Hari & Associates v. RNBC, INC.

946 F. Supp. 531, 1996 U.S. Dist. LEXIS 17442, 1996 WL 675859
CourtDistrict Court, M.D. Tennessee
DecidedNovember 20, 1996
Docket2:95-0077
StatusPublished
Cited by1 cases

This text of 946 F. Supp. 531 (Hari & Associates v. RNBC, INC.) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hari & Associates v. RNBC, INC., 946 F. Supp. 531, 1996 U.S. Dist. LEXIS 17442, 1996 WL 675859 (M.D. Tenn. 1996).

Opinion

MEMORANDUM

WISEMAN, Senior District Judge.

Before the Court is a motion for summary judgment in favor of Tucker Federal Savings & Loan (Tucker), a defendant, in the present diversity action that arose from the construction of a Hampton Inn motel in Cookeville, TN by Hari, the plaintiff. Athough Hari has maintained several causes of action against several defendants, only the causes of action relating to Tucker Savings & Loan are at issue in the present motion. Specifically, Hari maintains that Tucker is liable for fraud,' negligent misrepresentation, and breach of trust for its activities in relation to the surety, Capital Assurance Company of Baton Rouge, Louisiana. For the reasons that follow, Tucker’s motion for summary judgment on all three claims is GRANTED.

I. FACTS

A. The Early Days of the Hampton Inn— Cookeville Project

Mr. Hari and his family have been associated with the motel industry for roughly two decades. In this time, Hari has served as a *534 manager, owner, and developer of various motels in Tennessee and Kentucky. The present suit stems from Hari’s plan to build and develop a Hampton Inn motel in Cooke-ville, Tennessee, a plan that originated in 1991.

With the help of Victoria Denson of Weinberg & Associates, an Atlanta based financial broker, Hari was able to obtain commitments for both permanent financing and a construction loan. The permanent financing was arranged with Citizens State Bank of Liberal, Kansas (Citizens), and was to be guaranteed by the Small Business Association (SBA). Because of the SBA guarantee and the agreement with Citizens, Hari was obliged to provide evidence that his contractor had obtained “a 100% performance and labor and material payment bond executed by a corporate surety approved by the Treasury Department.” Hari Dep. Ex. 2 ¶ 5(B)(3).

Hari’s construction loan was obtained from Tucker, and was to be governed by the laws of Georgia. Pursuant to the SBA requirements, as part of their agreement, Hari was to provide evidence of “a contractor labor/material payment bond issued by a corporate surety approved by Lender in its sole discretion.” Hari Dep. Ex. 5 ¶ E(6). Hari acknowledged that he had an obligation both to the SBA and to Tucker to provide evidence of a surety. Hari Dep. p. 25, line 18, p. 26, line 20.

After the architectural plans for the motel were completed, Hari selected RNBC to serve as the general contractor for this project. Although Hari admitted that the surety bond requirements were not discussed in his initial discussions with RNBC, Hari informed RNBC that “the bank is requiring [a surety bond] and [RNBC is] to provide payment and performance bonds to [Tucker’s] satisfaction.” Hari Dep. p. 49, line 15-18. Hari did not mention the SBA’s requirement that the surety must meet with the Treasury Department’s approval. Nor did he check upon the identity and strength of the surety or verily that the surety met the SBA’s requirement. Hari Dep. p. 50-1.

Prior to the close of the construction loan, Hari learned that RNBC was having financial difficulties and may have been on the verge of bankruptcy. In response to .this disturbing news, Hari asked his attorney, Bateman, to check on the situation. Through Bateman, Hari was assured that RNBC would complete the project. Hari Dep. p. 74-6. Although Hari did not investigate the bonds after learning of the difficulty, he testified that he was relying upon the bonds being to Tucker’s satisfaction. Hari Dep. p. 76.

B. Closing the Hari — Tucker Loan Agreement

On November 2, 1992, Hari and Tucker closed their construction financing agreement. This closing went forward after RNBC provided Performance Bond No. PP92-RM-1085 and Labor and Material and Payment Bond No. PP92-RM-1085. As part of the closing, Hari delivered his equity contribution of $247,676.30 to the bank for the Cookeville project. Part of these funds were disbursed to RNBC to pay the costs associated with the bonds.

Under the Loan Agreement dated November 2, 1992, Hari agreed to commence construction of the motel within ten days and agreed that, upon completion, the premises were to be “without liens, claims, or assessments ... for any material,, labor or other items furnished.” Hari Dep. Exhibit 16, Article III, ¶ 5. Disbursements of the loan amount could be made to the borrower, Hari, or, at the discretion of Tucker, to the general contractor if the proceeds were being paid as part of the construction costs of the motel. Hari Dep. Exhibit 16, Article IV, ¶ 8(a). Furthermore, the contract provides that

[a]ll conditions of the obligation of [Tucker] ... are imposed solely and exclusively for the benefit of [Tucker] and its successors and assigns and no other person shall have standing to require satisfaction of such conditions in accordance with their terms or be entitled to assume that lender will refuse to make advances in the absence of strict compliance with any or all thereof and no other person shall, under any circumstances, be deemed to be a beneficiary of such conditions.

Hari Dep. Exhibit 16, Article VII, ¶ 1. Finally, the relationship between Hari and *535 Tucker was “that of creditor and debtor and is not intended to be and shall not in any way be construed to be that of a partnership, a joint venture or that of principal and agent.” Hari Dep. Exhibit 16, Article VII, ¶ 6. With an agreement in place, construction was begun on the Hampton Inn motel in Cookeville, Tennessee.

C. The Events Surrounding the Completion and Final Disbursement of Funds

Over the course of construction, a dispute arose between Hari and RNBC because Hari was forced to hire several subcontractors, paying for them with his own funds. RNBC submitted the bills for these subcontractors to Tucker for payment, but RNBC retained the payments without forwarding them to Hari. Tucker had not been informed that Hari had, in fact, paid for the work.

On October 1, 1993, RNBC requested a final payment of $124,343. Along with its request, RNBC submitted a Lien Waiver in which it stated, under oath, the premises could not “be made subject to any valid lien or claim by anyone who furnished materials, supplies, labor, or services to [RNBC] for use in the above named project.” Hari Dep. Exhibit 28, p. 493. Even with these assurances, Tucker hesitated in issuing the payment until it received the approval of Hari. Hari maintains that he knew this sworn statement was false and that he informed Tucker of this.

Hari and RNBC met to discuss the distribution of the final payment. They agreed that Hari would receive $52,495 and RNBC would receive $82,538. Before payment was made, RNBC executed a final lien waiver that stated, among other things, that all subcontractors had been paid or would be paid within ten days. But, Hari was still concerned.

On November 5, 1993, a conference call was held between Hari, Bateman, and Silver-man, a loan officer at Tucker. Silverman informed Hari that RNBC would not be able to pay the subcontractors unless the final payment was released.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemons v. Cloer
206 S.W.3d 60 (Court of Appeals of Tennessee, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
946 F. Supp. 531, 1996 U.S. Dist. LEXIS 17442, 1996 WL 675859, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hari-associates-v-rnbc-inc-tnmd-1996.