Harrison Construction Co. v. Nissen

199 P.2d 886, 119 Colo. 42, 1948 Colo. LEXIS 180
CourtSupreme Court of Colorado
DecidedNovember 15, 1948
DocketNo. 15,911.
StatusPublished
Cited by13 cases

This text of 199 P.2d 886 (Harrison Construction Co. v. Nissen) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison Construction Co. v. Nissen, 199 P.2d 886, 119 Colo. 42, 1948 Colo. LEXIS 180 (Colo. 1948).

Opinion

*43 Mr. Justice Jackson

delivered the opinion of the court.

Plaintiffs in error, who were the unsuccessful plaintiffs in the trial court, brought suit under an oral contract for leveling defendant’s land. They had done some leveling for defendant in 1944 under an earlier oral contract and were paid therefor at the rate of eleven dollars per hour per unit of machinery used. The undisputed evidence is that the 1945 operations, which are the subject matter of this suit, arose out of a conference between plaintiffs and defendant held at the Walsh Hotel in Alamosa on March 20, 1945, in which it was agreed that plaintiffs should do leveling of additional land belonging to defendant. At that time they had most of their land leveling units engaged in other operations, but they agreed to furnish one unit and start leveling a certain part of defendant’s land immediately at the rate of twelve dollars per hour. This particular phase was completed and it is agreed that for this part of the 1945 operations plaintiffs are entitled to $978.00 and the court so stated in its instructions.

The second phase of the 1945 operations, the basis of this litigation, concerns the subsequent leveling begun in May 1945, when plaintiffs’ other equipment became available. Plaintiffs claim this was to be employed at the rate of eleven dollars per hour per unit so engaged, and that these figures were quoted to defendant at the meeting on March 20. Defendant claims there was no mention of cost until May 9, 1945, when he told plaintiff Harrison that he had only so much money to spend and suggested forty dollars an acre as the approximate cost of the work. Harrison testified that not until June 15 or 20, when work was finished and bill presented, did defendant mention any definite amount he had to expend for the work. Thus defendant’s contention is that the second phase of the 1945 operations was not to be based upon the amount of time engaged in the operation, but at the rate of forty *44 dollars per' acre of land leveled. In his pleadings and testimony he claimed that plaintiffs’ operations did not result in the land being properly leveled according to specifications; that there was therefore no substantial performance.

Defendant filed three counterclaims: one for the amount of approximately $6,000.00 based upon the theory that, after plaintiffs had completed their work, it was necessary for defendant to employ someone else to complete the leveling operations so that the land would drain properly. In connection with this first counterclaim, defendant testified that he paid for this subsequent leveling at the rate of eleven dollars per hour. The second counterclaim was based upon the contention that plaintiffs’ leveling operations were to be completed within a certain time in order that defendant could use portions of the land for the raising of crops during the growing season of 1945; that by reason of plaintiffs’ failure so to level said land within the proper time, defendant lost crops to the amount and value of $1,125. A third counterclaim was for merchandise which plaintiffs purchased from defendant’s store in the amount of $1,-493.00. This is admitted by plaintiffs and is therefore not an issue in this case.

The undisputed evidence discloses that the survey made to guide the leveling operations by plaintiffs was made by Joseph P. Sexton, Jr., an employee of the U. S. soil conservation service; that Sexton was engaged by defendant to make the survey; that defendant personally assisted in the survey; that he “held the rod,” and set and marked the stakes.

Work began May 5, 1945, and ended June 4, 1945. Harrison testified that he and defendant had a conversation in the northeast corner of a field on May 9; that defendant told him he wanted him “to take that work by the acre---57 acres of it,” to which Harrison replied that he “wouldn’t take it by the acre for him or anybody else, that I had never worked by the acre at any *45 price.” Defendant told him to think it over and left. Defendant denies that Harrison told him he would not take it at any price by the acre. .Harrison further testified that he made a suggestion to defendant with reference to cutting down the cost, but that defendant “wouldn’t go for a skimming proposition at all,” he wanted to level it to the stakes, which was done.

After plaintiffs removed their equipment from defendant’s land on June 4, 1945, defendant made no immediate objection to the leveling work that had been performed, and on June 20 tendered plaintiffs a- check in the amount of $3,324.00, which included $1,044.00 for the first phase of the work, leaving $2,280.00 as payment for the second phase which is the basis of this litigation. Harrison refused the tender, and the next day defendant left the check at plaintiffs’ bank with instructions to credit to plaintiff’s account. Plaintiffs never gave the bank authority to carry -out this order, and after a time defendant called for and received his check from the bank. All of this occurred before this action was instituted.

The jury returned a verdict in favor of defendant on plaintiffs’ complaint, and verdicts in favor of plaintiffs on defendant’s first two counterclaims. Error is specified on the ground that these verdicts are inconsistent and not supported by the evidence. Error also is alleged because of certain court instructions given the jury, and subsequent proceedings leading up to the judgment.

The record shows that the taking of testimony was completed at five o’clock of the third day of the trial; that the court read its instructions to the mixed jury at six o’clock, and then inquired whether it would be necessary to make arrangements for overnight accommodations. The foreman of the jury thereupon replied that they did not Understand instruction No. 1, which contained the court’s statement of the pleadings and the issues involved in the case. The court replied it would not be proper to comment further upon it. Fifteen min *46 utes later the court again recalled the jury and inquired whether it would be necessary to provide accommodations for the night. Thereupon the following colloquy took place:

“The Court: Now the question is shall we find quarters for you ladies and gentlemen? A Juror: No, I don’t think it will take very long but it will take an hour or so yet. We will have to go all through that again. The Court: Is that the way you all feel about it? A juror: There is one question we can’t get together on. The Court: Well then bring in your verdict according to that last instruction I gave you [relating to a sealed verdict] at ten o’clock tomorrow and all the papers at ten o’clock with your verdicts. A juror: Alright.” At that time a form of sealed verdict was given to the jury. The record is silent as to when the signed, sealed verdict was delivered to the clerk. It was opened by the court the following morning, June 13, 1946, at ten o’clock a.m.

There would appear to be some ground for the contention that the jury was not very deliberate in its consideration of this case, and that it acted even hastily in view of the statement of its foreman, that they did not understand the issues formed by the pleadings as set forth by the court in its first instruction.

In instruction No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

School District No. 12 v. Security Life of Denver Insurance Co.
185 P.3d 781 (Supreme Court of Colorado, 2008)
School District No. 12 v. Security Life of Denver Insurance Co.
179 P.3d 1 (Colorado Court of Appeals, 2007)
Kleban v. Eghrari-Sabet
920 A.2d 606 (Court of Special Appeals of Maryland, 2007)
Boulder Valley School District R-2 v. Price
805 P.2d 1085 (Supreme Court of Colorado, 1991)
Hugh v. Washington Industrial Bank
757 P.2d 1154 (Colorado Court of Appeals, 1988)
Dysart Associates Architecture & Construction, Inc. v. Hoeltgen
728 P.2d 756 (Colorado Court of Appeals, 1986)
Polkes & Goldberg Insurance v. General Insurance Co. of America
481 A.2d 808 (Court of Special Appeals of Maryland, 1984)
Gray v. Houlton
671 P.2d 443 (Colorado Court of Appeals, 1983)
Wulff v. Christmas
660 P.2d 18 (Colorado Court of Appeals, 1982)
Weeks v. Churchill
615 P.2d 74 (Colorado Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
199 P.2d 886, 119 Colo. 42, 1948 Colo. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-construction-co-v-nissen-colo-1948.