Hazzard v. Southern Dredging Co.

811 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1228, 1993 WL 21724
CourtDistrict Court, D. South Carolina
DecidedJanuary 29, 1993
DocketCiv. A. No. 2:90-685-18
StatusPublished

This text of 811 F. Supp. 1127 (Hazzard v. Southern Dredging Co.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hazzard v. Southern Dredging Co., 811 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1228, 1993 WL 21724 (D.S.C. 1993).

Opinion

AMENDED ORDER

NORTON, District Judge.

I. BACKGROUND

James D. Hazzard (hereinafter “plaintiff”) is the owner of a small dredge named the HAZZARD. In September of 1989, Hurricane Hugo's destructive forces rendered the HAZZARD a total loss for insurance purposes. This damage occurred while the dredge was moored at Southern Dredging Company’s (hereinafter “Southern”) marina in Charleston, South Carolina. Plaintiff, bringing this admiralty action pursuant to Fed.R.Civ.P. 9(h), alleges that he is entitled to the recovery of insurance proceeds from Southern, which were collected under a policy covering the HAZZARD. Plaintiff bases his entitlement on causes of actions of breach of contract, constructive trust, and unjust enrichment. In addition, plaintiff seeks actual and punitive damages against both Southern and H. George Dent, Jr. (hereinafter “Dent”), individually, under a separate cause of action for breach of contract accompanied by a fraudulent act.

Southern answered and counterclaimed against the plaintiff to recover expenses of storage and salvage charges incurred during the mooring of the dredge HAZZARD at Southern’s marina and, in addition, claims lost profits because the sunken HAZZARD blocked the entrance to Southern’s marina after Hurricane Hugo. Plaintiff replied and asserted that Southern’s counterclaim fails to state a claim upon which relief can be granted. Plaintiff also asserted the affirmative defense of an Act of God being the sole cause of any loss. By Order of this court on August 14, 1991, Southern’s counterclaim for storage charges was dismissed.

The case was tried before this tribunal, sitting without a jury, on September 14, 1992. Having considered the testimony and the exhibits admitted at trial, and the pre-trial briefs and proposed orders submitted to the court by the parties, this court now makes the following Findings of Fact and Conclusions of Law in accordance with Fed.R.Civ.P. 52(a).

II. FINDINGS OF FACT

A. Plaintiff owned a dredging vessel known as the HAZZARD. Plaintiff purchased the HAZZARD on June 17, 1983, from International Paper Company for $6300.1

B. The HAZZARD was a small non-portable,2 shop-built dredge built in the early 1930’s. Compared to the newer, larger portable dredge models of today, the HAZZARD was extremely limited in her usefulness and power.

C. Mr. Robert Jantzen testified that the estimated value of the HAZZARD was in the range of $10,000 to $15,000, based primarily on her scrap value.3

[1130]*1130D. Plaintiff successfully procured only two leasing arrangements for the HAZZARD prior to her demise. In 1984, plaintiff leased the HAZZARD to Ocean Isle Developing Company of Shallotte, North Carolina, for dredging at a price of $1.85 per yard, for a total of 11,500 yards or $20,350. Plaintiffs Ex. # 24. Then, in 1985, plaintiff leased the dredge to Southern for dredging at a lump sum of $15,000.

E. The leasing arrangement between plaintiff and Southern was evidenced by a lease agreement dated December 30, 1985. The lease agreement, prepared by defendant Dent as President of Southern, stated that the dredge was to be used by Southern for a dredging project on the Charleston Municipal Marina. The agreement, in the form of a letter, stated, in part:

You [Mr. Hazzard] agree that you will furnish the dredge ... for a period of approximately 2 months____
[W]e [Southern] agree that we will provide all the necessary mobilization from Georgetown to Charleston and demobilization from Charleston back to Georgetown of all of the equipment. We also agree that we will insure the dredge and equipment for $100,000 under our marine policy ... and we agree that we will replace any tools or equipment that are missing upon return of the dredge to Georgetown.

Plaintiffs Ex. # 1.

F. Plaintiff requested the $100,000 insurance coverage amount for the HAZZARD. On February 18, 1986, Southern obtained $100,000 of insurance for the dredge HAZZARD on its fleet hull policy. Plaintiff was then listed as loss payee on the policy and was, by the terms of the addendum to the policy, to remain a loss payee from February 18, 1986 to the policy expiration date of April 2, 1986. Plaintiffs Ex. # 7 and # 8.

G. Southern only used the HAZZARD for dredging services for the City of Charleston. Southern, pursuant to a modification of the marina contract with the City of Charleston and in addition to the marina dredging, used the HAZZARD for dredging of the Charleston Yacht Club area for the week of April 30, 1986 to May 4, 1986. Southern was paid $11,325 for this additional work. Plaintiff received no extra compensation for the additional use of the HAZZARD.

H. Southern completed all dredging work for the City of Charleston on May 4, 1986.4

I. For reasons that the parties dispute, the dredge remained in Charleston at Southern’s marina for more than three years after the marina project. Southern asserts that plaintiff left the dredge at Southern in case Southern wanted to use it, for whatever reason, at no charge. Plaintiff contends that he allowed Southern to postpone return of the dredge in order to defer the cost and effort of demobilization and because Southern was considering dredging its own marina.

J. After the completion of the marina project and during the period when the HAZZARD remained in Southern's marina, Southern continued to maintain a hull insurance policy on the dredge HAZZARD. Southern, however, on the policy renewal inception date of April 3, 1987, placed the HAZZARD on a port risk basis, thereby deleting the full navigation coverage and reducing the premium charges.

K. In September of 1989, Hurricane Hugo rendered the HAZZARD a total loss. Numerous items, of value apart from the dredge, were also lost in the destruction of the HAZZARD:

1. 1200 gallon # 2 diesel E.90 $1,080.00
2. 1 Bbl — oil and pump 350.00
3. 2,'k" Demming booster pump 900.00
4. 3 b-8' collars NEW, $30.00/eaeh 900.00
5. 2 swing anchors, $200.00/eaeh 400.00
6. 200 lb. stainless steel anchor 350.00
7. Bench vice 50.00
8. IV2 gas pump with hose, NEW 450.00
9. 3 b. pipe wrench; 18 pipe wrench sledge hammers; cable cutters 250.00
TOTAL $4,480.00

Additionally, pipeline, totaling in value $7,500, was destroyed. Thus, the total val[1131]*1131ue of equipment lost, excluding the value of the dredge itself, was $11,980.5

L. The HAZZARD’s sinking contributed to the blocking of Southern’s marina and Rig Number 27. Rig Number 27 is a twenty-five ton floating crane.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
811 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1228, 1993 WL 21724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hazzard-v-southern-dredging-co-scd-1993.