Harrington v. Spokane County

114 P.3d 1233
Court of Appeals of Washington·Decided June 23, 2005·No. 22837-1-III·Published·Cited by 9 cases

Opinion

114 P.3d 1233 (2005)

Alan HARRINGTON, individually and dba Harrington Construction, Petitioner,
v.
SPOKANE COUNTY, a political subdivision of the State of Washington, Respondent.

No. 22837-1-III.

Court of Appeals of Washington, Division 3, Panel Eight.

June 23, 2005.

*1236 Stanley R. Schultz, Attorney at Law, Liberty Lake, WA, Stacy A. Bjordahl, Attorney at Law, Spokane, WA, for Appellant.

Martin D. Rollins, Spokane County Prosecutor's Office, Spokane, WA, for Respondent.

SWEENEY, A.C.J.

¶ 1 Standing to seek judicial review of a land use decision generally requires the petitioner to exhaust all administrative remedies. The superior court dismissed this land use petition because, among other things, the landowner failed to exhaust his administrative remedies. We agree with that decision and affirm.

FACTS

¶ 2 This is a dispute between Alan Harrington doing business as Harrington Construction and Spokane County (County) over the conditional grant of a permit to build a residence on a lot adjoining a canal off Long Lake.

¶ 3 In 1989, developer Gary Correll, Mr. Harrington's predecessor-in-interest, bought property on Long Lake for residential development. Mr. Correll constructed a canal through the subdivision to give each lot direct access to the lake. When Mr. Correll applied for a permit to install a central sewer system, the Department of Ecology designated the canal as "shoreline" subject to both the Shoreline Management Act of 1971 (chapter 90.58 RCW) (Act) and the Spokane County Shoreline Master Program. Mr. Correll disputed the shoreline designation but did not appeal it to the shoreline hearings board as required by the Act. Instead, he sued in superior court for a declaratory judgment that the canal was not shoreline. The court dismissed the action for failure to exhaust administrative remedies. We affirmed that decision in an unpublished opinion. Correll v. Dep't of Ecology, noted at 102 Wash.App. 1054, 2000 WL 1514842 (2000).

¶ 4 Mr. Harrington acquired one of the lots and in 2002 proceeded with his plan to build a single family residence on it. He first applied to the Spokane Regional Health District for a permit to install a conventional septic tank system. The Health District issued the permit on August 13, 2003. Mr. Harrington then submitted the permit with an application to the Spokane County Department of Building and Planning.

¶ 5 In a letter dated August 19, 2003, Spokane County withheld the permit because the proposed sewage system did not comply with the County's shoreline master program. The program includes a set of regulations for on-site sewage systems for single-family residences. The regulations require a 10-foot vertical separation between the ground water table and the bottom of any sewage system drain field or dry pit. Spokane County Shoreline Master Program (SCSMP) § 9.2.11 (the standard vertical separation is three feet). Mr. Harrington's proposed vertical clearance was less than 10 feet. He argued that the canal was not shoreline for the purposes of SCSMP § 9.2.11. The County rejected his argument. The County told Mr. Harrington that his remedies were either to seek an amendment to the regulation or to apply for a variance.

¶ 6 Mr. Harrington then submitted a proposal for a state-of-the-art alternative to the conventional gravity septic system. He argued that system should not be subject to the vertical clearance requirement because it employs neither a drain field nor a dry pit. Instead, this aerobic treatment unit treats waste in an internal digestion chamber to produce a clear, odorless, high quality effluent. Mr. Harrington asked the County to administratively interpret its regulations and evaluate the compliance of the aerobic treatment unit.

¶ 7 The County responded that it lacked the authority to render an administrative interpretation of its own regulations as applied to his proposed treatment unit. It explained that the shoreline master program does not just require that sewage systems with a drain field or dry pit have a 10-foot vertical clearance. Rather, only those systems with either a drain field or a dry pit and *1237 a 10-foot clearance can comply. The County again told Mr. Harrington that his administrative remedies were limited to trying to amend the shoreline master program or seeking a variance. The County insisted that no administrative review was available of the County's interpretation of the existing language of its regulations, because it was not authorized to render an interpretation. Not only could an alternative system not be approved, it could not even be considered.

¶ 8 Mr. Harrington replied that the County is the sole agency authorized by statute to administer the shoreline management regulations and that the County must have authority to interpret its own regulations. He also cited the County's earlier approval of an identical on-site aerobic treatment unit on another shoreline lot. The County acknowledged its exclusive statutory authority to administer the shoreline regulations, but insisted that the regulations contained no administrative process for considering alternatives to the systems contemplated by the regulations. And, while the previously granted permit for the same system could be construed as an administrative interpretation of the regulations, it should not be viewed as a policy that must be uniformly applied.

¶ 9 Mr. Harrington finally acquired and recorded an easement on neighboring property to install a conventional drainage system beyond the 200-foot shoreline management boundary. And the County issued a building permit the same day, November 25, 2003.

¶ 10 Mr. Harrington then filed a petition in the superior court on December 16, 2003, for judicial review under the Land Use Petition Act (LUPA), chapter 36.70C RCW. The land use decision appealed from was the County's grant of the modified permit. The petition challenged the canal's shoreline designation, the County's refusal to interpret its rules and render a decision on the aerobic treatment unit, and the alleged disparate treatment in the earlier approval of the identical aerobic treatment unit. Mr. Harrington claimed damages under chapter 64.40 RCW. That chapter provides relief for unreasonable government failure to act in the matter of land use permits. He also asserted 42 U.S.C. § 1983 claims for violations of his right to develop his property in accordance with the applicable land use regulations, denial of substantive and procedural due process, and violation of equal protection.

¶ 11 The County moved for summary judgment on a number of grounds: (1) LUPA specifically excludes judicial review of decisions reviewable by the shoreline hearings board. (2) The petition was untimely because approval of a permit is not appealable and Mr. Harrington never appealed the County's earlier adverse actions. (3) Mr. Harrington lacked standing because LUPA required exhaustion of administrative remedies. (4) Mr. Harrington alleged no injury in fact. (5) And the designation of the canal as shoreline was res judicata based on the 1999 Correll action.

¶ 12 The trial court granted the County's motion and dismissed the action. The court agreed that the County's approval of the permit was not appealable because it was not an "adverse decision." The adverse actions were instead the County's letters refusing to approve the conventional sewage system and refusing to consider the aerobic treatment unit. Because Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Harrington v. Spokane County, 114 P.3d 1233 (Wash. Ct. App. 2005).

114 P.3d 1233 (Harrington v. Spokane County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Buechler v. Wenatchee Valley College
298 P.3d 110 (Court of Appeals of Washington, 2013)
Hillary Buechler v. Wenatchee Valley College
Court of Appeals of Washington, 2013
Nickum v. City of Bainbridge Island
223 P.3d 1172 (Court of Appeals of Washington, 2009)
Kailin v. Clallam County
220 P.3d 222 (Court of Appeals of Washington, 2009)
Stientjes Family Trust v. Thurston County
217 P.3d 379 (Court of Appeals of Washington, 2009)
Harlan Claire Stientjes Family Trust v. Thurston County
152 Wash. App. 616 (Court of Appeals of Washington, 2009)