Opinion

LEVY, J.

[¶ 1] These separate proceedings both concern whether Winter Danforth Corporation’s (WDC) operation of its bed and breakfast guesthouse violates the terms of a contract zone agreement it entered into with the City of Portland. In Barbara Hathaway v. City of Portland, Barbara Hathaway, WDC’s president and sole shareholder, appeals from a judgment entered in the Superior Court (Cumberland, Crowley, J.) dismissing her complaint seeking a declaratory judgment for want of a justiciable controversy. In Winter [1170]*1170Danforth Corp. v. City of Portland, WDC appeals from a judgment entered in the Superior Court (Cumberland, Alexander, J.) pursuant to M.R. Civ. P. 80B affirming a decision of the City of Portland Zoning Board of Appeals (ZBA) affirming the determination by the City’s Zoning Administrator that WDC violated the terms of the contract zone agreement. We affirm the dismissal of Hathaway’s declaratory judgment action, but conclude in WDC’s 80B appeal that the Zoning Administrator’s finding of a breach of the agreement should have been reviewed by the Planning Board and not the ZBA, and vacate the Superior Court’s judgment.

I. BACKGROUND

[¶ 2] WDC operates a bed and breakfast guesthouse at 163 Danforth Street. Nearby, Hathaway leases an apartment at 188 Danforth Street. Both buildings are located in the R-6 Zone, a residential zone that does not permit business uses. In 1996, WDC received permission from the City to operate its business at 163 Danforth pursuant to a contract zone agreement. Hathaway is not a party to this contract.

[¶ 3] The contract zone agreement provides that “[t]he bed and breakfast use shall be limited to a maximum of nine (9) guest rooms ... [and] [m]eals may be offered only to guests of the bed and breakfast ....” It also states “in the event of a breach of any condition(s) set forth in this Agreement, the Planning Board shall have the authority, after hearing, to resolve the issue resulting in the breach or the failure to operate.”

[¶ 4] Recently, Hathaway’ has used her apartment at 188 Danforth Street to accommodate overflow guests of WDC. After discovering that the City’s planning department believed that WDC was in violation of the contract zone by accommodating overflow guests at 188 Danforth, Hathaway filed a complaint against the City seeking declaratory relief. Her complaint asserts that her activities at 188 Danforth Street do not constitute a violation of Portland’s Land Use Code (Code) and that WDC’s activities at 188 Danforth Street do not constitute a breach of the contract zone agreement.

[¶ 5] The City sought the dismissal of Hathaway’s declaratory judgment action for her failure to exhaust administrative remedies available under the Code. It claimed that Hathaway should have first sought an interpretation appeal from the Zoning Board of Appeals. The court granted the City’s motion, but on different grounds; it found that the complaint failed to state a claim upon which relief may be granted.

[¶ 6] During the pendency of Hathaway’s declaratory judgment action, the City’s Zoning Administrator sent WDC a Notice of Violation on December 20, 2002. It stated that WDC had violated the contract zone agreement by using 188 Dan-forth to accommodate overflow guests, and that its use of 188 Danforth Street violates §§ 14-135 and 14-138 of the City’s Land Use Code, which prohibits business uses in the R-6 Zone. The notice stated that WDC must file an appeal of the administrator’s decision with the ZBA within thirty days or it would be time-barred.

[¶ 7] WDC appealed the Zoning Administrator’s determination to the ZBA and argued, among other things, that the forum selection provision of the contract zone agreement required that the matter be heard by the Planning Board, and not the ZBA. After a public hearing, the ZBA affirmed the decision of the Zoning Administrator by a 3-2 vote, finding that the Zoning Administrator’s determination that “163 Danforth St. ... has violated the terms of their Contract Zone ...” was proper. Because the ZBA found that WDC violated the agreement, it did not [1171]*1171reach the issue of whether WDC’s use of the apartment at 188 Danforth violates the Code. The ZBA also did not address WDC’s argument regarding the forum selection provision of the contract zone agreement. WDC appealed from the order of the ZBA, and the Superior Court affirmed the ZBA’s decision.

[¶ 8] Hathaway and WDC appealed from the courts’ decisions and, at Hathaway’s request, we consolidated the appeals.

II. DISCUSSION

A. Hathaway v. City of Portland

[¶ 9] Hathaway contends that the court erred by dismissing the action based on its conclusion that there is no justiciable controversy between Hathaway and the City. We review the court’s grant of a motion to dismiss de novo for errors of law. Persson v. Dep’t of Human Servs., 2001 ME 124, ¶ 8, 775 A.2d 363, 365 (“The legal sufficiency of a complaint challenged by a motion to dismiss is a question of law subject to de novo review by this Court.”) (internal quotations omitted).

[¶ 10] The Superior Court concluded that Hathaway’s complaint failed to state a claim ripe for judicial decision:

In the instant case, Plaintiff alleges that the City of Portland has threatened action against her as an individual. Compl. ¶ 16. There is no allegation of an action pending against the Plaintiff. In fact, Plaintiff acknowledges that she has not been served “with any notice of violation,” Compl. ¶ 17, and that she “is not a party to the administrative proceedings,” referencing the letter from the City. Pi’s Opp’n to Mot. To Dismiss at 5. Under these facts, taken as true, there is no evidence of an “actual controversy” between the Plaintiff, as an individual, and the City of Portland that is fit for judicial decision at this time.

[¶ 11] A complaint seeking a declaratory judgment must establish that there is a genuine controversy between the parties. “[A] party seeking declaratory relief must establish that his case constitutes an active dispute of real interests between the litigants.” Randlett v. Randlett, 401 A.2d 1008, 1011 (Me.1979) (internal quotations omitted). A justiciable case or controversy involves “a claim of present and fixed rights, as opposed to hypothetical or future rights, asserted by one party against another who has an interest in contesting the claim.” Connors v. Int’l Hawester Credit Corp., 447 A.2d 822, 824 (Me.1982).

[¶ 12] Hathaway’s complaint asserts that it is brought pursuant to 14 M.R.S.A. § 5954 (2003), which provides, in pertinent part, that “[a]ny person ... whose rights ... are affected by a ... municipal ordinance ... may have determined any question of construction or validity arising under the ... ordinance.” The complaint does not, however, cite to any specific provision of the Code as affecting Hathaway’s rights, other than citing to the contract zone agreement between WDC and the City.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Dahlem v. City of Saco
2024 ME 32 (Supreme Judicial Court of Maine, 2024)
Copp v. Town of Gray
Maine Superior, 2023
DCCC and DSCC v. Dunlap
Maine Superior, 2020
Daniel R. Lawson v. Debby Willis
2019 ME 36 (Supreme Judicial Court of Maine, 2019)
Lawson v. Willis
204 A.3d 133 (Supreme Judicial Court of Maine, 2019)
Opinion of the Justices
2017 ME 100 (Supreme Judicial Court of Maine, 2017)
Bank of America, N.A. v. Scott Greenleaf
2015 ME 127 (Supreme Judicial Court of Maine, 2015)
Celli v. Friend Fort Knox
Maine Superior, 2005
Gensheimer v. Town of Phippsburg
2005 ME 22 (Supreme Judicial Court of Maine, 2005)
Melanson v. Secretary of State
2004 ME 127 (Supreme Judicial Court of Maine, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2004 ME 47, 845 A.2d 1168, 2004 Me. LEXIS 48, 2004 WL 745060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hathaway-v-city-of-portland-me-2004.