Opinion

OPINION

GEMMILL, Judge;

¶ 1 Gary and Bobbie Solomon, husband and wife, and Sol’s Construction Co. (collectively “Solomon”) appeal from the trial court’s judgment imposing indemnity liability in favor of Jason and Shannon Hatch, husband and wife, and Hatch Development, LLC (collectively “Hatch”). For the following reasons, we affirm.

BACKGROUND

¶ 2 Hatch filed a complaint seeking indemnity against Solomon in September 2011. The indemnity complaint alleged that Hatch, Solomon, and the Town of Taylor were sued in 2007 by Lee and Debbie Hunt (“Hunts”) for water damage caused by sewer and water line construction work Solomon performed on Hatch’s property. The indemnity complaint further alleged that Solomon was solely responsible for the sewer and water line construction and had left sewer line trenches open, resulting in the water damage to the Hunts’ property. Finally, the indemnity complaint alleged that Hatch and the Town of Taylor settled the lawsuit with the Hunts to avoid litigation costs. Hatch claimed that Solomon, who was not a party to the settlement agreement, was liable to Hatch for indemnity-

¶ 3 Solomon filed an answer and counterclaim denying liability and alleging that Hatch was not entitled to indemnification because he also was negligent and because the statute of limitations had run on the Hunts’ claim against Solomon before the settlement agreement was signed. Both parties filed motions for summary judgment. Hatch submitted his own declaration and declarations from a civil engineer who had inspected the work site and from the attorney who *174 represented Hatch in the settlement with the Hunts. Solomon submitted his own affidavit. After oral argument, the trial court granted Hatch’s motion for partial summary judgment on Solomon’s indemnity liability and denied Solomon’s motion for summary judgment.

¶4 Solomon filed motions to reconsider, asserting newly discovered evidence. He submitted an inspection report and an affidavit from an engineer regarding sewer line approval. The trial court authorized Hatch to respond to the motions. Hatch submitted a second personal declaration, along with declarations from an engineer and also a legal secretary who had worked for the firm representing Hatch during settlement negotiations. After oral argument, the court denied the motions to reconsider. The trial court later granted Hatch’s motions for summary judgment on damages and on the counterclaim, and entered judgment in favor of Hatch in the amount of $263,697.65, plus costs, as well as attorney fees in the amount of $51,997.40.

¶ 5 Solomon timely appeals, and we have jurisdiction under Atizona Revised Statutes (“A.R.S.”) sections 12-120.21(A)(1) and 12-2101(A)(1).

ANALYSIS

¶ 6 Solomon challenges the summary judgment holding him liable on Hatch’s indemnity claim. We review a trial court’s grant of summary judgment de novo, “viewing the evidence and reasonable inferences in the light most favorable to the party opposing the motion.” Felipe v. Theme Tech Corp., 235 Ariz. 520, 528, ¶ 31, 334 P.3d 210, 218 (App. 2014) (quoting Andrews v. Blake, 205 Ariz. 236, 240, ¶ 12, 69 P.3d 7, 11 (2003)). A trial court “shall grant summary judgment if the moving party shows that there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law.” Ariz. R. Civ. Proc. 56(a). 1

I. Consideration of the Statute of Limitations

¶7 To address Solomon’s arguments on appeal, a timeline of pertinent dates is instructive:

• April 2007—Solomon began work installing sewer lines on Hatch’s property-
• July 19, 2007—A large rainfall occurred, and Hatch was informed that muddy water had appeared in the sewer line. Hatch informed Solomon of the muddy water and Solomon assured Hatch he would take preventative measures.
• July 22, 2007—A second large rainfall occurred, overwhelming the sewer system, flooding the Hunts’ home and causing extensive damage.
• July 15, 2008—The Hunts filed a complaint against Hatch, Solomon, and the Town of Taylor, seeking damages for the harm they sustained due to the water.
• July 14, 2009—The Hunts’ complaint was dismissed for lack of prosecution.
• January 14, 2010—According to declarations by Hatch and his attorney, an oral settlement agreement among Hatch, the Town of Taylor, and the Hunts was reached by this date. An uneontested declaration from Hatch’s attorney states that the Hunts had a right to refile the action after it was dismissed for lack of prosecution but did not do so “in reliance upon the representations of both Hatch and the Town of Taylor that each party would continue to pursue the settlement as agreed.”
• January 21, 2010—The settlement was memorialized by a written settlement *175 agreement and contract for sale and purchase of property (“SAC”) and full and final release of claims and covenant not to sue (“FFR”). Solomon was not a party to either document.
• March 9, 2010—The SAC was fully executed.
• July 2, 2010—The FFR was fully executed.
• September 2011—Hatch filed his indemnity complaint against Solomon.

¶ 8 Solomon contends that the two-year statute of limitations for injuries to property had run on the Hunts’ claims against him by the time the settlement agreement was finalized. Citing a footnote in MT Builders, L.L.C. v. Fisher Roofing, Inc., 219 Ariz. 297, 303 n. 2, ¶ 13, 197 P.3d 758, 764 n. 2 (App. 2008), Solomon then concludes that Hatch cannot prove essential elements of common law indemnity—that the indemnity plaintiff (Hatch) and indemnity defendant (Solomon) owed a legally enforceable obligation to the third party (the Hunts).

A. Solomon’s Legal Obligation to the Hunts

¶ 9 Footnote 2 in MT Btdlders sets forth a three-pronged test for proving common law indemnity under certain circumstances:

In general, in an action for common law indemnity, the indemnity plaintiff must show, first, it has discharged a legal obligation owed to a third party; second, the indemnity defendant was also liable to the third party; and third, as between itself and the defendant, the obligation should have been discharged by the defendant. Absent consent or fault of the defendant, the plaintiff must show it has extinguished its own and the defendant’s liability to prove it has discharged the obligation to the third party in satisfaction of the first element.

219 Ariz. at 303 n. 2, ¶ 13, 197 P.3d at 764 n. 2 (emphasis added). Solomon’s reliance on these three prongs is misplaced, however, because—as the second sentence quoted above reveals—the three-pronged test in the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KAUFMAN v. GUEVARA
Court of Appeals of Arizona, 2025
Arpaio v. Hines Gs
Court of Appeals of Arizona, 2018

Cite This Page — Counsel Stack

Bluebook (online)
377 P.3d 368, 240 Ariz. 171, 741 Ariz. Adv. Rep. 9, 2016 Ariz. App. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hatch-development-llc-v-solomon-arizctapp-2016.