Harry C. Partridge, Jr. & Sons, Inc. v. M & R Construction Corp. (In Re Harry C. Partridge, Jr. & Sons, Inc.)

48 B.R. 1006, 1985 U.S. Dist. LEXIS 20059
CourtDistrict Court, S.D. New York
DecidedMay 7, 1985
DocketBankruptcy No. 85 B 20398, 85 Adv. 6022
StatusPublished
Cited by15 cases

This text of 48 B.R. 1006 (Harry C. Partridge, Jr. & Sons, Inc. v. M & R Construction Corp. (In Re Harry C. Partridge, Jr. & Sons, Inc.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harry C. Partridge, Jr. & Sons, Inc. v. M & R Construction Corp. (In Re Harry C. Partridge, Jr. & Sons, Inc.), 48 B.R. 1006, 1985 U.S. Dist. LEXIS 20059 (S.D.N.Y. 1985).

Opinion

DECISION ON MOTION TO RECOVER CONTRACT RETAINAGE

HOWARD SCHWARTZBERG, Bankruptcy Judge.

The debtor in this case, Harry C. Partridge, Jr. & Sons, Inc., seeks an eight *1007 percent solution with respect to the dispute involving the installation of detention cells for New Jersey’s Camden County Correctional Facility. The defendant, M & R Construction Corp. (“M & R”), is general contractor at the job site under a contract with the Camden County Board of Chosen Freeholders (the “Camden Board”), which provides that the Camden Board is entitled to withhold a sum equal to two percent of the amount of aggregate invoices submitted by M & R until the contract is satisfactorily completed. The debtor’s subcontract with M & R provides that M & R is entitled to withhold a sum equal to ten percent of the amount of the aggregate invoices submitted by the debtor until the debtor’s subcontract is satisfactorily completed. The subcontract also provides that if M & R’s retainage provision with Camden Board is reduced the debtor would be entitled to a reduction in the retainage provision under the subcontract. The debtor maintains that the difference between the two percent retainer called for under M & R’s contract with Camden Board and the ten percent retainer withheld by M & R under its subcontract with the debtor, namely a difference of eight percent, constitutes a reduction in the retainer provision entitling the debtor to the return of eight percent of the amount of the aggregate invoices submitted by the debtor to M & R. On the other hand, M & R asserts that there has been no reduction in the retainage provision under its agreement with Camden Board and the debtor is not entitled to the return of any retained amounts because the debtor has not completed the contract.

Independent of the dispute between the parties as to the merits, M & R contends that this is not a core proceeding within the meaning of 28 U.S.C. § 157(b) and that this court may hear this matter pursuant to 28 U.S.C. § 157(c), with any final order to be entered by a district judge after considering the proposed findings and conclusions of law of this court.

FINDINGS OF FACT

1.The debtor, Harry C. Partridge, Jr. & Sons, Inc., a corporation organized under the laws of the State of New York, filed with this court on September 18, 1984, its voluntary petition for reorganizational relief under Chapter 11 of the Bankruptcy Code.

2. The defendant, M & R Construction Corp., is a corporation organized under the laws of the State of New Jersey and is engaged in business as a general contractor in the construction of municipal properties and buildings.

3. The defendant, American Insurance Company, is a Pennsylvania corporation which furnished a surety bond to the Camden Board and guaranteed the payment and further performance by M & R in accordance with the general contract.

4. In April of 1983, M & R entered into a prime contract with the Camden County Board of Chosen Freeholders for the general construction at the Camden County Correctional Facility in Camden, New Jersey, at the price of $18,079,500. Pursuant to the requirements of the prime contract and the laws of the State of New Jersey, M & R furnished to the Camden Board a surety bond for the faithful performance of the prime contract of M & R and its payments to subcontractors, materialmen, laborers, suppliers and other persons, firms or corporations which perform labor or supply materials, provisions, or other supplies to M & R with respect to the prime contract.

5. Article 5 of the agreement between the Camden Board and M & R provides that Camden Board is entitled to withhold a sum equal to two percent of the amount of the aggregate invoices submitted by M & R until M & R has satisfactorily completed its entire obligations under the prime contract. The two percent retainage provision was established in recognition of the fact that M & R had also furnished a surety bond to Camden County to guaranty its faithful performance under the prime contract.

6. Immediately upon being awarded the prime contract in April of 1983, M & R heard from the debtor’s representative, Mr. Terry Partridge, who expressed the debt- or’s interest in bidding for the subcontract *1008 work involving the installment of detention equipment in accordance with the plans and specifications for the job in question. Terry Partridge and Mr. J. Mac Gregor for the debtor reviewed the plans and specifications for a few weeks and determined that the debtor should prepare and submit a bid for the job for four million dollars.

7. By letter dated May 4, 1983, M & R confirmed that the job would be awarded to the debtor and that a purchase order would follow. However, there ensued a delay during which time no contract was entered into between M & R and the debtor. By letter dated October 6, 1983, Anne Oswalt, vice president of the debtor, wrote to M & R complaining that the debtor had “performed an awful lot of work on this project without a proper contract.”

8. In April of 1984, M & R forwarded to the debtor a formal agreement covering the debtor’s subcontractual obligations at the Camden County construction facility.

9. Article 4 of the subcontract between M & R and the debtor provides that M & R was entitled to withhold a sum equal to ten percent of the amount of the aggregate invoices submitted by the debtor until the debtor has satisfactorily completed its entire obligations under the subcontract. This language is expressed in the subcontract as follows:

ARTICLE 4
PROGRESS PAYMENTS
The Contractor shall pay the Subcontractor monthly progress payments on the basis of invoices which are to be submitted in DUPLICATE on or before the XXX of each month, representing the value of labor performed and/or material delivered and properly stored during the month. When the General Contractor’s invoice has been approved and payment is received, payment will be made to the Subcontractor by the 25th of the following month on the basis of 90% of such invoice for each monthly submission. The retained percentage will be paid promptly upon approval by the Architect and payment by the Owner of the General Contractor’s final invoice, and upon receipt of a Release of Liens form acceptable to the General Contractor and executed by the Subcontractor. Invoices received after the XXX ofthe month will not be processed for the current billing.

10. When the debtor’s vice president, Anne Oswalt, reviewed the proposed subcontract she found the ten percent retain-age provision to be objectionable. She advised Mr. Peter Silva of M & R that ten percent was unwarranted. She testified that he said that M & R could not give up more than it had and that he would not take it out of M & R’s pocket. Anne Oswalt was not aware of the fact that the prime contract between Camden Board and M & R called for a two percent retainage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Wefco, Inc.
97 B.R. 749 (E.D. New York, 1989)
Edgcomb Metals Co. v. Eastmet Corp.
89 B.R. 546 (D. Maryland, 1988)
In Re L & v. Realty Corp.
76 B.R. 35 (E.D. New York, 1987)
Stallings v. Kellogg (In Re Hudson Oil Co.)
68 B.R. 735 (D. Kansas, 1986)
Arnold Printworks, Inc. v. Apkin
61 B.R. 520 (D. Massachusetts, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
48 B.R. 1006, 1985 U.S. Dist. LEXIS 20059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harry-c-partridge-jr-sons-inc-v-m-r-construction-corp-in-re-nysd-1985.