Hawa Construction, LLC v. Pollock

District Court, District of Columbia·Decided December 18, 2009·No. Civil Action No. 2009-1728·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

) HAWA CONSTRUCTION, LLC, ) ) Plaintiff-Counterdefendant, ) ) v. ) Civil Action No. 09-1728 (RMC) ) RICHARD M. POLLOCK, ) ) Defendant-Counterclaimant. ) )

MEMORANDUM OPINION

This dispute arises from Hawa Construction, LLC’s renovation of Richard M.

Pollock’s residence in Washington, D.C.1 Pending before the Court is Hawa Construction’s motion

to dismiss Count I of Mr. Pollock’s counterclaim [Dkt. # 9], which seeks disgorgement of $205,646

paid to Hawa Construction for change orders requested by Mr. Pollock and performed by Hawa

Construction but not reduced to writing as required by District of Columbia home improvement

regulations.2 For the reasons explained herein, the motion will be granted.

I. FACTS3

Mr. Pollock engaged the services of Hawa Construction to renovate and expand his

residence located in Northwest Washington, D.C. The parties entered into a written contract

whereby Hawa Construction would perform the renovation work for $2,129,057.

1 The Court has diversity jurisdiction under 28 U.S.C. § 1332(a). 2 All parties agree that District of Columbia law applies. 3 The facts are taken from Mr. Pollock’s counterclaim [Dkt. # 4] and are assumed to be true. Hawa Construction began work on the project in February 2008. Thereafter Mr.

Pollock considered requesting change orders to the specifications of the work and inquired whether

such contemplated change orders would cause him to incur additional costs. When Hawa

Construction responded that Mr. Pollock’s contemplated change orders would not increase the total

cost of the project, Mr. Pollock requested the change orders to the specifications of the work, and

Hawa Construction performed the change orders.

During the course of performance of the contract, Hawa Construction submitted nine

payment applications to Mr. Pollock and Mr. Pollock paid Hawa Construction a sum of

$1,903,405.07. After having done so, on June 4, 2009, Hawa Construction informed Mr. Pollock

that several subcontractors were owed substantial amounts of money for work they had performed

on the project, which surprised Mr. Pollock because he believed that Hawa Construction had fully

paid all subcontractors from the monies he paid to Hawa Construction.4 On June 17, 2009, Hawa

Construction abandoned the project. Thereafter Mr. Pollock paid the subcontractors a sum of

$69,815.84.

Of the $1,903,405.07 that Mr. Pollock paid Hawa Construction, $205,646 was for the

work associated with change orders # 1 through # 13, which Hawa Construction submitted in writing

to Mr. Pollock on June 17, 2009, after the work had been completed. Mr. Pollock never signed

change orders # 1 through # 13. In Count I of his counterclaim, Mr. Pollock alleges that change

orders # 1 through # 13 are void and unenforceable under the District of Columbia’s home

improvement regulations because they were not approved by him in writing, and he seeks

4 In each payment application Hawa Construction certified under oath that “all amounts have been paid by the contractor for work which previous Certificates for Payment were issued and payments received from the Owner.” Countercl. ¶ 12.

-2- disgorgement of the $205,646 that he paid Hawa Construction for work associated with those change

orders.

II. LEGAL STANDARD

A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) challenges

the adequacy of a complaint on its face, testing whether a plaintiff has properly stated a claim.

Federal Rule of Civil Procedure 8(a) requires that a complaint contain “a short and plain statement

of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a). A complaint must

be sufficient “to give a defendant fair notice of what the . . . claim is and the grounds upon which

it rests.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (internal citations omitted).

Although a complaint does not need detailed factual allegations, a plaintiff’s obligation to provide

the grounds of his entitlement to relief “requires more than labels and conclusions, and a formulaic

recitation of the elements of a cause of action will not do.” Id. The facts alleged “must be enough

to raise a right to relief above the speculative level.” Id. Rule 8(a) requires an actual showing and

not just a blanket assertion of a right to relief. Id. at 555 n.3. “[A] complaint needs some

information about the circumstances giving rise to the claims.” Aktieselskabet Af 21. Nov. 2001 v.

Fame Jeans, Inc., 525 F.3d 8, 16 n.4 (D.C. Cir. 2008) (emphasis in original).

A court must treat the complaint’s factual allegations as true, “even if doubtful in

fact.” Twombly, 550 U.S. at 555. But a court need not accept as true legal conclusions set forth in

a complaint. Ashcroft v. Iqbal, 129 S. Ct. 1937, 1949 (2009). “Threadbare recitals of the elements

of a cause of action, supported by mere conclusory statements, do not suffice.” Id. “While legal

conclusions can provide the framework of a complaint, they must be supported by factual

-3- allegations. When there are well-pleaded factual allegations, a court should assume their veracity

and then determine whether they plausibly give rise to an entitlement to relief.” Id. at 1950.

III. ANALYSIS

In Count I of his Counterclaim, Mr. Pollock alleges that Hawa Construction violated

Section 808.13 of title 16 of the District of Columbia Municipal Regulations, which provides that

“[t]here shall be no change in specifications [of home improvement contracts] without the written

approval of the homeowner.” 16 DCMR § 808.13. This is so, Mr. Pollock argues, because he never

approved change orders # 1 through # 13 in writing. See Countercl. ¶ 35.

The Court agrees that the regulation requires the homeowner’s written approval to

changes in specifications of home improvement contracts. However, because Hawa Construction

had fully performed the work associated with the requested change orders, Section 808.13 does not

operate to retroactively invalidate the executed oral agreement changing the specifications of the

work. See Thompson v. Wolfrey, 483 A.2d 636, 638 (D.C. 1984). In Thompson, the homeowner

argued that the contractor’s failure to put in writing the terms of their contract violated Section 808.1

of title 16 of the District of Columbia Municipal Regulations, which provides that “[n]o home

improvement contractor . . . shall accept any payment for home improvement work to be performed

for a homeowner until after the understanding between the homeowner and contractor . . . has been

reduced to writing . . . .” 16 DCMR § 808.1. In rejecting that argument, the District of Columbia

Court of Appeals reasoned that “[w]e agree that the regulation requires such contracts to be in

Free access — add to your briefcase to read the full text and ask questions with AI

Hawa Construction, LLC v. Pollock, (D.D.C. 2009).

Hawa Construction, LLC v. Pollock (Hawa Construction, LLC v. Pollock) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Tauber v. District of Columbia
511 A.2d 23 (District of Columbia Court of Appeals, 1986)
District of Columbia Housing Finance Agency v. Harper
707 A.2d 53 (District of Columbia Court of Appeals, 1998)
Hackney v. Morelite Construction
418 A.2d 1062 (District of Columbia Court of Appeals, 1980)
Thompson v. Wolfrey
483 A.2d 636 (District of Columbia Court of Appeals, 1984)