Havens v. Safeway Stores

678 P.2d 625, 235 Kan. 226, 1984 Kan. LEXIS 290
CourtSupreme Court of Kansas
DecidedMarch 24, 1984
Docket55,854
StatusPublished
Cited by21 cases

This text of 678 P.2d 625 (Havens v. Safeway Stores) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Havens v. Safeway Stores, 678 P.2d 625, 235 Kan. 226, 1984 Kan. LEXIS 290 (kan 1984).

Opinion

The opinion of the court was delivered by

Holmes, J.:

Defendant L. R. Foy Construction Co., Inc. (Foy) appeals from a judgment granted plaintiff Jim Havens d/b/a Havens Construction Company (Havens) in a dispute between Foy, the general contractor, and Havens, a subcontractor, over performance of a construction contract. The trial court rendered judgment for Havens in the amount of $40,422.00 and Foy has appealed. The case was transferred from the Court of Appeals pursuant to K.S.A. 20-3018(c).

Foy was the general contractor for the construction of a new building for Safeway Stores, Inc. (Safeway) in Liberal, Kansas. *227 Havens, a cement contractor, submitted a proposal to do the concrete work for $124,000.00 which was accepted by Foy and the two entered into a written contract in March, 1980. Under the contract plaintiff undertook to furnish all material, equipment and labor necessary for the complete cast-in-place concrete portion of the work to be performed in strict accordance with the plans and specifications prepared by Safeway and its architect. The instant case arose from a dispute over the method of payment and certain alleged breaches of the contract by Havens. Prior to the beginning of construction, Foy held a meeting with all the subcontractors at which representatives of Safeway outlined their method of payment. The subcontractors were to submit to Foy, as general contractor, an invoice by the 25th day of each month setting forth the amount claimed to be due for work performed. They were then to be paid for 90% of the amount claimed if it was found to be the correct amount based upon the percent of the work completed. Foy, after checking and verifying the percent of work completed and amount claimed, would then send all of the invoices to Safeway in Oklahoma City. If that office approved the invoices they were then returned to Foy, who would forward them to Safeway headquarters in Oakland, California. In due course the Oakland office would send one check for the approved amount to Foy who in turn paid the subcontractors. This rather lengthy procedure might take from four to six weeks depending upon how fast each party to the procedure processed the necessary paper work.

Havens commenced work on March 20, 1980, but did not submit an invoice for any of his work until April 23, 1980. As he had only worked a few days in March, he evidently chose to combine the March and April invoices in a total amount of $24,000.00. Foy combined this invoice with those from other subcontractors and sent them to the Oklahoma City division of Safeway. That office checked, verified, and approved the invoices for payment and mailed them back to Foy. Foy then forwarded these invoices to Safe way’s Oakland, California office for payment. A check was drawn by that office on May 23, sent to Foy, and Havens received payment on May 31. Thus there was a time interval of thirty-six days between April 25 and payment to Havens. This was the standard process for payment on the invoices, and was explained to the subcontractors at a meeting *228 before they began work. There is a dispute about the date the May invoice was received by Foy but it was dated May 23 and processed through the Oklahoma City and Oakland offices of Safeway. The check from Safeway was drawn July 3, 1980, and mailed to Foy who in turn was to pay the subcontractors. Thirty-nine days elapsed between the May 25 invoicing date and the drawing of the check at Oakland. Foy received the check within a few days thereafter.

During this time, Havens experienced several difficulties with the construction project. He was unable to keep an adequate number of men on the job to ensure work progressed in a timely fashion, and Foy responded by furnishing Havens with additional help. Contrary to Article XIII of the contract, Havens employed other subcontractors on the job without Foy’s permission. Weather problems were encountered, but Havens submitted no requests for additional time for these delays as he was entitled to under the contract. Finally, the cement work Havens completed met neither the specifications for levelness nor strength.

On May 31, 1980, Foy served Havens with a 72-hour deficiency notice under Article V of the contract. Havens put more men on the job in an effort to catch up with the schedule, but to no avail. Claiming a lack of money to meet his payroll and pay for his supplies, Havens discontinued his work and walked off the job on July 3, 1980, and never returned. It then became necessary for Foy to find a new cement contractor to remedy the alleged deficiencies in Havens’ work and complete the concrete work.

Thereafter Havens filed suit against Foy and Safeway seeking recovery of $62,542.00 which he alleged was the balance due for the work he had completed. There were numerous procedural questions in the trial court involving the filing of a mechanic’s lien by Havens and the joining of certain bonding companies as parties defendant. However, the issues on appeal are solely between Havens and Foy and we will make no further reference to the other parties. Prior to answering, Foy filed a motion seeking to have the dispute arbitrated, which it alleged was required by the contract. When this motion was denied Foy filed an answer and a counterclaim for actual and punitive damages for alleged breach of the contract by Havens and alleged willful *229 and malicious conduct of Havens. Following a trial to the court judgment was rendered in favor of Havens for $40,422.00. The trial court found that Foy had breached the contract with Havens by failing to make timely payments in accordance with the prevailing industry practice which the court found called for payment every thirty days. Foy has appealed.

In the first issue on appeal Foy claims the trial court erred in failing to order arbitration pursuant to the contract and the Uniform Arbitration Act. In support of this contention, Foy points to Article II of the contract:

“All disputes, claims or questions subject to arbitration under this contract shall be submitted to arbitration in accordance with the provisions as contained in the standard form of the American Institute of Architects general conditions of the contract for the construction of buildings.” (Emphasis added.)

and to K.S.A. 5-401:

“Validity of arbitration agreement. A written agreement to submit any existing controversy to arbitration or a provision in a written contract, other than a contract of insurance or a contract between an employer and employees or between their respective representatives, to submit to arbitration any controversy, other than a claim in tort, thereafter arising between the parties is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract.”

Foy’s position is that arbitration applies to all controversies arising under its contract with Havens. Havens, however, points out the clear language of the contract does not require arbitration for every

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trear v. Chamberlain
425 P.3d 297 (Supreme Court of Kansas, 2018)
Ribeau v. Katt
681 F.3d 1190 (Tenth Circuit, 2012)
Hartford Fire Ins. Co. v. P & H Cattle Co., Inc.
451 F. Supp. 2d 1262 (D. Kansas, 2006)
Amoco Production Co. v. Charles B. Wilson, Jr., Inc.
976 P.2d 941 (Supreme Court of Kansas, 1999)
Federal Land Bank v. Vann
890 P.2d 1242 (Court of Appeals of Kansas, 1995)
Boos v. National Federation of State High School Ass'n
889 P.2d 797 (Court of Appeals of Kansas, 1995)
Colburn v. Parker & Parsley Development Co.
842 P.2d 321 (Court of Appeals of Kansas, 1992)
Thomas v. Thomas
824 P.2d 971 (Supreme Court of Kansas, 1992)
Marsh v. Coleman Co., Inc.
774 F. Supp. 608 (D. Kansas, 1991)
Kennedy & Mitchell, Inc. v. Anadarko Production Co.
754 P.2d 803 (Supreme Court of Kansas, 1988)
Zurn Constructors, Inc. v. B.F. Goodrich Co.
685 F. Supp. 1172 (D. Kansas, 1988)
Stewart v. Brennan
748 P.2d 816 (Hawaii Intermediate Court of Appeals, 1988)
Craig Food Industries, Inc. v. Weihing
746 P.2d 279 (Court of Appeals of Utah, 1987)
CAT Aircraft Leasing, Inc. v. Cessna Aircraft Co.
650 F. Supp. 57 (Virgin Islands, 1986)
Holly Energy, Inc. v. Patrick
722 P.2d 1073 (Supreme Court of Kansas, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
678 P.2d 625, 235 Kan. 226, 1984 Kan. LEXIS 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/havens-v-safeway-stores-kan-1984.