HCS, Inc.

CourtArmed Services Board of Contract Appeals
DecidedSeptember 20, 2016
DocketASBCA No. 60533
StatusPublished

This text of HCS, Inc. (HCS, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HCS, Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) HCS, Inc. ) ASBCA No. 60533 ) Under Contract No. N69450-l 5-M-5346 )

APPEARANCE FOR THE APPELLANT: Mr. Douglas Reitmeyer Vice President for Litigation

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Robert G. Palmer, Esq. Associate Counsel Naval Facilities Engineering Command Southeast Jacksonville, FL

OPINION BY ADMINISTRATIVE JUDGE HARTMAN

The Department of the Navy unilaterally modified a contract's scope of work to require a contractor to cap a leaking 4" pipeline that perpendicularly intersected an 8" pipeline in lieu of replacing "up to 60 feet" of the 8" pipeline deemed originally by the Navy to be the source of a water leak. After completion of all contract work, the Navy unilaterally reduced the price of the parties' contract by more than 50%. Appellant seeks in this accelerated Board Rule 12.3 appeal its original fixed-price for the contract, less an adjustment for materials bid that it was not required to use and new materials added to the contract as a result of the Navy's unilateral change.

FINDINGS OF FACT

In July of 2015, a Department of the Navy contracting officer (CO), LT Joel Overson, requested receipt of quotes from small businesses to "Provide all Labor, Materials, equipment, Tools, Transportation and Management necessary to repair [an] 8" pipe and isolation valve" at Naval Air Station (NAS) Corpus Christi, Texas (R4, tab 1; tr. 89-90). The request contained a "STATEMENT OF WORK" providing as follows:

I. Isolate, drain, excavate, provide adequate shoring to ensure prevention of collapse/undermining of surrounding area(s). selectively demolish, and remove up to three twenty foot (20'-0") long sections of eight inch (8" dia.) steel water line sections located along A venue "C" that may have failed and are leaking and, as necessary, fittings ... that along with the pipe are buried at a maximum depth of up to approximately ten feet (10'-0") as well as the four inch diameter (4" dia.) Isolation Valve located approximately adjacent to Building 20 ....

3. Expose the existing potentially leaking sections of eight inch diameter (8" dia.) steel water piping section(s) by excavating the existing and adjoining/surrounding areas of the existing asphalt and/or concrete-base parking lot area(s) as necessary utilizing various safe methods of excavation (including saw cutting where appropriate) to completely expose leaking piping section(s) and utilize a trench box to provide the necessary shoring and limit the ultimate amount of excavation required.

5. Having determined what excavated and existing section(s) and fitting(s) of the eight inch diameter (8" dia.) have in-fact failed and are leaking, selectively demolish and remove the affected section(s) of eight inch diameter (8" dia.) of water line and fittings (if required) with the piping sections to facilitate the necessary and direct installation of the replacement section length(s) of eight-inch diameter (8" dia.) ... poly or High Pressure Certified HDPE Piping, as well as the appropriate and matching material eight-inch diameter (8" dia.) Pipe Fittings ....

6. Having excavated and exposed the existing failed/leaking isolation valve (Valve 119). selectively demolish and remove the existing isolation valve (Valve 119), and then install a replacement isolation valve that exactly matches the existing isolation valve ....

2 9. After having completed the installation and connection of the new section of Poly or High Density Polyethylene (HOPE) eight inch diameter (8" dia.) ... Water Piping Sections(s), and the new four inch diameter (4" dia.) isolation valve ... perform the appropriate flow and leak testing for both the newly installed piping and the newly installed isolation valve, remove the trench box utilized for shoring, backfill (as required) the excavated trenched section opening(s), and replace the excavated asphalt parking area to match the existing asphalt parking area(s) to complete restoration of the job site area(s) to a normal condition. [Emphasis added]

(R4, tab 1 at 4-5) The quotation request stated that the period of performance is 20 calendar days and that there would be a site visit for potential offerors "to satisfy themselves as to the general and local conditions that may affect the cost of the performance of the work to the extent that such information is reasonably attainable" (id. at 3, 5). The request incorporated by reference various standard contract clauses, including Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES-ALT. 1 (MAY 2014); FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984); and FAR 52.243-5, CHANGES AND CHANGED CONDITIONS (APR 1984) (R4, tab 1 at 21-22). Attached to the request was a .. PROJECT LOCATION MAP," which contained an arrow pointing to a specific area at the NAS Corpus Christi along .. C" Street, and stated: "ISOLATE 8" ISO-VAL VE 121 A AND EFFECT REPAIRS TO REPLACEMENT OF FIVE FOOT (5'-0") LONG SECTION OF EXISTING 8" DIA. WATER LINE" (R4, tab 1at51).

On 17 August 2015, the CO amended the statement of work in the request for quotations to advise potential offerors that:

4. Groundwater is an ongoing issue that any trenching or digging related project can encounter. As such the contractor should take prudent steps to deal with any groundwater encountered in a manner consistent with both regulatory/statutory requirements and safety practices.

(R4, tab 2 at 8)

Appellant, HCS, Inc. (HCS), is a small business located in Waco, Texas, about five hours away from NAS Corpus Christi. Both the president of HCS, Carl Ballerino, and Ben Moberg, president of HCS's prospective pipe-repair subcontractor, Quality Contracting, attended the site visit at NAS Corpus Christi. Based on his experience

3 that most pipe leaks occur at pipeline joints and the small size of the sink-hole that existed at the site of the NAS leak, Mr. Moberg, believed the NAS leak likely occurred at a pipeline joint, and could be replaced by cutting and removing a small section of the pipe and installing a short section of new pipe (along with appropriate couplings). He prepared a bid for Mr. Ballerino/HCS based on this belief, Mr. Ballerino/HCS relied upon that bid in preparing HCS' prime contractor bid, and HCS submitted to the CO a bid in the sum of $40,975.00, which was within 2 percent of the government's estimated cost for performance of the work specified. (Tr. 166, 273-76; exs. G-1, A-1)

On 3 September 2015, the Department of the Navy CO awarded Contract No. N69450-l 5-M-5346 to HCS for the pipeline repair work at NAS Corpus Christi and HCS entered into a subcontract with Quality Contracting with respect to the performance of that work. Thereafter, HCS (and Quality) obtained the necessary approval of plans, permits, and training certification necessary to proceed with the work. (R4, tab 4; tr. 7, 33-38, 229, 237-38, 248-49)

On Tuesday, 8 December 2015, Mr. Moberg traveled about five hours from Waco, Texas, to Corpus Christi, Texas, with two IO-foot sections of 8" pipe and two mechanical couplings. After arriving at the site, he located the utilities and measured the depth of the pipe to be repaired. (R4, tab 13 at 1, 29; tr. 236, 251-52) The next day, on 9 December 2015, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce Construction Corporation v. The United States
324 F.2d 516 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
HCS, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hcs-inc-asbca-2016.