Hardy v. Higginson

849 P.2d 946, 123 Idaho 485, 1993 Ida. LEXIS 86
CourtIdaho Supreme Court
DecidedMarch 25, 1993
Docket19262
StatusPublished
Cited by6 cases

This text of 849 P.2d 946 (Hardy v. Higginson) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardy v. Higginson, 849 P.2d 946, 123 Idaho 485, 1993 Ida. LEXIS 86 (Idaho 1993).

Opinion

REINHARDT, Justice Pro Tern.

Earl Hardy (Hardy) appeals the appellate decision of the district court which affirmed in part the decision of the Director of the Idaho Department of Water Resources (IDWR) allowing Hardy to amend his two existing water permits. Affirmed in part and remanded for further findings.

The facts of this case are not in dispute. Hardy holds two water permits to divert water from Box Canyon Creek to Blind Canyon for the purpose of fish propagation. The first permit, NO. 36-7091, was granted in 1971 and established a single point of diversion for 300 c.f.s. The second permit, NO. 36-7334, was granted in 1975 and established six points of diversion for 600 c.f.s. Five of Hardy’s points of diversion are located at or below a natural sculpin pool in Box Canyon Creek, 1 and the other two are located above the sculpin pool. In 1988, Hardy applied for an application to amend his water permits to secure an additional point of diversion which would coincide with a right-of-way granted by the Bureau of Land Management (BLM) over BLM land adjacent to Box Canyon Creek. This proposed point of diversion is located downstream from the sculpin pool.

Upon receipt of Hardy’s application, the Director of the Idaho Department of Water Resources (Director) published statewide notice seeking protests against approval of the proposed amendments. Twelve protests were filed on the basis that the proposed amendments were against the public interest. Hardy filed a motion to dismiss the protests on the grounds that the public interest was not a proper basis for protest. The Director denied the motion.

A hearing was held on September 28, 1988. Hardy renewed his motion to dismiss the protestants, which was again denied. At the hearing, Hardy testified that the proposed amendments would not result in an increased use of water, nor would they adversely affect the water rights of others. Hardy also submitted the testimony of Robert Cordell, the BLM Resource Area Manager for the Box Canyon area, who testified that in BLM’s estimation, the proposed point of diversion was preferable over the existing points of diversion as far as environmental considerations were concerned, and that there would be no adverse environmental impacts other than those already identified and addressed by BLM. The “Right-of-Way/Temporary Use Permit” issued by BLM, and an environmental assessment prepared by BLM, were placed in the record to establish which environmental factors the BLM took into consideration in granting Hardy’s right-of-way. The only other significant testimony came from the protestants which generally stressed that the new diversion would be contrary to the local public interest because of the adverse impacts on aesthetics, recreation and fishing. None of the protestants lived or owned property in Box Canyon.

In an order and amended order issued November 29, 1988, and February 17, 1989, respectively, the Director approved the proposed amendments. However, based on the local public interest, the Director im *488 posed various conditions on the amended permits. The Director stated that Hardy must abandon his approved points of diversion located at and below the sculpin pool once all the required approvals for use of the new point of diversion were given. As to the two points of diversion located above the sculpin pool, the Director ruled that the local public interest required Hardy to divert water from these points only “to the extent that such diversion can occur without increasing or decreasing the water levels, temperature, quality, and/or flow velocity within the natural sculpin pool located downstream.” The Director also ordered Hardy to construct a measuring device at the new point of diversion to measure the amount of water entering the new diversion. This condition was in addition to a similar condition imposed by the BLM in granting Hardy’s right-of-way which required Hardy to construct a measuring device at the proposed diversion to assure a minimum stream flow.of 75 c.f.s.

Hardy appealed the Director’s decision to the district court which affirmed the authority of the IDWR to consider the local public interest in proceedings to amend a water permit under I.C. § 42-211. However, the district court determined that the Director’s condition requiring Hardy to abandon his points of diversion located at and below the sculpin pool upon all the required approvals was inappropriate. The district court also questioned the necessity of requiring the installation of a permanent measuring device at the new point of diversion in light of the fact that the BLM right-of-way required Hardy to install a structure to verify a 75 c.f.s. minimum bypass flow. Finally, the district court determined that the Director’s condition imposed on Hardy’s points of diversion above the sculpin pool was not supported by the record because there were no findings, outside a general conclusion that the sculpin are sensitive to water changes, as to what might be required to protect the sculpin pool. Accordingly, the district court issued an order of remand to allow the IDWR to conduct further proceedings and to make further findings regarding the need for limiting the amount of water Hardy may divert from the points of diversion above the sculpin pool, and for the need to install a permanent measuring device beyond that required by the BLM.

Hardy appeals the district court’s decision and order of remand, raising the following issues:

1. Whether the Director may consider the local public interest in amending a water permit under I.C. § 42-211.

2. Whether the Director properly imposed the condition limiting the amount of water that Hardy can divert from his points of diversion located above the sculpin pool.

3. Whether the Director properly imposed the condition requiring Hardy to place a measuring device at the new point of diversion.

The IDWR has filed a cross-appeal, raising the following issue:

1. Whether the Director properly imposed the condition requiring Hardy to relinquish his points of diversion located below the sculpin pool upon receiving all the necessary approvals for use of the new point of diversion.

I.

STANDARD OF REVIEW

In an appeal from an agency decision, we review the agency’s decision independently of the district court’s decision and our review is limited to the record. Dovel v. Dobson, 122 Idaho 59, 831 P.2d 527 (1992); St. Alphonsus Med. Ctr. v. Canyon County, 120 Idaho 420, 816 P.2d 977 (1991). Under I.C. § 67-5215(g), this court can reverse or modify an agency decision only in limited circumstances such as when the agency’s decision is affected by error of law, is clearly erroneous in view of the whole record, or is found to be arbitrary or capricious. In addition, if the record is insufficient to support the agency’s decisions, we can reverse the decision or remand the case for further proceedings. Dovel v. Dobson, supra; Idaho County Nursing Home v. Department of Health and Welfare, 120 Idaho 933, 821 *489 P.2d 988 (1991); Love v. Board of County Commr’s,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Idaho Power Co. v. Idaho Department of Water Resources
255 P.3d 1152 (Idaho Supreme Court, 2011)
Department of Ecology v. Theodoratus
135 Wash. 2d 582 (Washington Supreme Court, 1998)
State, Dept. of Ecology v. Theodoratus
957 P.2d 1241 (Washington Supreme Court, 1998)
Idaho County v. Idaho Department of Health & Welfare
920 P.2d 62 (Idaho Supreme Court, 1996)
Cunningham v. City of Twin Falls
874 P.2d 587 (Idaho Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
849 P.2d 946, 123 Idaho 485, 1993 Ida. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardy-v-higginson-idaho-1993.