Harnischfeger Engineers, Inc. v. Uniflo Conveyor, Inc.

883 F. Supp. 608, 1995 U.S. Dist. LEXIS 5667, 1995 WL 248077
CourtDistrict Court, D. Utah
DecidedApril 25, 1995
Docket94-C-1150W
StatusPublished
Cited by19 cases

This text of 883 F. Supp. 608 (Harnischfeger Engineers, Inc. v. Uniflo Conveyor, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harnischfeger Engineers, Inc. v. Uniflo Conveyor, Inc., 883 F. Supp. 608, 1995 U.S. Dist. LEXIS 5667, 1995 WL 248077 (D. Utah 1995).

Opinion

MEMORANDUM DECISION AND ORDER GRANTING MOTION TO DISMISS

WINDER, Chief Judge.

I. INTRODUCTION

This matter is before the court on defendant Uniflo Conveyor, Inc.’s (“Uniflo”) motion to dismiss plaintiff Hamischfeger Engineers, Inc.’s (“HEI”) complaint for lack of personal jurisdiction pursuant to Rule 12(b)(2) of the Federal Rules of Civil Procedure. The court held a hearing on Uniflo’s motion on April 14, 1995 at 8:00 a.m. At the hearing, Joseph E. Tesch and Robert A. Lonergan represented plaintiff HEI, while Charles E. Millsap and David M. Wahlquist represented defendant Uniflo.

Before the hearing, the court considered carefully the memoranda and other materials submitted by each of the parties relating to Uniflo’s motion. The court had also read certain of the authorities cited by each of the parties. Following oral argument, and after taking Uniflo’s motion under advisement, the court has further considered the law and facts related to the motion. Having now fully considered the issues in this case, and good cause appearing, the court enters the following Memorandum Decision and Order.

*610 II. BACKGROUND 1

Plaintiff HEI is a Delaware corporation with its principal place of business in Brook-field, Wisconsin and with offices located in West Valley City, Utah. 2 HEI is in the business of designing and constructing complex integrated material handling systems. On March 20, 1992, HEI entered into a contract with the United States Postal Service (“USPS”) to design and construct certain portions of the new USPS Van Nuys General Mail Facility (“Post Office”) in Santa Clarita, California. One of the things that HEI was hired to design and construct at the Post Office was a mail tray conveyor system.

Defendant Uniflo is a Kansas corporation with its principal place of business in Wichita, Kansas. Uniflo is in the business of designing and constructing conveyor systems. On June 3, 1992, HEI hired Uniflo as a subcontractor to help design and construct the mail tray conveyor system for the Post Office. Under the terms of the subcontract, Uniflo was to complete its work at the Post Office by June 25, 1993.

On January 17, 1994, the Santa Clarita area was hit by an earthquake. Because of the earthquake, much of the construction that had already been completed at the Post Office site — including construction on the mail tray conveyor system — needed to be repaired. Accordingly, on February 1, 1994, HEI contacted Uniflo by letter and asked it to' estimate the damage to the mail tray conveyor system and the delays that would result in completing the system as a result of the earthquake.

On February 10 and February 14, 1994, Uniflo sent HEI two letters which divided Uniflo’s assessment of the damage into three categories, and which stated that repairs under two of the categories were beyond Uni-flo’s contractual responsibilities and would require additional consideration from HEI before being undertaken.

On February 17, 1994, HEI sent a response letter to Uniflo’s February 10 and February 14, 1994 letters. In that letter, HEI informed Uniflo that it was contractually required to repair all of the damage to the mail tray conveyor system caused by the earthquake, and that HEI would pursue appropriate relief from the USPS if Uniflo did not fix the damage.

Soon thereafter, upon inspecting the Post Office site for earthquake damage, HEI discovered that Uniflo’s design and construction of the floor anchors for the mail tray convey- or system were inadequate. Accordingly, by letter dated February 22, 1994, HEI served on Uniflo a formal “Notice to Cure” as was required by the terms of its general contract with the USPS. HEI’s Notice to Cure asked Uniflo to re-install the floor anchors in conformity with the specifications called for in Uniflo’s subcontract with HEI.

Uniflo responded to HEI’s Notice to Cure by letter dated March 2,1994. In that letter, Uniflo again told HEI that it needed “additional compensation from HEI” prior to either repairing the damage caused by the earthquake or re-installing the floor anchors for the mail tray conveyor system. Six days later, on March 8, 1994, HEI terminated Uniflo’s subcontract. Subsequently, HEI undertook to complete the design and installation of the mail tray conveyor system for Uniflo. The engineering, project analysis, and project management portions of the completion work were done at HEI’s West Valley City, Utah offices, and the total cost of the work is alleged by HEI to have been $830,-000.

Subsequently, on September 1, 1994, Uni-flo sent a letter to Mr. Ramon Regó, a postal service employee located in Tennessee, seeking the USPS’s help in getting HEI to pay for spare parts that Uniflo delivered to the Post Office site several months earlier. Paragraph two of the letter to Mr. Rego stated:

Uniflo is extremely concerned that we will not receive payment for the legitimate supply of the $108,000 in spare parts we supplied to the Van Nuys jobsite. We are further concerned that the USPS is about *611 to release a sizeable sum of retention to [HEI] that will never find its way to Uni-flo. [HEI] illegally and unjustifiably terminated Uniflo’s contract, and we will prove this fact in a court of law. Our real concern, however, lies in the fact that even with a favorable decision from the courts, [HEI’s] financial condition will leave us with an “empty well.”

Letter from Joseph P. Forte, President of Uniflo, to Ramon Regó, R.A., Manager of Design and Construction for the United States Postal Service, at 1 (Sept. 1, 1994) (emphasis added).

Finally, on November 28, 1994, HEI commenced the present action by filing its five-count complaint against Uniflo with this court. The first three claims in HEI’s complaint are all breach of contract claims which arise out of Uniflo’s subcontract to construct and install the mail tray conveyor system for the Post Office. See Complaint at ¶¶ 26-37. The fourth claim in HEI’s' complaint is a defamation claim which arises out of Uniflo’s September 1,1994 letter to Mr. Regó. Id. at ¶¶ 38^40. The fifth claim in HEI’s complaint is a tortious interference with contract claim which also arises out of Uniflo’s September 1, 1994 letter to Mr. Regó. Id. at ¶¶ 41-43.

III. STANDARD OF REVIEW

HEI, as the plaintiff in this ease, bears the ultimate burden of establishing by a preponderance of the evidence that personal jurisdiction exists over Uniflo. Doe v. National Medical Servs., 974 F.2d 143, 145 (10th Cir.1992); DeMoss v. City Market, Inc., 762 F.Supp. 913, 915-16 (D.Utah 1991) (citing Taylor v. Phelan, 912 F.2d 429, 431 (10th Cir.1990), cert. denied, 498 U.S. 1068, 111 S.Ct. 786, 112 L.Ed.2d 849 (1991)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pohl, Inc. of America v. Webelhuth
2008 UT 89 (Utah Supreme Court, 2008)
POHL, INC. OF AMERICA v. Webelhuth
2007 UT App 225 (Court of Appeals of Utah, 2007)
Bathcrest, Inc. v. Safeway Safety Step, Inc.
417 F. Supp. 2d 1236 (D. Utah, 2006)
Jacobsen Const. Co., Inc. v. Teton Builders
2005 UT 4 (Utah Supreme Court, 2005)
Miner v. Rubin & Fiorella, LLC
242 F. Supp. 2d 1043 (D. Utah, 2003)
Hydro Engineering, Inc. v. Landa, Inc.
231 F. Supp. 2d 1130 (D. Utah, 2002)
iAccess, Inc. v. WEBcard Technologies, Inc.
182 F. Supp. 2d 1183 (D. Utah, 2002)
First Mortgage Corp. v. State Street Bank & Trust Co.
173 F. Supp. 2d 1167 (D. Utah, 2001)
Phone Directories Co., Inc. v. Henderson
2000 UT 64 (Utah Supreme Court, 2000)
Morrison Co., Inc. v. WCCO Belting, Inc.
35 F. Supp. 2d 1293 (D. Kansas, 1999)
Haas v. A.M. King Industries, Inc.
28 F. Supp. 2d 644 (D. Utah, 1998)
Patriot Systems, Inc. v. C-Cubed Corp.
21 F. Supp. 2d 1318 (D. Utah, 1998)
Procter & Gamble Co. v. Haugen
179 F.R.D. 622 (D. Utah, 1998)
Beck v. Bijoux D'Amour S.A.
923 F. Supp. 196 (D. Utah, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
883 F. Supp. 608, 1995 U.S. Dist. LEXIS 5667, 1995 WL 248077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harnischfeger-engineers-inc-v-uniflo-conveyor-inc-utd-1995.