Harris County Fresh Water Supply District No. 61 v. FWO Development, Ltd.

396 S.W.3d 639, 2013 WL 326318, 2013 Tex. App. LEXIS 825
CourtCourt of Appeals of Texas
DecidedJanuary 29, 2013
Docket14-12-00496-CV
StatusPublished
Cited by1 cases

This text of 396 S.W.3d 639 (Harris County Fresh Water Supply District No. 61 v. FWO Development, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris County Fresh Water Supply District No. 61 v. FWO Development, Ltd., 396 S.W.3d 639, 2013 WL 326318, 2013 Tex. App. LEXIS 825 (Tex. Ct. App. 2013).

Opinion

OPINION

ADELE HEDGES, Chief Justice.

In this interlocutory appeal, Harris County Fresh Water Supply District No. 61 (the “Water District”) challenges the trial court’s denial of its jurisdictional grounds for dismissal raised in a summary-judgment motion. 1 Specifically, the Water District asserts that FWO Development, Ltd. (“FWO”) failed to exhaust its administrative remedies through an appeal to the Texas Commission on Environmental Quality (the “Commission”), thus depriving the trial court of subject-matter jurisdiction. It further argues that the Commission is vested with exclusive jurisdiction to decide issues such as the amount of interest reimbursable to a developer such as FWO, with the result that the trial court has no subject-matter jurisdiction over FWO’s breach of contract claim for additional reimbursement of this interest from the Water District. Because we conclude that the trial court has subject-matter jurisdiction over FWO’s breach-of-eon-tract claim against the Water District, we affirm the trial court’s denial of the jurisdictional issues raised in the Water District’s motion for summary judgment.

BACKGROUND

On July 20, 2005, the Water District 2 and FWO entered into a contract, pursuant to which FWO agreed to pay for and construct specific water facilities necessary for development of property it owned and wished to develop within the Water District. In return, the Water District agreed to issue bonds necessary to reimburse FWO for certain costs associated with construction of the facilities. The contract between the parties required the Water District to “make its best efforts to issue bonds (the “Bonds”) at the earliest time for the purpose of purchasing the Facilities from [FWO], ... together with interest thereon.” (emphasis added). In ex *641 change for reimbursement from the bond proceeds, FWO agreed to convey the facilities to the Water District. FWO agreed to cooperate in transferring title to the facilities by “executing such documents as necessary to memorialize title as the Water District may require.”

Specifically, once FWO constructed the facilities, the Water District promised to “use its best efforts to issue, sell and deliver its bonds ... on the best available terms as soon as reasonably practical” in accordance with the other terms of the contract. The Water District would then use the proceeds of the sale of the bonds to pay the “Reimbursable Share” incurred by FWO in the manner and amount approved by the Commission. “Reimbursable Share” is defined by the contract as “the maximum amount of reimbursement allowable for projects under the Rules of the Commission and allowed and approved by the Commission, together with interest thereon, calculated from the date of payment by [FWO] ... through the date of acquisition of the facilities,” with the interest rate equal to the “net effective interest rate at which the bonds are sold.” The contract additionally provides: “Notwithstanding any other provisions of this Contract, [FWO] agrees to waive any and all claims against other sources of revenues of the District, and to look solely to the issuance of Bonds as the source of reimbursement for [FWO].”

In 2008, the Water District began preparing an application to the Commission for approval of both various developers’ projects, including FWO’s project, and the issuance of bonds to be used to reimburse these developers for the cost of these projects. At an August 27, 2008 meeting of the Water District board of directors, a representative from FWO raised several issues concerning reimbursement to FWO under the 2008 bond application. One of the issues he raised was the interest to be reimbursed under the bond application. The board’s attorney informed him that “all District preconstruction agreements with past and current developers call for payment of no greater than two years interest on the eligible costs.” 3 The FWO representative informed the board that “Commission rules may permit additional interest to be paid under certain circumstances.” The minutes from this meeting state, “[T]he Board declined to extend any interest past the two-year interest authorized by the District’s reimbursement agreement.” FWO did not appeal the Water District decision to request only two years reimbursement of interest in its bond application to the Commission. 4

In January 2009, after the facilities were constructed, the Water District applied to the Commission for approval of the projects and issuance of the bonds for reimbursement. On September 18, 2009, the Commission issued its initial order approving the projects and bond issuance, including interest reimbursement of only two years for FWO as requested by the Water District. One of the other developers challenged the Commission’s order, which had denied certain costs for which the Water District had sought reimbursement. That challenge resulted in the Commission’s issuing a revised order on February 9, 2010. *642 This order also limited FWO’s interest reimbursement to two years.

That same developer asserted an administrative challenge to the revised order, which was overruled. The developer then unsuccessfully sued the Commission. Following the conclusion of these unsuccessful challenges, the Water District began the process of issuing the bonds authorized by the Commission’s revised order almost eighteen months later, in July 2011. The minutes from a July 20, 2011 Water District Board Meeting indicate that FWO had corresponded with the Water District on July 13 and July 15, 2011, requesting that the District consider reimbursement of approximately $240,000.00 in additional developer interest. The minutes reflect that the Water District’s attorney “confirmed the Board’s position that it will not be making any application to the Commission to amend the bond order to pay additional interest to any party.” The bond sale was tentatively scheduled for August 10, 2011.

On July 22, 2011, the Water District responded in writing to FWO’s correspondence of July 13 and 15, 2011. In this letter, the District stated:

The District respectfully disagrees with FWO’s assertion that the District is required to pay additional interest above the two years authorized under the Commission staff memorandum dated February 5, 2010 and Order dated February 9, 2010. The District will not be making an amended application for additional interest for any party.
[[Image here]]
The District will require the execution of a release and a conveyance of facilities at the time reimbursement occurs. Any litigation filed by FWO will only complicate matters and result in a delay of reimbursement.

FWO filed an original petition and application for a temporary restraining order (“TRO”) on July 29, 2011 against the Water District. It alleged that the District had breached its contract with FWO, damaging it to the extent of up to three years interest, or a maximum of almost $250,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
396 S.W.3d 639, 2013 WL 326318, 2013 Tex. App. LEXIS 825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-county-fresh-water-supply-district-no-61-v-fwo-development-ltd-texapp-2013.