Hartlin v. Cody

134 A.2d 245, 144 Conn. 499, 1957 Conn. LEXIS 127
CourtSupreme Court of Connecticut
DecidedJuly 24, 1957
StatusPublished
Cited by17 cases

This text of 134 A.2d 245 (Hartlin v. Cody) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartlin v. Cody, 134 A.2d 245, 144 Conn. 499, 1957 Conn. LEXIS 127 (Colo. 1957).

Opinion

King, J.

The plaintiffs and the defendant entered into a written contract for the installation of a heating system on the second floor of the defendant’s building in East Haven. The contract, dated September 23, 1953, took the form of a conditional sale agreement and incorporated by reference a letter written on the preceding day by the plaintiffs to the defendant. The contract price was $1130, payable in cash in two instalments, the first, of $500, when the work was roughed in, and the second, of $630, when it was completed. The contract stated: “Time for making payments . . . shall be and is of the essence of this contract, and if any of the above payments shall be in default ... the whole amount owing shall become due and payable at the option of the Seller[s].” The sellers guaranteed that the “system, when operated according to directions, will heat all rooms in which registers have been placed to the Buyer’s reasonable satisfaction except said guarantee shall not be operative while any default exists in the payment for the furnace as outlined above.” It was also provided that “[sjhould occasion arise, within one year from date of sale, for complaint against the service, it is mutually agreed that the Seller[s] will be permitted to examine the installation, system and premises, *502 and. if the installation is at fault, to make such adjustments as are necessary.”

Although installation was completed about January 11, 1954, and the defendant has since used the system whenever weather conditions required, he has paid no part of the purchase price. On March 8, 1954, the plaintiffs filed a mechanic’s lien on the premises, and on or about July 21, 1954, the defendant procured dissolution of the lien upon the substitution of a bond under the provisions of § 7221 of the General Statutes (as amended, Cum. Sup. 1955, § 2975d).

The plaintiffs instituted this action in September, 1954, seeking, as a first claim for relief, recovery of the amount due under the contract and, as a second claim for relief, an adjudication of the amount due under the mechanic’s lien, with interest. The defendant, besides denying the material allegations of the complaint, interposed a special defense alleging that the system was of insufficient capacity and failed to provide adequate heat. A jury trial was had, confined to the issues involved in the first claim for relief. The jury returned a verdict for the plaintiffs on the complaint for $1263.69, being the amount due under the contract, with interest, and a verdict for the plaintiffs on the counterclaim. Judgment was entered December 29, 1955.

The defendant’s only exception to the charge was based on the court’s failure precisely to give the written requests to charge. An exception is unnecessary in the case of a failure to give a written request to charge. Degnan v. Olson, 136 Conn. 171, 172, 69 A.2d 642; Practice Book § 153; Maltbie, Conn. App. Proc. (2d Ed.) p. 137. Nor is a court request; it is sufficient if the substance of the re-ever required to charge in the precise words of a *503 quest is clearly given. Jacobs v. Swift & Co., 141 Conn. 276, 280, 105 A.2d 658; Maltbie, op. cit., p. 134.

Although divided into three paragraphs, the requests to charge covered but one basic proposition, as follows: Under the circumstances, and notwithstanding the provisions of the contract as to times of payment, the buyer had a reasonable time in which to pay; the guarantee was effective until the expiration of this period; and if before its expiration the buyer discovered that the system was not as guaranteed, he would be under no duty to pay until the guarantee was fulfilled, since the obligation to pay within a reasonable time and the guarantee as to heating to the buyer’s reasonable satisfaction were mutually dependent. It is obvious that the purpose of the defendant in making these requests to charge was to guard against a finding by the jury that because he had not made payments as provided in the contract the guarantee was inoperative, for if the jury so found, they might hold him liable for the contract price regardless of whether the system performed in accordance with the terms of the guarantee.

The court in effect charged that the plaintiffs were not entitled to recover anything under the contract “unless [they had] fully performed the obligations placed upon [them] by the contract” or unless recovery was possible under the rule of substantial performance, which the court explained in a portion of the charge to which no exception was taken. The court further charged: “If the work was not done to the defendant’s reasonable satisfaction . . . the plaintiffs cannot recover. The plaintiffs are under the duty to install a heating system that would substantially heat the premises to the reasonable satisfaction of the buyer.” It is *504 obvious that tbe jury could have allowed nothing under these instructions unless they found, as their verdict indicates that they did, that the system was as guaranteed. The charge as given completely ignored the exculpatory provision in the guarantee and unequivocally stated that unless the heating system performed to the reasonable satisfaction of the defendant, the plaintiffs could recover nothing. It was far more favorable to the defendant than his requested charge. There is no merit in the claim of error predicated on the failure to give the requests to charge.

The defendant complains of one ruling on evidence. He finished his direct testimony near the close of the day. The next morning, counsel for the plaintiffs began to cross-examine him, utilizing, for the purpose, a transcript of his direct testimony. The defendant objected on the ground that the transcript was not in evidence. Thereupon the plaintiffs offered it in evidence. It does not appear that the defendant objected to its admission, although he did take an exception without giving any reason for doing so. Since no objection was made, the admission of the transcript could not have been erroneous under any circumstances. There was no claim on which the court was asked to rule. Maltbie, Conn. App. Proc. (2d Ed.) § 52.

After the judgment on the verdict, the plaintiffs, in accordance with the second paragraph of their claims for relief, moved that the court adjudicate the amount secured by their mechanic’s lien. The court, after hearing, found that the amount secured by the lien, with interest, was $1263.69, and judgment was entered to that effect. See Burque v. Naugatuck Lumber Co., 113 Conn. 350, 354, 155 A. 414.

*505 Aside from claims for the correction of the finding which cannot be granted in any particular which will advantage the defendant, the assignments of error on this branch of the case raise the decisive claim that under the wording of the conditional bill of sale the heating system remained personal property, so that in the event of nonpayment the plaintiffs had as a matter of law no right to a mechanic’s lien but merely a right to repossess the system under the terms of the conditional bill of sale.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Farms Associates v. Commissioner of Revenue Services
903 A.2d 152 (Supreme Court of Connecticut, 2006)
Kelehear v. Northeast Specialty Corp., No. 062589 (Dec. 18, 2000)
2000 Conn. Super. Ct. 16308 (Connecticut Superior Court, 2000)
Hall v. Cohn, No. 9803-8730 (Mar. 16, 1998)
1998 Conn. Super. Ct. 2913 (Connecticut Superior Court, 1998)
New England Savings Bank v. Meadow Lakes Realty Co.
706 A.2d 465 (Supreme Court of Connecticut, 1998)
Chayka v. Perugini, No. Cv97-0256513s (Jul. 15, 1997)
1997 Conn. Super. Ct. 12395 (Connecticut Superior Court, 1997)
Thompson & Peck, Inc. v. Division Drywall, Inc.
696 A.2d 326 (Supreme Court of Connecticut, 1997)
Landscape Mgmt. Ser. v. Farmington Plaza, No. Cv94-0539633s (Sep. 18, 1996)
1996 Conn. Super. Ct. 5331 (Connecticut Superior Court, 1996)
American On-Time Plumbing v. Foxboro Develop., No. 281572 (Sep. 7, 1990)
1990 Conn. Super. Ct. 2300 (Connecticut Superior Court, 1990)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Six Carpenters, Inc. v. Beach Carpenters Corp.
372 A.2d 123 (Supreme Court of Connecticut, 1976)
Cain v. Country Club Delicatessen of Saybrook, Inc.
203 A.2d 441 (Connecticut Superior Court, 1964)
Louche v. Silvestri
179 A.2d 835 (Supreme Court of Connecticut, 1962)
Bell & Zajicek, Inc. v. Heyward-Robinson Co.
182 A.2d 339 (Connecticut Superior Court, 1962)
Biller v. Harris
161 A.2d 187 (Supreme Court of Connecticut, 1960)
Glens Falls Insurance v. Somers
156 A.2d 146 (Supreme Court of Connecticut, 1959)
Presta v. Monnier
146 A.2d 404 (Supreme Court of Connecticut, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
134 A.2d 245, 144 Conn. 499, 1957 Conn. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartlin-v-cody-conn-1957.