Harold P. Cousins, D/B/A Cousins Construction v. MK Ferguson of Oak Ridge Company

CourtCourt of Appeals of Tennessee
DecidedMarch 2, 1998
Docket03A01-9709-CV-00435
StatusPublished

This text of Harold P. Cousins, D/B/A Cousins Construction v. MK Ferguson of Oak Ridge Company (Harold P. Cousins, D/B/A Cousins Construction v. MK Ferguson of Oak Ridge Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harold P. Cousins, D/B/A Cousins Construction v. MK Ferguson of Oak Ridge Company, (Tenn. Ct. App. 1998).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE FILED March 2, 1998

Cecil Crowson, Jr. Appellate C ourt Clerk HAROLD P. COUSINS, d/b/a ) ANDERSON CIRCUIT COUSINS CONSTRUCTION, ) ) Plaintiff/Appellant ) NO. 03A01-9709-CV-00435 ) v. ) HON. JAMES B. SCOTT, JR. ) JUDGE MK-FERGUSON OF OAK RIDGE ) COMPANY, ) ) Defendant/Appellee ) AFFIRMED

Brian C. Quist, Knoxville, for Appellant. E. H. Rayson, William P. Snyder and John C. Burgin, Jr., Knoxville, for Appellee.

MEMORANDUM OPINION

INMAN, Senior Judge

This is an action to recover profits the plaintiff contractor alleges he

would have made had he been allowed to construct an additional four

warehouses similar in design and usage to a fifth warehouse he constructed

and for which he was paid.

The defendant is a prime contractor for the U. S. Department of Energy

and awarded a subcontract to the plaintiff for the construction of so-called

generic warehouses. Whether this subcontract firmly committed the parties to

the construction of five buildings, or, as the defendant insisted, to only one

building, with the option retained by the defendant to issue proceed orders for

the remaining four buildings, was a prime issue.

The first building was constructed, and settlement made. The parties thereafter began negotiations for the construction of the

second building. They were unable to agree on a price, and the defendant

thereupon informed the plaintiff that no options would be exercised under the

subcontract. Three of the remaining buildings were built by other contractors;

one was never constructed.

The trial court found that the subcontract was not a requirements

contract, and while the plaintiff had no guarantee that he would be awarded a

commitment, the defendant had a duty to negotiate in good faith. Pursuing

this rationale the trial court then found that the defendant breached its good-

faith obligation and awarded the plaintiff $12,557.00 as damages for certain

increased costs, but declined to award damages for loss of profits.

The trial court found that loss of profits was not a proper measure of

damages under the subcontract, and in any event the plaintiff failed to carry

his burden of proof. Somewhat singularly, the trial court then gave the

plaintiff another opportunity to prove his damages. At the second hearing the

plaintiff proffered a different theory of recovery - damages for unabsorbed

overhead - and the trial court made the award aforementioned.

The plaintiff appeals, insisting that the court erred in declining to award

damages for loss of profits, which is the proper measure in Tennessee. The

court’s declination was based on a firm finding that the plaintiff failed to

prove that such profits, even if arguably established, “would have been

available to him under the contract.” The effort of the plaintiff at the second

hearing to prove damages incurred by increased costs in lieu of proving

damages for lost profits was rejected by the court.

The issue of credibility permeated this case to a dispositive extent.

While the plaintiff’s argument that the trial court erred in declining to find that

loss of profits was not the proper measure of damages is, prima facie, meritorious, see: McLain v. Kimbrough Const., 806 S.W.2d 194 (Tenn. App.

1990), under the markedly peculiar facts of this case we cannot say that the

correct result was not reached. We certainly cannot find that the evidence

preponderates against the judgment. R ULE 13(d), T.R.A.P.

This is a proper case for affirmance pursuant to RULE 10, RULES OF THE

COURT OF APPEALS.1 Costs are assessed to the appellant.

____________________________ William H. Inman, Senior Judge

CONCUR:

_______________________________ Herschel P. Franks, Judge

_______________________________ Don T. McMurray, Judge

1 Affirm ance W ithout O pinion - M emor andum Opinio n. (b) The Court, w ith the con currenc e of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated “MEMORANDUM OPINION,” shall not be published, and shall not be cited or relied on for any reason in a subsequent unrelated case. [As amended by order filed April 22 , 1992.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Harold P. Cousins, D/B/A Cousins Construction v. MK Ferguson of Oak Ridge Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harold-p-cousins-dba-cousins-construction-v-mk-fer-tennctapp-1998.