Hartmann-Clark Bros. v. State

17 Ill. Ct. Cl. 99, 1947 Ill. Ct. Cl. LEXIS 26
Court of Claims of Illinois·Decided November 12, 1947·No. No. 3290·Published

Opinion

Eckert, C. J..

During the year 1982, claimant, a general building contractor, having its principal office at Peoria, Illinois, entered into a series of nine contracts with the State of Illinois, for the construction of certain concrete highways. Under the terms of these contracts the respondent agreed to furnish the necessary cement. Claimant thereafter began work, supplying, transporting, and installing the necessary machinery, tools and equipment- at the situs of the work; securing workmen and laborers, and perfecting an organization in connection with each contract until it was forced to suspend operations because of respondent’s failure to supply cement. Claimant alleges that this failure interrupted and delayed the prosecution of claimant’s work; that it prevented claimant from completing its work in an orderly, usual, and economical manner, and in sequence; that it caused claimant ’s men and equipment to remain idle; and that it compelled claimant to pay an increased cost of gasoline, materials and labor. The total damages claimed are in the amount of $137,649.92.

The contracts provided that the work be done according to the Standard Specifications for Road and Bridge Construction of the Division of Hig'hways, adopted January 2, 1932. Work was begun on six of the contracts in the fall of 1932, and was suspended in November and .December when all work was shut down for the winter season. During the month of February, 1933, respondent notified claimant to file requisition for cement requirements on this projects not later than March 1st, and claimant accordingly thereafter filed requisitions for cement, requesting delivery by April 10th to April 14th. Claimant was ready to proceed with the paving work at that time, and in two instances two adjoining contracts were to be worked with the same paving units and equipment. The cement, however, was not made available to claimant when requested, and was not furnished until the 26th of June for three contracts. not until the 28th of June for three other contracts, and not until the 7th of July for two contracts.

From the time claimant was ready to proceed with the paving, until the cement was available, all of claimant’s equipment and organization were idle. Continued requests were made of the respondent during that period, and conferences were had between claimant and the Division of Highways. Claimant alleges that as a result of respondent’s failure to furnish cement as and when requested, claimant’s equipment and organization remained idle a total of 310 days. The fair rental value of this equipment, based upon the schedule of Equip7 ment Ownership Expense, published by the Associated G-eneral Contractors of America, would be $63,990.34.

Another element of damage alleged by claimant is general overhead amounting to $38,753.10. This amount was determined by computing its overhead for the year 1933, which, based on an eight month construction season, amounted to $15,001.75 per month. This was divided among four paving units, amounting to $3,750.44 per unit, or a total expense of $125.01 per. paving unit per day.

Claimant also alleges a loss of profits which it contends it could have earned during the period of idleness. This was found by taking the average profit for the preceding six years, which, based on an eight month construction season, and allocated to four units, amounted to $53.39 per day per unit, or a total of $16,550.90.

Other damages sought by the claimant consist of the following items:

Transporting paving unit to Altamont, Illinois, at the direction of respondent........................................$ 884.21
Maintaining night watchman............................... 124.61
Moving paving unit to Marshall County...........,......... 1,628.14
Rented equipment idle from April 14th to June 20th, 1933.... 3,666.89
Maintaining skeleton crew during delay..................... 2,022.61
Cost of cleaning brick...................................... 209.04
Equipment rental, R. Balton during delay.................. 2,557.20
Increased cost of labor-wage scale........................... 2,659.74
Increased cost of gasoline................................... 2,645.86
Increased cost of paving due to winter operations........... 424.90
Cost of straw curing method made necessary due to delay in furnishing cement ....................................... 972.57
817,795.77

In its answer, the respondent has alleged that during January 1933, “as a result of the persistent collusion by cement producers and others to impose exorbitant prices for cement and to induce and cause collusive bidding,” respondent by “executive order” refused to accept bids on cement; that it was not until June 15, 1933, that the respondent was able to procure cement through competitive bidding; that the conspiracy and collusion by cement producers and others prevented the State from obtaining and delivering cement to the claimant; and that the State of Illinois, as a sovereign commonwealth, is not liable to claimant in damages for any delay caused by such executive order, or its failure to deliver cement to claimant during the periods complained of.

The claimant contends, however, that the respondent - presented no evidence of any “collusion” or “conspiracy”, and presented no evidence that the respondent was prevented from delivering cement to claimant during this period. Claimant contends that the evidence shows that there was abundant cement in the market; that the companies were overstocked; that the price of bids was fair and in line with the then commercial market; and that the bids protected the State against any increase during the year.

At the hearing before Commissioner Blumenthal, Robert Kingery, former Assistant and Acting Director of the Department of Public Works and Buildings, testifying on behalf of the respondent, stated that on January 20, 1933 the respondent advertised for bids returnable February 27th; that seventeen companies submitted bids, and that the bids received were uniform at an average statewide bid of $1.62 per barrel at point of delivery; that he had a conference with Mr. Lieberman and, Mr. Hathaway, Engineer of Construction, to discuss what action should be taken; that it was agreed that they would reject the bids, but took the matter up with Governor Horner; that he told the Governor at that conference that the bids were 68c per barrel higher than the bids in 1932, but that during the preceding year there had been what was known as a “ cement war, ’ ’ and that the companies bidding in 1932 had bid prices which were, in his judgment, lower than the cost of cement; that he thought a fair price might be somewhat over $1.25 per barrel, but considered $1.62 out of line; that the Governor asked what his recommendation was, and that he recommended the bids be rejected and that the Governor told him to reject “those bids.” Accordingly, he rejected the bids, and advertised for new bids, returnable March 27th, 1933.

Free access — add to your briefcase to read the full text and ask questions with AI

Hartmann-Clark Bros. v. State, 17 Ill. Ct. Cl. 99, 1947 Ill. Ct. Cl. LEXIS 26 (Ill. Super. Ct. 1947).

17 Ill. Ct. Cl. 99 (Hartmann-Clark Bros. v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)