Chicago House-Wrecking Co. v. United States

106 F. 385, 53 L.R.A. 122, 1901 U.S. App. LEXIS 3970
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 12, 1901
DocketNo. 643
StatusPublished
Cited by10 cases

This text of 106 F. 385 (Chicago House-Wrecking Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago House-Wrecking Co. v. United States, 106 F. 385, 53 L.R.A. 122, 1901 U.S. App. LEXIS 3970 (7th Cir. 1901).

Opinion

Upon the foregoing statement of facts,

BUNN, District Judge,

delivered the opinion of the court.

We think it was error to direct a verdict for the full amount of $20,000, the amount named in the bond, without requiring evidence of actual damages sustained. Such a claim would seem to savor more of the pound of flesh and "due and forfeit of my bond” rule than of the spirit of modern equity. Unless it be clear that the case is one where it would be difficult or impossible to assess the actual damages from testimony given, the court should construe the amount named in the bond or contract as a penalty, although the parties have chosen to call it “stipulated damages." It is a general rule that, where the contract provides for the payment of a large; sum of money upon the failure of the party to pay a smaller sum, the amount named as damages will be construed as a penalty, although called “stipulated damages.” This is not because the contract to pay money is essentially different from a contract to perform work or labor or to do any other thing, but because the actual damages are capable of assessment; and the rule is just the same in all cases where the actual damages can be assessed from testimony. The parties cannot, by calling the sum mentioned “stipulated damages,” change what is essentially a penalty intended to secure the performance of the contract into damages, to take the place of the damages actually sustained. The Revised Statutes of the United States (section 961) provide:

“Tn all suits brought to recover the forfeiture annexed to any articles of agreement, covenant. Pond, or other specialty, where the forfeiture, breach or nou-peri'ornmneo appears by the default or confession of the defendant or upon demurrer, the court shall render judgment for the plaintiff to recover so much as is due according to equity. And when the sum for which judgment should be rendered is uncertain, it shall, if either of the parties request it, be assessed by a jury.-’

This rule congress has provided for the guidance of the federal courts in all cases where it is applicable. It is just, benign, and equitable, while the rule which the court has applied in the case at bar seems harsh, inequitable, and quite unnecessary. Aside from the above statute, which defines the attitude of the government towards these cases, and prescribes the rule it is willing to abide by, we think, under the more recent adjudications of the courts, both in this country and in England, the $20,000 mentioned in the bond in this case should be construed as a penalty, rather than as stipulated damages to be recovered upon any slight breach of the contract, when nominal damages or small actual damages to be assessed by the jury would satisfy the conditions more justly and equitably. If the parties could at will change what is essentially a penalty, and properly intended to enforce the obligations of the contract, into stipulated damages, it could be done in any case, although the dam[390]*390ages might be either nominal or easily assessable. Take the case at bar. When found that the work of removal could not be completed by the time named, the parties entered into an agreement extending the time several months, to April 1st. At the time of giving the bond in suit, and when the time was thus extended, the work of removal had not reached the cement bed or foundation upon which the whole building rested, and which has been the prime obstacle to the performance of the job. When this cement foundation was reached it was found, or at least it was so alleged, to be much thicker, — more than twice as thick in places as the government proposals and schedules had given out. This, it was claimed, caused great delay and an extra expense of some $16,500. Can it be just, or really supposed to have entered into the contemplation of the parties, that under such circumstances, arising, probably, without any expectation •or anticipation of either party, if the completion of the work was delayed for a single hour or day beyond the 1st of April, that the wrecking company should pay the sum of $20,000? Or if the work were completed by the time named, except a few yards of excavation in the cement foundation, or the clearing away of a little rubbish, which could be accomplished in a few hours or days, and the expense «easily estimated, that the like punishment should follow? Such a rule, if supported by law, certainly does not seem to comport ydth the more benign and beneficent rule of the statute above quoted, or the plain principles of equity and fair dealing. According to tin» ■construction placed upon the contract, the same measure of damages would apply if the wrecking company required one day or six months beyond the time fixed to complete the work. Such considerations, we think, go to show that the amount named should be construed as a penalty. There is no complaint that the wrecking company did not complete the job. The only complaint is that it ran a little beyond the time fixed. Saying nothing about the claimed right of the company to recover of the government the extra expense of $10,500 incurred in the removal of the cement foundation, is there anything unreasonable in the claim, in case it be true that there was this «difference between the actual facts in regard to the thickness of the cement and the representations in the government schedules upon which the bid was made, that this would form a reasonable excuse for not completing the work by the very day named in the contract? Or suppose it be true, as claimed, that the company was hindered and delayed in the work by the action of the government officers having the matter in charge; is there anything unreasonable in the claim that this would form a good excuse for delay? / A similar question has recently twice been before this court, particularly in East Moline Co. v. Weir Plow Co., 37 C. C. A. 62, 95 Fed. 250, where the question was gone into more or less exhaustively, and the decisions reviewed. That case grew out of a contract for the removal of the plow company’s factory from Monmouth, Ill., to a point near Port Byron Junction, where the plaintiff company owned real estate it «desired to enhance in value and to place upon the market. The contract contained various stipulations of varying degrees of importance, with this provision as to damages:

[391]*391“It is hereby mutually agreed by and between the parties hereto that the measure of damages for the default of either party to carry out its agreement shall be $50,000. less such sums as may have been paid by either party to the other.”

. The plaintiff sought to recover the $59,000 as stipulated damages, and the defendant made the same claim against the plaintiff, by way of counterclaim. No proof of damages was offered by either party, and «he court held that neither party could recover the §50,000, which, the court construed as a penalty. The opinion in that case will obviate the necessity of any very extended review of the authorities in the case at bar. fcftill, a brief reference to some of the leading adjudications contained in the brief for plaintiff in error may not be inappropriate.

In Manufacturing Co. v. Camp, 13 C. C. A. 137, 65 Fed. 794, 25 U. S. App. 134, it was provided in the contract that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archie Bradsher Davis v. Peerless Insurance Co.
255 F.2d 534 (D.C. Circuit, 1958)
Weathers Bros. Transfer Co. v. United States
109 Ct. Cl. 310 (Court of Claims, 1947)
Poinsettia Dairy Products, Inc. v. the Wessel Co.
166 So. 306 (Supreme Court of Florida, 1936)
United States v. New Amsterdam Casualty Co.
41 F.2d 917 (First Circuit, 1930)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)
Johnson v. Southwestern Surety Ins.
206 F. 486 (D. Oregon, 1913)
Pacific Hardware & Steel Co. v. United States
48 Ct. Cl. 399 (Court of Claims, 1913)
Evans v. Moseley
114 P. 374 (Supreme Court of Kansas, 1911)
United States v. Alcorn
145 F. 995 (U.S. Circuit Court for the District of Western Missouri, 1906)
Wood v. Niagara Falls Paper Co.
121 F. 818 (Second Circuit, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
106 F. 385, 53 L.R.A. 122, 1901 U.S. App. LEXIS 3970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-house-wrecking-co-v-united-states-ca7-1901.