas court had previously approved to discharge the mechanic's lien

against Deltro related to HCS' work covered by the lien from April 1, 2021 through June

12, 2021 in the sum of $785,932.21.

{¶ 3} The claims arose from services provided by HCS on a construction project

located in Brown County, Ohio commonly known as the Hillcrest Solar Project whose

general contractor was the non-party PCL Construction Services, Inc. ("PCL"). There is

no dispute that Deltro was the electrical contractor for the project pursuant to a contract

between Deltro and PCL. There is also no dispute that HCS provided labor and/or

materials to Deltro for the project pursuant to a contract between Deltro and HCS.

{¶ 4} On August 28, 2023, the parties reached the material terms of a settlement

agreement, whereby HCS was to accept payment of the lien amount ($785,932.21) from

Deltro as full and complete settlement of their respective dispute. This agreement was

made via email between the parties' respective counsel, wherein Deltro's then counsel

advised HCS' counsel that the full lien amount being "offered" was the maximum that it

would agree to pay, within 60 days, to which HCS' counsel responded, "My client will

accept payment of the lien amount as full and complete settlement." Deltro, however,

-2- Brown CA2024-04-003

later refused to pay anything within the agreed upon 60-day timeframe and instead

advised HCS that it was no longer able to go forward with any settlement that they may

have previously agreed to.

{¶ 5} On January 18, 2024, HCS filed a combined motion to enforce settlement,

or, alternatively, judgment on its claim on the bond securing the lien amount owed to it by

Deltro. Approximately two weeks later, on January 31, 2024, counsel for Deltro moved

to withdraw as Deltro's counsel. The record indicates that Deltro's counsel moved to

withdraw due to Deltro failing to pay counsel's legal fees and, as counsel later explained,

"because I'm a witness in this matter, with regard to whether there's a settlement or not."

The record also indicates that Deltro's counsel was instructed by the common pleas court

to advise Deltro that it "had to get separate counsel because of me being a witness,"

which Deltro's counsel did, "and they did not obtain counsel."

{¶ 6} On February 28, 2024, the trial court held a hearing on both HCS' combined

motion to enforcement settlement, or, alternatively, judgment on its claim on the bond and

Deltro's counsel's motion to withdraw. During this hearing, and hearing no objection, the

common pleas court granted Deltro's counsel's motion to withdraw. The common pleas

court then accepted arguments from the parties, following which the common pleas court

issued its decision finding:

The Court finds clearly and convincingly there was a settlement in this case. And there was an agreement to pay money. And, the amount was agreed upon. And apparently somebody got cold feet after the settlement was negotiated.

The Court is going to find that there was a settlement. And it's gonna order that the settlement be enforced.

The Court is going to grant judgment on the Bond. You guys can fight it out later, if that's what you chose to do. But when you Bond out a Mechanic's Lien and the judgment is given, and the Lien isn't – and the money isn't paid, the Sureties are responsible.

-3- Brown CA2024-04-003

So, unless my understanding of the law in Ohio got up and flew away somewhere, and I don't think it did, that will be the Order of the Court.

{¶ 7} Later that day, once the hearing concluded, the common pleas court issued

an entry granting Deltro's counsel's motion to withdraw as Deltro's counsel. Thereafter,

on April 9, 2024, the common pleas court issued an entry granting HCS' combined motion

to enforcement settlement, or, alternatively, judgment on its claim on the bond. In so

doing, the common pleas court noted its finding that HCS had proven, by clear and

convincing evidence, that a settlement agreement had been reached between HCS and

Deltro for Deltro to pay HCS the sum of $785,932.21 and that Deltro had breached that

settlement agreement by failing to have yet paid said amount to HCS despite previously

agreeing to do so. The common pleas court therefore held that judgment should be

entered to HCS against Deltro in the amount of $785,932.21 and that HCS shall recover

from Sureties if Deltro did not pay said amount to HCS within ten days.1

Deltro's Appeal and Single Assignment of Error

{¶ 8} On April 18, 2024, Deltro filed a notice of appeal. Following briefing, on

December 11, 2024, the matter was submitted to this court for consideration. Deltro's

appeal now properly before this court for decision, Deltro has raised one assignment of

error for review.

{¶ 9} THE TRIAL COURT COMMITTED REVERSIBLE ERROR BY GRANTING

APPELLEE'S COMBINED MOTION TO ENFORCE SETTLEMENT, OR IN THE

ALTERNATIVE, JUDGMENT ON ITS CLAIM ON THE BOND, WITHOUT HOLDING AN

EVIDENTIARY HEARING AND WITHOUT ALLOWING APPELLANT A REASONABLE

OPPORTUNITY TO ENGAGE REPLACEMENT COUNSEL.

1. The common pleas court's judgment was subsequently stayed pending this appeal.

-4- Brown CA2024-04-003

{¶ 10} In its single assignment of error, Deltro argues the common pleas court

erred by granting HCS' motion to enforcement settlement, or, alternatively, judgment on

its claim on the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foor v. Columbus Real Estate Pros.com
2013 Ohio 2848 (Ohio Court of Appeals, 2013)
Clermont Cty. Transp. Improvement Dist. v. Smolinski
2015 Ohio 3176 (Ohio Court of Appeals, 2015)
Fowler v. Smith, Unpublished Decision (11-24-2003)
2003 Ohio 6257 (Ohio Court of Appeals, 2003)
Carnahan v. City of London, Unpublished Decision (12-19-2005)
2005 Ohio 6684 (Ohio Court of Appeals, 2005)
BST Ohio Corp. v. Wolgang (Slip Opinion)
2021 Ohio 1785 (Ohio Supreme Court, 2021)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Rulli v. Fan Co.
683 N.E.2d 337 (Ohio Supreme Court, 1997)
Rulli v. Fan Co.
1997 Ohio 380 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hcs-renewable-energy-v-deltro-elec-ohioctapp-2025.