Havens v. Dallas Power & Light Co.

256 S.W.2d 689, 1953 Tex. App. LEXIS 2282
CourtCourt of Appeals of Texas
DecidedMarch 13, 1953
Docket14610
StatusPublished
Cited by9 cases

This text of 256 S.W.2d 689 (Havens v. Dallas Power & Light Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Havens v. Dallas Power & Light Co., 256 S.W.2d 689, 1953 Tex. App. LEXIS 2282 (Tex. Ct. App. 1953).

Opinion

YOUNG, Justice.'

Appellant Plavens instituted -this suit against Dallas Power & Light Company for recovery of damages. The occasion. was this: While in course or erecting a sign on roof of the new Johnson Bros. Chevrolet'warehouse, Industrial"District, Dallas,'a steel rod he was -handling' made contact with a high voltage line owned and maintained by appellee, with result of a violent' electrical shock' and serious personal injuries. National Automobile Casualty Insurance Company ■ intervened to claim re-coupment of $14,440.95 paid out in compensation benefits to Plenry Havens; defendant in due course filing motion for summary judgment,: alleging nonexistence of genuine issues concerning any material facts. Upon hearing and consideration of pleadings, depositions, . affidavits, photographs, drawings, and stipulations relating to location of the building in question, sign upon which Havens was working, size and capacity of defendant’s power lines located in the vicinity, the motion was sustained, with take nothing judgment in accordance; and timely appeal from such adverse rendition.

The locale of injury was on Payne Street, running generally east and west, *690 near its intersection with Industrial Boulevard, a street running north and south. The particular distribution line of defendant was installed in September -1947 on a series of telephone poles along the north side of Payne Street and within the dedicated portion thereof some seven feet south of the property line of lots adjacent to Payne Street at northwest corner of Payne and Industrial Boulevard, where Johnson Bros, later erected this warehouse. High-tension wires (13,000 volt potential), 32.5 ft. above the ground, were there mounted on top cross-arms of two poles 90 ft. apart.

According to affidavit of R. D. Meador, general contractor (plaintiff’s Exhibit A), construction of Johnson Bros, warehouse was begun during March 1949 and completed in July; the only activity from July 10 to August 1st 'being the placing of lugs on steel trusses so that a sign could be in-' stalled. Plaintiff was working as a welder on the job throughout. The warehouse sat well back from and faced Industrial Boulevard; the sign running along roof at east wall; construction of the sign beginning August 1 and plaintiff sustaining injury on August 4, 1949.

The following dimensions were stipulated: Vertical: From base of sign on east side of warehouse to north high-tension wire, 14.5 ft.; height of sign on same side of building, 10.8 ft.; top of roof at highest point to northernmost wire, 8 ft.; top of sign at east side of warehouse to most northern wire, 4.4 ft.; from the ground to northernmost wire at southeast corner of building 32.5 ft.; southwest corner of building roof to most northerly wire, 18.5 ft. Horizontal distances: Center line of west pole to south edge of building, 7 ft.; center line of top of west pole to south end of building, 6.1 ft.; northernmost wire to southwest corner of building, 2.5 ft.; northernmost wire to south end of building, southeast comer, 3 ft.; northernmost wire to south end of the sign frame on east side of building, 3 ft.; distance from west pole to east pole, 90.3 ft. The situation with respect to defendant’s equipment remained unchanged from 1947 to date except that on October 25, 1949 (after the injury) Johnson Bros, applied-for service at the warehouse and a connection was made off of the west pole, consisting of a three-wire drop.

We will here adopt appellant’s narrative, explanatory of injuries, as recited in his brief: “In order to bring construction material up onto the roof where he was working, the plaintiff took a position on a horizontal cross member in the framework of the sign approximately five feet above the roof of the building. As 'he stood on this structural steel member, he reached down and brought a piece of structural steel approximately fifteen or twenty feet long up onto the roof from a co-worker on the ground. As he was bringing the rod up hand over hand, it made electrical contact with the high voltage line of the defendant. This line carried a large current of electricity, having an electrical potential between phases of approximately thirteen thousand volts and an electrical potential between the wire and the ground of seven thousand six hundred twenty volts. Instantaneous with this contact the plaintiff received a severe electrical shock. The current passed through both his hands and through hjs back, causing severe burns.. He was hurled backward onto the roof of the warehouse on which he was working. After receiving these injuries, the plaintiff remained in the hospital for three months. His hospital bill was approximately Sixteen Hundred Dollars ($1600.00), 'and his bills for doctors’ and nurses’ services amounted to approximately Four Thousand Five Hundred Dollars ($4,500.00). It was necessary to amputate the thumb and first finger of plaintiff’s left hand, and the remaining fingers on both hands are contracted like claws and have practically no motion.”

Appellant asserts error in the trial court’s grant of defendant’s motion for summary judgment; in that, he says, (1) a fact question exists “as to whether or not the defendant had notice of the condition on the premises and the danger resulting therefrom by reason of the dose proximity of the roof of the building to the high voltage wires of the defendant”; (2) “as to whether or not the defendant was guilty of negligence proximately -causing the injuries of plaintiff”; and (3) “as to whether or not *691 the plaintiff was guilty of negligence proximately causing the injuries sustained by him.”

The facts relied on in this connection as constituting notice to. defendant of actual conditions on the warehouse job and danger incident to adjacency of defendant’s high voltage wires to building roof will be outlined briefly. The previous year (1948) defendant had established a salvage depot also on Payne Street but farther to the west from Industrial Boulevard. It was in charge of L. E. Eads, salvage supervisor and purchaser for the Light Company, with some five employees under his direction and control. It was their duty to pick up material at other points in Dallas and convey same to the salvage house, .using either Payne or Levee Street in their trips; Eads, by deposition, stating that he had observed the Johnson Bros, warehouse under construction from time to time, seeing workmen there; that he had nothing to do with maintenance of defendant’s distribution lines either as to keeping them up, .salvaging, or tearing them down; neither was the duty of lookout for proper clearances of power lines any part of his business or of the employees under him. Leslie Bur-ford, Superintendent of distribution for defendant, by deposition testified that he had no notice (other than happening of the accident) that the Johnson warehouse had been erected until they made request for electric service more than three months thereafter.

Art. 1436a, Vernon’s Ann.Civ.St, regulating corporations dealing in electric energy, requires their lines to be constructed, operated, and maintained “as to clearances” in accordance with the National Electrical Safety Code and that same shall be at least 22 ft. “above the surface of the traffic lane.” Such Code, paragraph 234, under heading “C. 4.” “Conductors Passing by or over Buildings” (emphasis ours), involving wires of 8,700 to 15,000 voltage, calls for clearance of 8 ft. either horizontal or vertical.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Power & Light Co. v. Martinez
806 S.W.2d 892 (Court of Appeals of Texas, 1991)
Houston Lighting & Power Company v. Brooks
336 S.W.2d 603 (Texas Supreme Court, 1960)
Texas Power & Light Company v. Jacobs
323 S.W.2d 483 (Court of Appeals of Texas, 1959)
HOUSTON LIGHTING AND POWER COMPANY v. Brooks
319 S.W.2d 427 (Court of Appeals of Texas, 1958)
Texas Power & Light Co. v. Peterson
288 S.W.2d 247 (Court of Appeals of Texas, 1956)
Loud v. Sears, Roebuck & Co.
262 S.W.2d 548 (Court of Appeals of Texas, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
256 S.W.2d 689, 1953 Tex. App. LEXIS 2282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/havens-v-dallas-power-light-co-texapp-1953.