Hawaiian Telephone Co. v. Microform Data Systems, Inc.

829 F.2d 919, 4 U.C.C. Rep. Serv. 2d (West) 1090, 1987 U.S. App. LEXIS 13425
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 9, 1987
Docket86-2181
StatusPublished
Cited by6 cases

This text of 829 F.2d 919 (Hawaiian Telephone Co. v. Microform Data Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawaiian Telephone Co. v. Microform Data Systems, Inc., 829 F.2d 919, 4 U.C.C. Rep. Serv. 2d (West) 1090, 1987 U.S. App. LEXIS 13425 (9th Cir. 1987).

Opinion

DAVID R. THOMPSON, Circuit Judge:

Microform Data Systems, Inc. (“MDS”) appeals the district court’s judgment in favor of Hawaiian Telephone Company (“HT”) in HT’s breach of contract action.

FACTS AND PROCEEDINGS

In 1978, MDS, a California corporation, contracted with HT, a Hawaii public utility, to manufacture and install a computerized directory system. The contract provided that MDS would complete installation of the host computer by February 16, 1979, and specified fifteen dates for MDS to install operator, supervisory, and training positions, beginning February 16 and ending April 20, 1979. Failure to meet these installation dates would trigger a penalty. This penalty, which the parties agreed would not exceed $100,000, was to accrue at the rate of $1,000 for each day installation was delayed, and was to be discounted from the system’s sales price. Additionally, if installation of the host computer by February 16, 1979 was “substantially delayed,” MDS agreed to provide HT with an interim backup system that would be fully operational by May 19, 1979. After installation, HT had five business days to reject the equipment if the system did not perform according to specifications. The specifications required that: (1) the system be able to handle 15,000 calls per hour, while maintaining a response time of one sec *921 ond; 1 (2) the system hardware and software be tested before shipping to demonstrate fourteen functional tasks; 2 (3) the system include “non-stop” hardware and software to ensure automatic recovery from any component failure; and (4) the system contain an HT data base which could be updated and loaded into the system’s memory daily.

In January 1979, HT representatives traveled to the MDS facilities in California to inspect the hardware and to observe the system perform. During testing, it was apparent that the system was not functionally operational even though the contract required the system to be operating by December 1, 1978. Seven key functions could not be demonstrated satisfactorily.

In February, MDS informed HT that factory acceptance testing would be delayed five weeks and that software development was behind schedule. MDS missed the February 16 installation date and was notified by HT that the installation penalties had been triggered. MDS did not notify HT that it would install the backup, nor did it exercise any rights it had under the agreement to provide the interim backup system. On February 28, MDS informed HT that factory acceptance testing would begin March 26, eight weeks behind schedule. MDS’ internal office memoranda indicated that it was still encountering serious problems with the system and that it did not have any feasible plans to solve these problems.

On April 6, 1979, HT representatives visited MDS and discovered that the system could not perform critical functions such as “non-stop” data base loading, multiple inquiry searching, and a one-second response time for business listings. The HT representatives concluded that MDS would require an additional nine to twelve months to bring the system up to specifications. On April 27, MDS informed HT that the system’s software would not be completed until September and that non-stop would not be included. MDS also proposed altering the system, adding hardware, and changing the data retrieval strategy. These proposed changes were unacceptable to HT.

By letter of May 8, 1979, HT notified MDS that it was canceling the contract because of serious development delays and MDS’ elimination of critical performance functions. On June 8, MDS’ president reported to the MDS board of directors that (1) the HT program was nine months or more behind schedule; (2) success in meeting specifications was “far from assured” even after an extended development period; and (3) MDS had accepted a cancellation of the contract from HT. Further MDS evaluations of the project indicated that it would take MDS one to two years and require at least three people working full time to bring the system up to specifications.

HT sued MDS for breach of contract in Hawaii state court on February 9, 1981. MDS removed the case on the basis of diversity to the United States District Court for the District of Hawaii. After a bench trial, the district court found that HT was entitled to cancel the agreement on May 8, 1979 because MDS had materially breached the agreement. The court concluded that under the provisions of the contract, HT had the right to give MDS notice of cancellation on May 8, 1979, or, in the alternative, HT did not need to give MDS prior notice of cancellation because by May 8, 1979, any obligation to give notice had been excused as a “useless act.” The district court also concluded that: (1) the provision in the agreement excluding consequential damages never became effective because MDS never installed a system; (2) the warranties failed of their essential purpose; and (3) because the breach was so total and fundamental, the exclusion of *922 consequential damages was unconscionable. The court entered judgment in favor of HT for $600,872, which included consequential damages of $295,982. The court also awarded HT $188,780 in attorney fees.

On appeal, MDS contends that the court erred (1) in finding MDS in breach of the agreement on May 8, 1979; (2) in concluding that HT could cancel the agreement without first complying with a contractual provision which required thirty days advance notice and an opportunity to cure; and (3) in awarding consequential damages. We have jurisdiction under 28 U.S.C. § 1291 and we affirm.

DISCUSSION

A. Standard of Review

We review de novo the district court’s interpretation of contractual provisions. United States v. City of Twin Falls, Idaho, 806 F.2d 862, 869 (9th Cir. 1986), cert, denied, — U.S.-, 107 S.Ct. 3185, 96 L.Ed.2d 674 (1987). We review the district court’s factual findings for clear error. Fed.R.Civ.P. 52(a); Anderson v. City of Bessemer City, 470 U.S. 564, 572, 105 S.Ct. 1504, 1511, 84 L.Ed.2d 518 (1985) (“even when the trial judge adopts proposed findings verbatim, the findings are those of the court and may be reversed only if clearly erroneous”).

In this diversity case, we apply conflict-of-law principles of the forum state, Hawaii. See, e.g., S.A. Empresa de Viacao Aerea Rio Grandense v. Boeing Co., 641 F.2d 746, 749 (9th Cir.1981). The contract provides that it shall be governed by California law. Under Hawaii law, “[w]hen the parties choose the law of a particular state to govern their contractual relationship and the chosen law has some nexus with the parties or the contract, that law will generally be applied.” Airgo, Inc. v. Horizon Cargo Transport, Inc., 66 Haw.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
829 F.2d 919, 4 U.C.C. Rep. Serv. 2d (West) 1090, 1987 U.S. App. LEXIS 13425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawaiian-telephone-co-v-microform-data-systems-inc-ca9-1987.