Harris v. Miller

11 F. 118, 6 Sawy. 319, 1880 U.S. App. LEXIS 2766
CourtDistrict Court, D. Oregon
DecidedMarch 8, 1880
StatusPublished
Cited by7 cases

This text of 11 F. 118 (Harris v. Miller) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Miller, 11 F. 118, 6 Sawy. 319, 1880 U.S. App. LEXIS 2766 (D. Or. 1880).

Opinion

Deady, D. J.

The plaintiffs, M. Harris and M. Lichenstein, bring this action to recover the sum of $2,000 as liquidated damages for the alleged violation of an agreement by the defendants, James D. Miller and Charles P. Church, to construct a brick building on the south-east corner of First and Morrison streets, in this city, and to lease to the plaintiffs certain rooms therein for the term of five years from and after July 1, 1878. The cause was heard by the court without a jury upon the issues of fact, and, at the same time, upon a demurrer to the replication. From the evidence it appears that on December 8, 1878, the plaintiffs and defendants entered into a written agreement whereby the latter agreed to erect a brick building upon a lot on the south-east corner of First and Morrison streets, in this city, and to lease to the former certain rooms therein for the term of five years from and after July 1, 1878, for the monthly rent of $150, payable in advance, in consideration whereof the defendants agreed to so pay said rent, and “to make, execute, and deliver” to the defendants on or before February 1, 1878, and to their satisfaction, “a good and sufficient and approved bond in the sum of $2,000, conditioned to become void on the payment of said rent, and to become forfeited as “the agreed and fixed amount of damages” to be recovered by the defendants for a default of 30 days in the payment of said rent; and a failure on the part of the plaintiffs to so furnish such bond was to render the agreement void. It is also provided in said agreement that any failure upon the part of the defendants to perform the same shall entitle the plaintiffs to recover the sum of $2,000 for such failure, as “stipulated and liquidated damages.”

The defence to the action, as contained in the answer, is that the sum mentioned in the agreement as liquidated damages for the violation thereof, was only intended as a penalty; that the defendants erected the building as per said agreement; but that the plaintiffs did not on or before February 1, 1878, nor since, deliver to the defendants a good and sufficient bond, as by said agreement they undertook and promised.

The replication alleges that before February 1, 1878, the defendants had so changed the plan of said building as to put it out of their power to comply with their agreement, and thereby excused the plaintiffs from tendering the bond"for payment of the rent.

The argument in support of the replication is that if the defendants, on February 1, 1878, by reason of their own act, were unable [120]*120to perform their contract, the plaintiffs may recover the stipulated damages for non-performance, without having complied with the condition precedent on "théir part, to-wit, the delivery of the bond for the payment of the rent. As authority for the proposition, counsel cite Pattridge v. Gildermiester, 40 N. Y. 96, and Hawley v. Keeler, 53 N. Y. 120. The first case is one where a party to a contract having failed to perform a condition precedent, the other was allowed to recover for part performance, and is therefore not in point. In the second case the court does say that “the party who disables himself from performing his contract before default by the other party waives the performance of acts by the latter, which, except for such disability, he would be bound to perform as conditions precedent to a recovery on the contract.” But the court held that the contract to give security for the payment of a quantity of cheese was not a condition precedent to the delivery thereof, but only concurrent with such delivery, and that, therefore, when the owner of the cheese had otherwise disposed of the same before the time for delivery, the other party was excused from providing or tendering the security, and might maintain an action for the non-delivery.

But the giving of the bond for the payment of the rent wa,s a condition precedent in this case, and a very material one, for upon the faith of it the defendants were not only to furnish the rooms for five years, but in a large part to incur the expense of constructing a comparatively costly building.

However this may be, this demurrer must be sustained, because a mere change of plan before February 1, 1878, did not in the least degree affect the ability of the defendants to construct the building ‘so as to furnish the plaintiffs with rooms therein according to the contract. The plan of the building might be changed every day. The defendants were under no obligation to build according to any plan until the bonds were furnished for the rent, and when that was done they could build according to the agreement, notwithstanding any changes of plan that may have been made in the mean time.

Considering the case, then, with this demurrer sustained, from the evidence the further facts appear to be that early in January the the plaintiffs delivered to the defendants a bond in the sum of $2,000, in due form of law, conditioned for the payment of the rent, as provided in the agreement, executed by themselves and William Harris and Isaac Friedman, of San Francisco, on December 26, 1879. Soon after it was received, the defendants sent the names of the sureties to Dun & Co.’s commercial agency in San Francisco, to ascer[121]*121tain their financial condition and standing, and towards the last of January received an answer to the effect that they were not at all equal to any such undertaking, and that what real property they had was covered with homesteads; and there is no evidence in the case tending to show the fact to be otherwise. On January 30th defendants returned the bond to the plaintiffs, saying: “Neither of the parties referred to seem to be men of any financial standing beyond the value of homestead exemption, and we therefore refuse the bond offered by you, not being satisfied with the guarantors thereon. We require men of undoubted standing as bondsmen, particularly as the amount of the bond is much less than the aggregate liability for rental.”

The work upon the building was not commenced until in March, and, so far as the rooms which the plaintiffs were to have are concerned, the building was constructed substantially as was contemplated at the time of the agreement, except that the width of the principal room on the lower floor was one foot in twenty-nine less, and that an elevated platform and a small circular stairway, convenient for the uses of the plaintiffs, were not put in said room, but can be at any time at a comparatively small cost.

After refusing the bond offered by the plaintiffs, the defendants were still willing and offered to allow the plaintiffs to give a satisfactory bond, but the plaintiffs did nothing further in the matter except to claim that the one given was sufficient, when, about the last of February, the defendants told the plaintiffs that the contract was at end, and they could not have the rooms. The building was finished in July, when the portion which the plaintiffs were to have was leased to a third person for something less than they were to pay for it. Upon these facts the first point made by counsel for defendants is that the sum named in the agreement as liquidated damages, to be paid by them for a failure to furnish and lease the rooms, is, notwithstanding such designation, only a penalty, .and therefore can only be recovered so far as the proof shows the plaintiffs to have been injured by such failure.

Upon this subject the law is peculiar, and, instead of giving effect to the contract of the parties according to their intentions, it assumes to control them according to its standard of justice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Southwestern Surety Ins.
206 F. 486 (D. Oregon, 1913)
Merica v. Burget
75 N.E. 1083 (Indiana Court of Appeals, 1905)
Mondamin Meadows Dairy Co. v. Brudi
72 N.E. 643 (Indiana Supreme Court, 1904)
Pressed Steel Car Co. v. Eastern Ry. Co.
121 F. 609 (Eighth Circuit, 1903)
Chicago House-Wrecking Co. v. United States
106 F. 385 (Seventh Circuit, 1901)
Gay Manuf'g Co. v. Camp
65 F. 794 (Fourth Circuit, 1895)
Patchen v. Keeley
19 Nev. 404 (Nevada Supreme Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
11 F. 118, 6 Sawy. 319, 1880 U.S. App. LEXIS 2766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-miller-ord-1880.