Haynam v. Laclede Electric Cooperative, Inc.

827 S.W.2d 200, 1992 Mo. LEXIS 57, 1992 WL 55213
CourtSupreme Court of Missouri
DecidedMarch 24, 1992
Docket73556
StatusPublished
Cited by18 cases

This text of 827 S.W.2d 200 (Haynam v. Laclede Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haynam v. Laclede Electric Cooperative, Inc., 827 S.W.2d 200, 1992 Mo. LEXIS 57, 1992 WL 55213 (Mo. 1992).

Opinion

THOMAS, Judge.

This appeal arises out of a suit for wrongful termination of electrical service. Frank and Sondra Haynam sued Laclede Electric Cooperative. At trial, the jury awarded the Haynams $945 in actual damages and $30,000 in punitive damages. Laclede filed a Motion for Judgment Notwithstanding the Verdict or, in the alternative, for a New Trial. The trial court granted Laclede’s Motion for New Trial on all issues without specifying the grounds for the new trial. Both parties appealed from the trial court. The Court of Appeals, Southern District, set aside the order granting a new trial and remanded the case to the trial court for entry of a judgment notwithstanding the verdict in favor of Lac-lede. The court of appeals found that the Haynams did not present sufficient evidence to conclude that Laclede’s termination of services was malicious, willful or wanton.

The Haynams own and operate a dairy farm. Laclede billed the Haynams each month. The Haynams read their own meter each month, and the billing was based upon the reported usage each month. Pri- or to the events that led up to this suit, Sondra Haynam routinely read the meter. In March 1986, however, Frank Haynam read the meter and reported the reading to Laclede as required. According to this reading, the Haynam’s electric usage for the month was 13,299 kilowatt hours, an increase of six times their normal usage, resulting in a net charge of $683.91. Frank Haynam contacted James Snavely, an area foreman for Laclede, about the increase in usage. Snavely visited the Haynam farm to look at the meter but did not find a problem; however, he did not test the meter. He told Frank Haynam that the high reading resulted from the actual use of too much electricity, possibly due to a surge and not to a malfunction of the meter. Upon the recommendation of Snavely, the Haynams hired an electrician to inspect their appliances, but the inspection failed to disclose any defects.

The Haynams protested the large bill, claiming the meter must have malfunctioned. Laclede refused to reduce the bill, claiming the high usage resulted from the Haynam’s fraudulent reading of the meter during the previous year.

In order to continue electrical service, the Haynams agreed to pay the bill pursuant to special arrangements. Sondra claims that Laclede agreed to allow them to pay one half in April and the other half by May 30,1986. Laclede’s accounts manager *203 recorded May 16, 1986, as the date of final payment in her log book. Both the Hay-nams testified that they were told by several officials of Laclede including both Kenneth Miller, the general manager, and James Snavely, the area foreman, that the electricity would not be disconnected without a personal visit from Laclede to inform the Haynams that the electricity would be disconnected. Miller later testified that he authorized the disconnection of service without notice to the Haynams.

On May 22, 1986, Laclede terminated electrical service without notice to the Hay-nams when the final payment was not received. Laclede had removed the meter and left a note that said “when you pay your bill we will bring your meter back.” Prank Haynam called his wife immediately after the disconnection. Sondra Haynam called the Lebanon office of Laclede to inquire about the disconnection, but the representatives told her the electricity could not be restored until the bill was paid in full. Laclede restored the electricity to the farm within four hours after the disconnection following a call from an attorney for the Haynams. The Haynams reluctantly agreed to pay all reconnection fees and an additional security deposit, along with the amount due on the bill.

Contrary to the court of appeals, the Haynams argue that they presented a sub-missible case for wrongful termination based upon Laclede’s conduct in terminating their electricity without notice, despite the special arrangements that had been made. First, the Haynams contend that a cause of action for wrongful termination only requires the defendants act negligently, which, according to the Haynams, is easily satisfied in this case. In the alternative, the Haynams assert that, even if the cause of action for wrongful termination requires the higher standard of willful and wanton conduct, the punitive damage award evidences the submissibility of their claim because the jury must have found the defendants acted maliciously in order to award punitive damages. Laclede, on the other hand, claims that the tort of wrongful termination requires the defendants act with intentional maliciousness and that the Haynams did not satisfy this element of the tort, much less the standard for a punitive damage award.

Before reaching the submissibility issue, this Court must first determine the elements of the cause of action for wrongful termination of electrical service. In Ellyson et ux. v. Missouri Power & Light Co., 59 S.W.2d 714, 716 (Mo.App.1933), plaintiffs successfully plead the tort of wrongful failure to supply electricity by pleading the following elements: (1) defendant was engaged in the discharge of a public enterprise or service; (2) plaintiffs fell within the class of persons whom defendant was obligated to serve; (3) plaintiffs had performed all conditions precedent entitling them to service; (4) defendant had wrongfully refused or neglected to supply such service to them; and (5) plaintiffs had been damaged. Furthermore, in 1973, the Court of Appeals, Eastern District, held that an electric company is required to exercise reasonable care in fulfilling the obligation to provide adequate and continuous service arising from either contracts or regulatory enactments. National Food Stores, Inc. v. Union Electric Co., 494 S.W.2d 379 (Mo.App.1973).

In 1979, the Court of Appeals, Western District, decided Rose v. Missouri Public Service Co., 586 S.W.2d 767 (Mo.App.1979). The court held that the electrical supplier was liable for damages due to interrupted service only if the interruption was caused by or due to the willful and wanton misconduct of the company. Id. at 767. This decision, however, was based upon a contractual obligation that provided the utility would only be liable for damages caused by or due to the willful and wanton misconduct of the company. DeLong v. Osage Valley Electric Cooperative Ass’n, 716 S.W.2d 320 (Mo.App.1986), continued the application of the willful and wanton standard, despite the fact that Rose was based upon a contractual provision and De-Long was not.

We hold that, in the absence of a contrary provision in a contract, a plaintiff seeking recovery in tort for wrongful ter *204 mination of electrical service is required to show that defendant acted negligently in its failure to supply electrical service. In the alternative, a plaintiff may show the termination was an intentional wrongful act, i.e., with knowledge that plaintiff was entitled to receive service under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joe Frazier v. City of Kansas City, Missouri
467 S.W.3d 327 (Missouri Court of Appeals, 2015)
State v. Shockley
410 S.W.3d 179 (Supreme Court of Missouri, 2013)
Mitchell v. Kardesch
313 S.W.3d 667 (Supreme Court of Missouri, 2010)
Dudley v. Southern Union Co.
261 S.W.3d 598 (Missouri Court of Appeals, 2008)
State v. Saucier
926 A.2d 633 (Supreme Court of Connecticut, 2007)
Central Missouri Electric Cooperative v. Wayne
18 S.W.3d 46 (Missouri Court of Appeals, 2000)
Shoemaker v. Ekunno
960 S.W.2d 527 (Missouri Court of Appeals, 1998)
Allstates Transworld Vanlines, Inc. v. Southwestern Bell Telephone Co.
937 S.W.2d 314 (Missouri Court of Appeals, 1996)
Haynam v. Laclede Electric Cooperative, Inc.
889 S.W.2d 148 (Missouri Court of Appeals, 1994)
Olinger v. General Heating & Cooling Co.
896 S.W.2d 43 (Missouri Court of Appeals, 1994)
Ross v. Ford Motor Credit Co.
867 S.W.2d 546 (Missouri Court of Appeals, 1993)
Sparks v. Platte-Clay Electric Cooperative, Inc.
861 S.W.2d 604 (Missouri Court of Appeals, 1993)
Miles v. Dennis
853 S.W.2d 406 (Missouri Court of Appeals, 1993)
Porter v. Erickson Transport Corp.
851 S.W.2d 725 (Missouri Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
827 S.W.2d 200, 1992 Mo. LEXIS 57, 1992 WL 55213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haynam-v-laclede-electric-cooperative-inc-mo-1992.