Harris County v. Donaldson & Hines

48 S.W. 791, 20 Tex. Civ. App. 9, 1898 Tex. App. LEXIS 353
CourtCourt of Appeals of Texas
DecidedDecember 22, 1898
StatusPublished
Cited by17 cases

This text of 48 S.W. 791 (Harris County v. Donaldson & Hines) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris County v. Donaldson & Hines, 48 S.W. 791, 20 Tex. Civ. App. 9, 1898 Tex. App. LEXIS 353 (Tex. Ct. App. 1898).

Opinion

WILLIAMS, Associate Justice.

On the 27th day of May, 1897, an action was brought in the court below by Donaldson & Hines against Harris County to recover, for the benefit of certain named assignees, to whom plaintiffs had assigned parts of the fund sued for, the sum of two thousand nine hundred and eighty-four dollars, in which amount it was alleged the county had become indebted to Donaldson & Hines as the contract price for putting furniture in a building built by the county for its Criminal District Court and jail. In this suit some of the assignees, to whom plaintiffs had assigned parts of the fund, intervened, *10 setting up their rights, and the county, on the 9th day of October, 1897, filed its answer, alleging the assertion of claims upon the money by other persons besides those named in plaintiffs’ petition, and praying that such persons be made parties. The answer claimed also that certain deductions should be made from the amount claimed by plaintiffs on account of their failure to comply with the contract. The answer further alleged the pendency of another suit involving the same subject matter. The suit thus referred to was one in the nature of a bill of interpleader filed by the county on the 7th day of June, 1897, alleging the facts stated in the answer, claiming the same deductions and stating the existence of conflicting claims to the fund; in connection with which the county paid into court the sum of $1980, admitted by it to be due, and prayed for proper adjudications of the rights of all parties and protection to itself.. To this latter action all persons interested were made parties and also appeared, filing pleadings raising the same issues as those made in the suit first filed.

This statement will show the nature of the proceedings sufficiently for the purposes of the decision, in which a review of the numerous pleadings filed in the two actions is not made necessary by the questions raised. The two causes were consolidated by the order of the court and a trial was had before the court without a jury and the judgment rendered, from which this appeal is prosecuted, in which the county, W. D. Cleveland & Co., B. A.' Everts, A. L. Autrey & Co., and J. Shapley all assign errors.

The following is a statement of the facts found by us from the record thought to be essential to a disposition of the appeal:

On the 21st day of September, 1896, Donaldson & Hines made a contract with Harris County by which they agreed, in accordance with various stipulations not necessary to be stated, to “well and sufficiently perform and finish all the work included in the wood furniture for the Harris County Jail and Criminal Courtroom Building as per plans and specifications on file,” etc. It is stated in the brief filed for Cleveland & Co. that the contract involved the furnishing of the courtroom and appurtenances only and not the jail, and the case is presented by all parties on this assumption, which the record indicates, though not very clearly, to be true. The plans, etc., by which the furniture was specified are not in the record, and we can not see whether or not the use of the jail by the county was dependent upon the performance of the contract by the contractors, but, as the case seems to have been tried below and is presented here on the assumption that it was not, we shall take it for granted that the contract called for the furnishing of the courthouse proper and not the jail, and that the terms above quoted were employed in the contract simply as descriptive of the building. The sixth clause of the contract, under which the principal question arises, is as follows:

“Sixth. The contractor shall and will proceed with the said work, and every part and detail thereof, in a prompt and diligent manner, and shall and will wholly finish the said work according to the said drawings *11 and specifications, and this contract, on or before the 25th day of November, in the year one thousand eight hundred and ninety-six; and in the default thereof the contractor shall pay to the owner ten dollars for every day thereafter that the work shall remain unfinished, as and for liquidated damages.”

The seventh clause provides for extension of time for specified causes to be ascertained in a specified manner, “in which case the contractors shall be released from the payment of the stipulated damages for the additional time” certified and no more.

For the work and material the county agreed to pay the contractors the sum of twenty-nine hundred and eighty-four dollars on the second Monday of the month after the work should be completed.

The contract also contained the provision, relied on by the appellee, Shapley: “And provided further, that before each payment, if required, the contractor shall give the architect good and sufficient evidence that the premises are free from all liens and claims chargeable to the said contractors. The owner shall have the right to retain out of any payment then due or thereafter to become due, an amount to completely indemnify it against such lien or claim, until the same shall be effectually satisfied, discharged, or canceled. And, should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien on said premises, made obligatory in consequence of the farmer’s default.”

The contractors did not complete the work by the time stipulated and extensions were granted until December 31, 1896. There was.further delay in completing the work until April 3, 1897, when the county took possession. At that time the work was all complete and the furniture all in place except some items worth $104. The county had taken possession of the portion of the building constituting the jail on January 25, 1897, and thereafter used it. Owing to the fact that the furnishing of the courthouse was not completed, the county, could not use it before the date first stated. The Criminal Court was, prior to that date, held in a room of the old courthouse, and the February term was held there. The new jail, where the prisoners were kept during this term, was distant more than a mile therefrom, without public conveyance between them, and the proceedings of this term of the court were delayed and obstructed by the necessity of having the prisoners taken back and forth, one witness stating that' at least one-third of time was thus lost. There were daily in attendance from twenty-four to twenty-six jurors and also a sheriff or deputy, all of whom were paid by the county for the attendance upon court, and who were thus left unemployed for a considerable portion of the time.

The county, in anticipation of the occupancy of the new building, had sold its old jail to the city, taking the note of the latter for $7500. During .the time between December 31, 1896, and January 25, 1897, the county rented the jail from the city at the rate of $50 per month, and re *12 mitted the interest upon the note at 6 per cent. The new courthouse and jail building cost $80,300, and the ground on which it stood cost the county $15,000. Several real estate agents gave their opinion as to the value of the rent of the courthouse and appurtenances, placing it at from $200 to $300 per month. They admitted that, though possessing knowledge of rental values generally, they could not well judge as to such buildings because they were never rented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stewart v. Basey
241 S.W.2d 353 (Court of Appeals of Texas, 1951)
Sanders Nursery Co. v. J. C. Engelman, Inc.
109 S.W.2d 1131 (Court of Appeals of Texas, 1937)
Kelly v. Cochran County
50 S.W.2d 848 (Court of Appeals of Texas, 1932)
Austin Bros. Bridge Co. v. Love
34 S.W.2d 574 (Texas Commission of Appeals, 1931)
City Nat. Bank of Beaumont v. American Surety Co. of New York
34 S.W.2d 321 (Court of Appeals of Texas, 1930)
Mitchell v. City Nat. Bank of Wichita Falls
14 S.W.2d 909 (Court of Appeals of Texas, 1929)
Hewitt v. Buchanan
4 S.W.2d 169 (Court of Appeals of Texas, 1927)
Southern Surety Co. v. Bering Mfg. Co.
295 S.W. 337 (Court of Appeals of Texas, 1927)
Southern Surety Co. v. Guaranty State Bank of De Leon
275 S.W. 436 (Court of Appeals of Texas, 1925)
Rock v. Keton
229 S.W. 362 (Court of Appeals of Texas, 1921)
Hess & Skinner Engineering Co. v. Turney
216 S.W. 621 (Texas Supreme Court, 1919)
Gordon-Jones Const. Co. v. Welder
201 S.W. 681 (Court of Appeals of Texas, 1918)
City of San Antonio v. Reed
192 S.W. 549 (Court of Appeals of Texas, 1917)
West Texas Lumber Co. v. Tom Green County
188 S.W. 283 (Court of Appeals of Texas, 1916)
First Nat. Bank of Paris v. O'Neil Engineering Co.
176 S.W. 74 (Court of Appeals of Texas, 1915)
Goggin v. State Nat. Bank of El Paso
156 S.W. 321 (Court of Appeals of Texas, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
48 S.W. 791, 20 Tex. Civ. App. 9, 1898 Tex. App. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-county-v-donaldson-hines-texapp-1898.