HAWA CONSTRUCTION, LLC v. Pollock

674 F. Supp. 2d 256, 2009 U.S. Dist. LEXIS 118518
CourtDistrict Court, District of Columbia
DecidedDecember 18, 2009
DocketCivil Action No. 09-1728 (RMC)
StatusPublished

This text of 674 F. Supp. 2d 256 (HAWA CONSTRUCTION, LLC v. Pollock) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HAWA CONSTRUCTION, LLC v. Pollock, 674 F. Supp. 2d 256, 2009 U.S. Dist. LEXIS 118518 (D.D.C. 2009).

Opinion

MEMORANDUM OPINION

ROSEMARY M. COLLYER, District Judge.

This dispute arises from Hawa Construction, LLC’s renovation of Richard M. Pollock’s residence in Washington, D.C. 1 Pending before the Court is Hawa Construction’s motion to dismiss Count I of Mr. Pollock’s counterclaim [Dkt. # 9], which seeks disgorgement of $205,646 paid to Hawa Construction for change orders requested by Mr. Pollock and performed by Hawa Construction but not reduced to writing as required by District of Columbia home improvement regulations. 2 For the reasons explained herein, the motion will be granted.

I. FACTS 3

Mr. Pollock engaged the services of Hawa Construction to renovate and expand his residence located in Northwest Washington, D.C. The parties entered into a written contract whereby Hawa Construction would perform the renovation work for $2,129,057.

Hawa Construction began work on the project in February 2008. Thereafter Mr. Pollock considered requesting change orders to the specifications of the work and inquired whether such contemplated change orders would cause him to incur additional costs. When Hawa Construction responded that Mr. Pollock’s contemplated change orders would not increase the total cost of the project, Mr. Pollock requested the change orders to the specifications of the work, and Hawa Construction performed the change orders.

During the course of performance of the contract, Hawa Construction submitted nine payment applications to Mr. Pollock and Mr. Pollock paid Hawa Construction a sum of $1,903,405.07. After having done so, on June 4, 2009, Hawa Construction informed Mr. Pollock that several subcontractors were owed substantial amounts of money for work they had performed on the project, which surprised Mr. Pollock because he believed that Hawa Construction had fully paid all subcontractors from the monies he paid to Hawa Construction. 4 On June 17, 2009, Hawa Construction abandoned the project. Thereafter Mr. Pollock paid the subcontractors a sum of $69,815.84.

Of the $1,903,405.07 that Mr. Pollock paid Hawa Construction, $205,646 was for the work associated with change orders # 1 through # 13, which Hawa Construction submitted in writing to Mr. Pollock on June 17, 2009, after the work had been completed. Mr. Pollock never signed change orders # 1 through # 13. In Count I of his counterclaim, Mr. Pollock alleges that change orders # 1 through # 13 are void and unenforceable under the District of Columbia’s home improvement regulations because they were not ap *258 proved by him in writing, and he seeks disgorgement of the $205,646 that he paid Hawa Construction for work associated with those change orders.

II. LEGAL STANDARD

A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) challenges the adequacy of a complaint on its face, testing whether a plaintiff has properly stated a claim. Federal Rule of Civil Procedure 8(a) requires that a complaint contain “a short and plain statement of the claim showing that the pleader is entitled to relief.” Fed.R.Civ.P. 8(a). A complaint must be sufficient “to give a defendant fair notice of what the ... claim is and the grounds upon which it rests.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (internal citations omitted). Although a complaint does not need detailed factual allegations, a plaintiffs obligation to provide the grounds of his entitlement to relief “requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Id. The facts alleged “must be enough to raise a right to relief above the speculative level.” Id. Rule 8(a) requires an actual showing and not just a blanket assertion of a right to relief. Id. at 555 n. 3, 127 S.Ct. 1955. “[A] complaint needs some information about the circumstances giving rise to the claims.” Aktieselskabel AF 21. Nov. 2001 v. Fame Jeans, Inc., 525 F.3d 8, 16 n. 4 (D.C.Cir.2008) (emphasis in original).

A court must treat the complaint’s factual allegations as true, “even if doubtful in fact.” Twombly, 550 U.S. at 555, 127 S.Ct. 1955. But a court need not accept as true legal conclusions set forth in a complaint. Ashcroft v. Iqbal, — U.S. -, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009). “Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice.” Id. “While legal conclusions can provide the framework of a complaint, they must be supported by factual allegations. When there are well-pleaded factual allegations, a court should assume their veracity and then determine whether they plausibly give rise to an entitlement to relief.” Id. at 1950.

III. ANALYSIS

In Count I of his Counterclaim, Mr. Pollock alleges that Hawa Construction violated Section 808.13 of title 16 of the District of Columbia Municipal Regulations, which provides that “[tjhere shall be no change in specifications [of home improvement contracts] without the written approval of the homeowner.” 16 DCMR § 808.13. This is so, Mr. Pollock argues, because he never approved change orders # 1 through # 13 in writing. See Countercl. ¶ 35.

The Court agrees that the regulation requires the homeowner’s written approval to changes in specifications of home improvement contracts. However, because Hawa Construction had fully performed the work associated with the requested change orders, Section 808.13 does not operate to retroactively invalidate the executed oral agreement changing the specifications of the work. See Thompson v. Wolfrey, 483 A.2d 636, 638 (D.C.1984). In Thompson, the homeowner argued that the contractor’s failure to put in writing the terms of their contract violated Section 808.1 of title 16 of the District of Columbia Municipal Regulations, which provides that “[n]o home improvement contractor ... shall accept any payment for home improvement work to be performed for a homeowner until after the understanding between the homeowner and contractor ... has been reduced to writing....” 16 DCMR § 808.1. In rejecting that argu *259

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Tauber v. District of Columbia
511 A.2d 23 (District of Columbia Court of Appeals, 1986)
District of Columbia Housing Finance Agency v. Harper
707 A.2d 53 (District of Columbia Court of Appeals, 1998)
Hackney v. Morelite Construction
418 A.2d 1062 (District of Columbia Court of Appeals, 1980)
Thompson v. Wolfrey
483 A.2d 636 (District of Columbia Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
674 F. Supp. 2d 256, 2009 U.S. Dist. LEXIS 118518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawa-construction-llc-v-pollock-dcd-2009.