Hartford Accident & Indemnity Co. v. Western Casualty & Surety Co.

173 F. Supp. 544, 1959 U.S. Dist. LEXIS 3135
CourtDistrict Court, S.D. Mississippi
DecidedMay 27, 1959
DocketNo. 2156
StatusPublished
Cited by1 cases

This text of 173 F. Supp. 544 (Hartford Accident & Indemnity Co. v. Western Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Co. v. Western Casualty & Surety Co., 173 F. Supp. 544, 1959 U.S. Dist. LEXIS 3135 (S.D. Miss. 1959).

Opinion

BEN C. DAWKINS, Sr., District Judge.

Filed originally in the State Court of Mississippi, this case was removed here on the ground of diversity.

One H. C. Vaughan on December 30, 1947, signed a contract with United States to construct a portion of the Natchez Trace Parkway in Leake County, Mississippi, for the sum of $305,760 and plaintiff became the surety on his performance bond for the penal sum of $152,880. Thereafter, March 1, 1948, Vaughan sub-let a portion of the work to Norman Concrete Works (called Norman) for $94,583, and the latter also gave Vaughan a performance bond for the full contract price, on which defendant, Western Casualty & Surety Company (called Western), was surety.

The contract between Vaughan and the United States provided for payments as follows:

“Article 16. Payments to contractors. — (a) Unless otherwise provided in the specifications, partial payments, will be made as the work progresses at the end of each calendar month, or as soon thereafter as practicable, on estimates made and approved by the contracting officer. In preparing estimates [545]*545the material delivered on the site and preparatory work done may be taken into consideration.
“ (b) In making such partial payments there shall be retained 10 percent on the estimated amount until final completion and acceptance of all work covered by the contract: Provided, however, That the contracting officer, at any time after 50 percent of the work has been comleted, if he finds that satisfactory progress is being made, may make any of the remaining partial payments in full: And provided further, that on completion and acceptance of each separate building, vessel, public work or other division of the contract, on which the price is stated separately in the contract, payment may be made in full, including retained percentages thereon, less authorized deductions.”

Plaintiff’s bond as surety for Vaughan to the Government was rather short, latitudinous and said nothing about retain-age or withholding 10 percent or any other portion of the contract price to be paid Norman, but stated:

“Now, Therefore, if the principal shall promptly make payment to all persons supplying labor and material in the prosecution of the work provided for in said contract, and any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications of said contract that may hereafter be made, notice of which modifications to the surety being hereby waived, then this obligation to be void; otherwise to remain in full force and virtue.”

However, both the sub-contract and bond, by Norman with Vaughan, in which defendant was surety, contained provisions for retaining by Vaughan 10 per cent of the entire price, as appears from the following excerpts from those two documents:

The Contract

“It is understood and agreed to by both parties that we shall be paid on a monthly estimate basis as furnished you by the Public Roads Administration and that you shall retain ten per cent (10%) of the monthly estimates uhtil the work is accepted and paid for by the Public Roads Administration.”

The Vaughan-Norman Bond, on which defendant was surety:

“Now, Therefore, the condition of this obligation is such that if the Principal shall faithfully perform the terms and conditions of the contract and pay all persons furnishing labor and materials thereon, and shall indemnify and save harmless the Obligee by reason of failure so to do, then this obligation shall be null and void; otherwise to remain in full force and effect.
“Provided, However, That the Obligee will not make final settlement with the Principal or release to him any portion of the retained percentage without the written consent of the Sitrety.”

It thus appears that meticulous care was used in wording both contract and bond for the sub-let work. However, stipulations of this nature, in bonding contracts, are for the benefit of everyone concerned having a financial interest, including owner, contractor, laborers, materialmen and bondsmen, where that purpose reasonably appears.

Norman completed its work which was approved and accepted, the money to pay for it was passed, presumably, by the Government, to Vaughan, who in turn, without the knowledge or consent of defendant, surety, or creditors of Norman paid the latter who failed to pay the following claims incurred by it in doing the job: Faulkner Concrete Company $5,112.40, Lion Oil Company $786.64, and Pylates Welding and Machine Shop $552.67, a total of $6,451.71. .Suits were filed upon those claims in the State Court [546]*546against Hartford, who, as surety, paid them and in turn brought this suit.

In disposing of motions by defendant for particulars and for summary judgment, by consent, the following order was entered by the Judge of this Court:

“Came on to be heard the Defendant’s motion for a bill of particulars, whereupon Plaintiff, through its counsel of record, announced that it elected: (1) to stand and proceed exclusively upon its position that Plaintiff is entitled to recover as a subrogee of third parties paid by Plaintiff, viz.: Faulkner Concrete Pipe Company; Lion Oil Company and Pylate’s Welding Machine Shop; and (2) to deny the materiality of, but to concede, for the purposes of this suit, the fact that M. C. Vaughan released retainage in the amount of $9,458.30 without Defendant’s knowledge or consent, expressed or implied; and (8) that said retainage has not been tendered or made available to Defendant and that Plaintiff cannot and will not attempt to justify as a subrogee of M. C. Vaughan; and (4) to abandon anything in the form of allegations, statements or denials in the pleadings or record to the contrary.
“Wherefore, the Court is of the opinion that the particulars called for in Defendant’s motion are immaterial to the issues thus defined and it is ordered that Plaintiff’s election, as above recited, supercede anything to the contrary in the pleadings and record herein and that Defendant’s motion for a bill of particulars be overruled.”

This obligation of Hartford to protect others against violation of primary contract by Vaughan included the surety for Norman.

At the trial the claims paid by Hartford were stipulated, with the concluding paragraph reading as follows:

“That Norman Concrete Works completed Part C of Project 3M1A, Natchez Trace Parkway, Leake County, Mississippi, without default, at a profit in excess of $6500.-00, subject to and before allowance for the claims aforesaid of Faulkner, Lion and Pylate’s and that there was enough retainage in the job to have satisfied said claims but said retainage was by M. C. Vaughan released to Norman Concrete Works without the knowledge or consent, express or implied, of Defendant, and same was not applied in payment of said claims.”

Plaintiff has chosen to rely solely on its claim to subrogation to the rights of the creditors whose bills it paid.

It and defendant were paid sureties, the first on the whole and the latter that part of the work sub-contracted by Norman from Vaughan in the sub-contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
173 F. Supp. 544, 1959 U.S. Dist. LEXIS 3135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-co-v-western-casualty-surety-co-mssd-1959.