Hartford Accident & Indemnity Co. v. Flanaghan

73 Pa. D. & C. 506, 1950 Pa. Dist. & Cnty. Dec. LEXIS 401
CourtPennsylvania Court of Common Pleas, Berks County
DecidedJanuary 5, 1950
Docketno. 95
StatusPublished

This text of 73 Pa. D. & C. 506 (Hartford Accident & Indemnity Co. v. Flanaghan) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Berks County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Co. v. Flanaghan, 73 Pa. D. & C. 506, 1950 Pa. Dist. & Cnty. Dec. LEXIS 401 (Pa. Super. Ct. 1950).

Opinion

Shanaman, J.,

Hartford Accident and Indemnity Company, plaintiff, sued T. M. Flanaghan, defendant, in assumpsit on a book account to recover a net balance of premiums claimed to be due for various types of insurance. None of the items of the book account are in dispute except those relating to bond no. 1988964, with respect to which Flanaghan had admittedly paid the original premium. The dispute has arisen because Flanaghan contends that only a part of his premiums was earned, and that he, therefore, is entitled to a rebate. Both parties, through their counsel, stipulated at the trial that the respective claims of plaintiff and defendant are $2,329.27 and $774.21. Each party presented a single point for binding instructions in the amount of such party’s [507]*507claim. Both parties, through their counsel, represented to the trial judge that no issue of fact was raised for the jury, although such representation does not appear of record. Neither counsel addressed the jury, nor moved for leave to address the jury. The court gave binding directions for plaintiff for $2,329.27, and reserved a point as to whether binding instructions should not have been given for defendant against plaintiff for $774.21. The jury returned a verdict for plaintiff for $2,329.27. Defendant filed rules for new trial and for judgment n. o. v. The sole issue under those rules, as stated in defendant’s brief, is whether plaintiff was bound as surety on the bond in question for all of the work performed by Flanaghan under subcontract 956 and the change orders in question, alleged to pertain thereto, or whether plaintiff was only bound as surety in the sum of $58,989, which is the amount of w;ork done by Flanaghan under his original engagement, and not including work done by him under the change orders in question. If plaintiff was bound to indemnify for any failure or defect of work done by Flanaghan under the change orders, it earned the full premium, because the amount of the work done by Flanaghan under the change orders plus the amount of work done in performance of his original obligation, exceeded the amount of the original contract and bond. If plaintiff had earned the full premium originally paid by defendant, defendant is entitled to no rebate, and the verdict for plaintiff was correct. If, on the other hand, plaintiff was not bound under its bond to indemnify as to defendant’s work done under the change orders, defendant is entitled to a rebate and the verdict should be set aside and judgment should be entered for defendant Flanaghan, n. o. v., for $774.21. It is not alleged that defendant in any way defaulted in his performance of the work assigned him under his contract and the change orders.

[508]*508The facts are as follows: Chas. H. Tompkins Co. was the United States Navy’s wartime prime contractor for the construction of a naval training station at Bainbridge, Md., for $28,000,000, an amount subsequently greatly increased. Article 12 of the prime contract authorized the United States to make changes in the prime contract by addition or decrease, or diminution of projects, or other modification, whether or not the time required to perform was thereby altered. Various changes were from time to time made by the Government, greatly increasing the amount of the contract price. Defendant Flanaghan became the successful bidder as a subcontractor under Chas. H. Tompkins Co., on a contract to install water and sewage distribution systems, under and subject to the general contract, including all water and sewer connections for the various group areas, and service connections exterior to the areas and to the individual buildings. He was accordingly awarded subcontract no. 956, for $234,396. His agreement (exhibit no. 1) authorized change orders to vary the extent or amount of the work. Flanaghan supplied, as was required, an indemnity bond of plaintiff company, bond no. 1988964, for $234,396, and paid to plaintiff the premium. The bond covered the original subcontract and “any and all duly authorized modifications of said contract that may hereafter be made”. Defendant’s work had to do with four boot camps, located at four different spots on the general blue print of the training camp. His work was of the same general nature at each. He performed the work at group 4, being one of the boot camps, but was stopped by the contractor from doing the work under his contract at groups 1, 2 and 3. His work at group 4 amounted to $58,000, or more accurately $58,989. Groups 1, 2 and 3 were taken from him by the contractor and assigned to other persons in order to rush the job. Defendant does not dispute [509]*509the authority of the contractor to have done this. After defendant had completed group 4, the contractor asked him to bid on other similar work connected with the same training station, and he became the successful bidder and performed such additional work, to a total amount, including the $58,000, of $313,000. The full amount of this has either been paid or tendered by Chas. H. Tompkins Co. to defendant.

The additional work was done in accordance with four change orders dated, respectively, 10-26-42, 7-2-43, 8-18-43, and 8-23-43. Each was marked as a change order under order no. 956, defendant’s original order and subcontract number. No new or separate contract was entered into between Tompkins Company and defendant for the additional work. No additional bond was given by defendant or requested from him for such additional work. The general contractor likewise was in possession of relevant change orders from the Government to the general contractor. Of the work done by Flanaghan, under the change orders, all was outside groups 1, 2, 3 and 4; some was physically outside the Naval base, and some physically inside the Naval base; all of them were connected with the necessary construction of the Naval base. Some of the additional work was contained in the original plans, and some was not. All the work was for the base and done at or near it, and all was of the same general nature, viz., sewer and water system construction.

Since the Government retained power under its general contract to change the work contracted to be done, or even the projects themselves, subject to equitable adjustment with the contractor, and since the subcontractor contracted with the contractor subject to the provisions of the general contract between the general contractor and the Government, and since defendant’s subcontract also permitted change orders to be made or given subject to equitable adjustment [510]*510(exhibit 1, art. V), and since the changes were all within the scope of the contractor’s as well as the nature of the subcontractor’s original service, and were all for the construction of the same great object, viz., the national training camp, it is reasonable to regard the modifications as mere changes of the amount and of the exact locus of the physical service to be rendered by defendant, without any substantial alteration of the fundamental purpose either of the subcontract, the kind of work, or the location or identity of the main object, to wit, the training camp. It follows that all the work done by defendant was done under his subcontract no. 956, and basic purchase order no. 956 by means of lawful change orders thereunder.

It is true that defendant’s four change orders came after the date on which he had contracted to complete his performance of the work originally assigned to him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indemnity Company v. . Perry
151 S.E. 629 (Supreme Court of North Carolina, 1930)
Monongahela Street Railway Co. v. Philadelphia Co.
39 A.2d 909 (Supreme Court of Pennsylvania, 1944)
Koch v. Moyer and Burkhart
158 A. 198 (Superior Court of Pennsylvania, 1931)
Morse v. City of Boston
148 N.E. 813 (Massachusetts Supreme Judicial Court, 1925)
Mueller v. Eau Claire County
84 N.W. 430 (Wisconsin Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
73 Pa. D. & C. 506, 1950 Pa. Dist. & Cnty. Dec. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-co-v-flanaghan-pactcomplberks-1950.