Hawkins/Korshoj v. State Board of Regents

255 N.W.2d 124, 1977 Iowa Sup. LEXIS 1092
CourtSupreme Court of Iowa
DecidedJune 29, 1977
Docket2-59060
StatusPublished
Cited by25 cases

This text of 255 N.W.2d 124 (Hawkins/Korshoj v. State Board of Regents) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawkins/Korshoj v. State Board of Regents, 255 N.W.2d 124, 1977 Iowa Sup. LEXIS 1092 (iowa 1977).

Opinion

MOORE, Chief Justice.

Defendant appeals trial court judgment entered in plaintiff’s favor which sustained an arbitration award of $83,887.02. We affirm.

The case was submitted below on stipulated facts. In October 1969, plaintiff contractor entered into a contract with defendant Board of Regents to build a dental science building at the University of Iowa by October 1971 for $5,068,311. Construction was eventually completed in the fall of 1972 and acceptance made by the Board in January 1973.

Pursuant to the contract plaintiff periodically submitted “periodic estimates for partial payment” and was paid without incident accordingly. On February 26, 1973 plaintiff submitted its final estimate of $261,031.93. Defendant paid $226,031.93 of this amount in March but withheld $35,000 to cover damage sustained to the project “until such time” as the party or parties responsible for a 1972 break in the water main at the building could be ascertained.

On May 11,1973 plaintiff filed a demand with defendant later amended on June 6, 1973, for $518,849.11 for additional items received and expenses resulting from delays in construction. Plaintiff had on August 26, 1972 notified defendant such claims would be made.

In October 1973, defendants commenced an action in Johnson County District Court against plaintiff and two other contractors to determine responsibility for a broken water main. Plaintiff meanwhile, in December 1973, filed a “notice of intent to arbitrate” its claim pursuant to the contract arbitration clause which provided:

“7.10.1 All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, * * * except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraphs 9.7.5 and 9.7.6; shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement so to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
“7.10.2 Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within * * * . a reasonable time after the claim, dispute or other matter in question has arisen, * * *.
“7.10.3 The Contractor shall carry on the Work and maintain the progress schedule during any arbitration proceedings, unless otherwise agreed by him and the Owner in writing.”

In the Johnson County litigation the parties entered into a stipulation that only the *126 water main damage issue would be adjudicated therein and any other claims plaintiff made against defendant were to be arbitrated. The stipulation provided in relevant part:

“There is expressly reserved to Hawkins and Korshoj and State of Iowa and State Board of Regents the right to resolve by arbitration proceedings all other claims, disputes and matters in question arising out of or relating to the October 24,1969, contract between said parties.
“That Hawkins/Korshoj’s claim against the Regents shall be and is to be arbitrated in accordance with the demand for arbitration heretofore filed by Hawkins/Korshoj and pursuant to the provisions of Paragraph 7.10 Arbitration, Article VII, miscellaneous provisions, of the general conditions of the contract for construction and entered into by Regents and Hawkins/Korshoj on October 24, 1969.”

Subsequently in April 1974 defendant paid plaintiff $31,126.15 on condition its insurance carrier agree to pay any judgment ultimately entered when the liability issue was resolved. In oral argument the parties indicated the matter was still pending.

An arbitration hearing was finally held on plaintiff’s claim on December 9, 1974. Prior to the reception of evidence defendant raised an objection to the arbitrability of plaintiff’s claim. The basis of this objection was section 9.7.6 of the construction contract which provided:

“The acceptance of final payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and still unsettled.”

At the close of the evidence and before final submission defendant renewed its objection. In both instances it specifically asserted it was not waiving the objection by proceeding with the arbitration. After due consideration the arbitrators awarded plaintiff $82,976. Subsequently the American Arbitration Association directed defendant to pay plaintiff an additional $911.02 for costs previously advanced by plaintiff.

Plaintiff thereafter filed a petition in Polk County District Court praying for judgment in the amount of the arbitration award and costs which defendant had refused to pay. Defendant in its answer affirmatively alleged plaintiff’s claim was not ar-bitrable under the construction contract and thus the award was null and void.

In sustaining the arbitration award trial court concluded defendant waived any rights it had pursuant to the original contract by entering into the stipulation filed in the Johnson County water main damage suit. Defendant has appealed.

I. While this controversy is not governed by either Federal labor laws or the Federal Arbitration Act, Title 9, United States Code, we believe recent decisions rendered in those areas provide guidance in resolving our commercial arbitration problem. Hanes Corp. v. Millard, 174 U.S.App. D.C. 253, 531 F.2d 585, 599; National R. R. Passenger Corp. v. Missouri Pacific R. R. Co., 8th Cir., 501 F.2d 423, 427, 428.

Similarly, although Iowa has not adopted the Uniform Arbitration Act, we believe cases decided by sister states which have adopted that Act may properly be considered in our ultimate determination whether the arbitration award should be enforced pursuant to our Code chapter 679.

II. Defendant first contends trial court erred in its determination error was not preserved on the arbitrability issue. For the reasons hereinafter set forth we agree.

Trial court reasoned that defendant by entering into the Johnson County stipulation waived any rights it may have had under sections 7.10 and 9.7.6 of the construction contract to bar plaintiff’s damage claim. We do not believe a fair reading of the stipulation can support this conclusion.

In construing stipulations the court should always attempt to ascertain and give effect to the intention of the parties. 83 C.J.S. Stipulations § 11a, page 26.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JM 48, LLC v. Heartland Co-Op
918 N.W.2d 502 (Court of Appeals of Iowa, 2018)
Wesley Retirement Services, Inc. v. Hansen Lind Meyer, Inc.
594 N.W.2d 22 (Supreme Court of Iowa, 1999)
Modern Piping, Inc. v. Blackhawk Automatic Sprinklers, Inc.
581 N.W.2d 616 (Supreme Court of Iowa, 1998)
Regent Insurance Co. v. Estes Co.
564 N.W.2d 846 (Supreme Court of Iowa, 1997)
ML Park Place Corp. v. Hedreen
862 P.2d 602 (Court of Appeals of Washington, 1993)
Des Moines Asphalt & Paving Co. v. Colcon Industries Corp.
500 N.W.2d 70 (Supreme Court of Iowa, 1993)
Reicks v. Farmers Commodities Corp.
474 N.W.2d 809 (Supreme Court of Iowa, 1991)
Woodruff v. Associated Grocers of Iowa, Inc.
364 N.W.2d 215 (Supreme Court of Iowa, 1985)
Iowa City Community School District v. Iowa City Education Ass'n
343 N.W.2d 139 (Supreme Court of Iowa, 1983)
George H. Wentz, Inc. v. Sabasta
337 N.W.2d 495 (Supreme Court of Iowa, 1983)
Johnson Controls, Inc. v. City of Cedar Rapids, Iowa
713 F.2d 370 (Eighth Circuit, 1983)
Graen's Mens Wear, Inc. v. Stille-Pierce Agency
329 N.W.2d 295 (Supreme Court of Iowa, 1983)
Litchsinn v. American Interinsurance Exchange
287 N.W.2d 156 (Supreme Court of Iowa, 1980)
County of Jefferson v. Barton-Douglas Contractors, Inc.
282 N.W.2d 155 (Supreme Court of Iowa, 1979)
State Ex Rel. Miller v. National Farmers Organization
278 N.W.2d 905 (Supreme Court of Iowa, 1979)
Johnson v. Fireman's Fund Insurance Co.
272 N.W.2d 870 (Supreme Court of Iowa, 1978)
Union Pacific Railroad v. Johnson
264 N.W.2d 796 (Supreme Court of Iowa, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
255 N.W.2d 124, 1977 Iowa Sup. LEXIS 1092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawkinskorshoj-v-state-board-of-regents-iowa-1977.