Hardy Exploration & Production (India), Inc. v. Government of India, Ministry of Petroleum and Natural Gas

CourtDistrict Court, District of Columbia
DecidedJune 7, 2018
DocketCivil Action No. 2016-0140
StatusPublished

This text of Hardy Exploration & Production (India), Inc. v. Government of India, Ministry of Petroleum and Natural Gas (Hardy Exploration & Production (India), Inc. v. Government of India, Ministry of Petroleum and Natural Gas) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardy Exploration & Production (India), Inc. v. Government of India, Ministry of Petroleum and Natural Gas, (D.D.C. 2018).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

HARDY EXPLORATION & : PRODUCTION (INDIA), INC., : : Petitioner, : Civil Action No.: 16-140 (RC) : v. : Re Document No.: 1, 36, 37 : GOVERNMENT OF INDIA, MINISTRY : OF PETROLEUM & NATURAL GAS, : : Respondent. :

MEMORANDUM OPINION

DENYING PETITION TO CONFIRM ARBITRATION AWARD; DENYING AS MOOT PETITIONER’S MOTION FOR LEAVE TO FILE SUR-REPLY; DENYING AS MOOT RESPONDENT’S CROSS- MOTION FOR LEAVE TO FILE RESPONSE

I. INTRODUCTION

In 1997, Hardy Exploration and Production (India), Inc. (“HEPI”) entered into a contract

with the Government of India that would allow HEPI to search for and potentially extract

hydrocarbons from an area off of India’s southeastern coast. The contract provided that if HEPI

found crude oil, it would have two years to ascertain if that oil was commercially viable, but that

if it found natural gas, that assessment period would last for five years. HEPI discovered a

reserve of hydrocarbons in 2006 and claimed that it was natural gas, entitling it to a five-year

appraisal period. India disagreed, and after two years, it informed HEPI that its rights to the

Block had been relinquished. When the Indian Government refused to change its position on the

type of hydrocarbons that had been discovered, HEPI initiated arbitration proceedings pursuant

to the contract. The Tribunal ultimately found in HEPI’s favor and ordered India to allow HEPI

back onto the Block for another three years to continue its assessment of whether the natural gas it had discovered was commercially viable. The Tribunal also awarded HEPI interest on its

original investment in the Block, as well as certain costs. India immediately appealed the award

to the Delhi High Court, and HEPI filed a separate suit in the Delhi High Court to enforce the

award. As far as the Court is aware, those cases remain pending. Three years after it had won the

arbitral award, HEPI had still not been allowed back onto the Block, and therefore filed a petition

for confirmation of its arbitral award in this court under the Federal Arbitration Act. India

opposed the confirmation, claiming that the enforcement of the award’s specific performance

order would violate U.S. public policy, as would confirmation of the interest portion of the

award, which India claimed is punitive and coercive, rather than compensatory. For the reasons

set forth below, the Court finds that confirmation and enforcement of the specific performance

portion of the award would violate U.S. public policy, and therefore, the Court declines to

confirm that portion of the award. Additionally, the Court finds that granting the award of

interest, which is predicated on India complying with an order that this Court cannot issued,

would also violate U.S. public policy, and therefore declines to confirm that portion of the award

as well.

II. FACTUAL AND PROCEDURAL BACKGROUND

This case stems from HEPI’s participation in a Production Sharing Contract (“PSC”) with

the Government of India for the extraction, development, and production of hydrocarbons in a

geographic block found off the southeastern coast of India called CY-OS/2 (the “Block”). See

Decl. of Ian MacKenzie (“MacKenzie Decl.”) ¶ 3, ECF No. 1-2; see generally MacKenzie Decl.

Ex. 2 (“PSC”), ECF No. 1-4. The PSC was originally entered into in November 1996 by three

private companies; India’s state-owned oil company, the Oil and Natural Gas Corporation

Limited (“ONGC”); and “[t]he President of India, acting through the Joint Secretary, Ministry of

2 Petroleum and Natural Gas.” PSC at 1. The PSC permitted the three private companies to

explore the Block and, if they found commercially viable hydrocarbon reserves, to extract those

resources under a production sharing arrangement. See Pet’r’s Mem. Law Supp. Pet. to Confirm

Arbitration Award (“Pet’r’s Mem.”) at 2–3, ECF No. 1-1; PSC arts. 14–15. While HEPI was not

an original participant in the PSC, it acquired a 25% participation share from one of the original

participants in 1997, and by August 2001, HEPI had acquired a 100% participation share in the

PSC. See Pet’r’s Mem. at 3; see also MacKenzie Decl. Ex. 1 (“Award”) at 3, ECF No. 1-3;

MacKenzie Decl. Ex. 4 at 1–2, ECF No. 1-6. HEPI then transferred 25% of its interest in the

PSC to GAIL (India) Ltd, a state-owned retail gas processing and distribution company in India.

MacKenzie Decl. Ex. 5 at 2, ECF No. 1-7. HEPI maintained a 75% interest in the PSC at all

times relevant to this dispute. See Pet’r’s Mem. at 4.

Each participant in the PSC entered the agreement at their own risk. If a participant

discovered a reserve of hydrocarbons that was capable of being extracted and produced

commercially, then it would be entitled to extract and produce the hydrocarbons, and would be

entitled to keep a percentage of the hydrocarbons for itself, with the rest going to the

Government of India. See PSC arts. 14–15. If participants’ work on the Block yielded no

commercially viable discovery, the participants would be entitled to no compensation for the

investment they had put into the Block. See PSC art. 7.4 (providing that the contractor shall

“conduct all Petroleum Operations at its sole risk, cost and expense and provide all funds

necessary for the conduct of Petroleum Operations . . .” unless otherwise provided in the PSC);

see also Award at 41 (observing that “[t]here is no dispute” that a contractor “is not entitled to

any compensation if it is unable to get commercial discovery of the product within the period

specified in the contract”).

3 The PSC outlined the procedures the parties would follow in the event of a hydrocarbon

discovery. See PSC art. 9. Under the PSC, after the discovery of hydrocarbons, the participants

would enter into an appraisal period to determine whether the production of the hydrocarbons in

the newly discovered reserve would be commercially feasible. See Pet’r’s Mem. at 4; PSC arts.

9.5, 21.4.4. The PSC provided for appraisal periods of different lengths depending on the type of

hydrocarbons discovered. If the discovery was crude oil, the appraisal period would be two

years, see PSC art. 9.5; if it was natural gas, the appraisal period would be five years, see PSC

art. 21.4.4.

In late 2006, HEPI and GAIL discovered a reserve of hydrocarbons and promptly

informed the Ministry of Petroleum and Natural Gas of their discovery. Pet’r’s Mem. at 4;

Award at 7–8. HEPI believed that the hydrocarbons it had discovered was natural gas, and more

particularly, Non-Associated Natural Gas (“NANG”), and therefore that its declaration of

commerciality would not be due until January 7, 2012. Id. at 6–7, 9–11. However, the Ministry

insisted that the discovery was in fact crude oil, and accordingly that HEPI’s declaration of

commerciality was due on January 7, 2009. Id. at 9–11. Therefore, the Ministry informed HEPI

via letters dated February 20 and March 23, 2009, that HEPI’s rights to the Block were

relinquished due to its failure to submit its declaration of commerciality on time. Id. Despite

HEPI’s efforts to convince the Ministry over the next year that its discovery was natural gas and

therefore that it had not missed its deadline to file a declaration of commerciality, India would

not yield. Id. at 5. Therefore, HEPI initiated arbitration proceedings pursuant to Article 33 of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scherk v. Alberto-Culver Co.
417 U.S. 506 (Supreme Court, 1974)
Verlinden B. v. v. Central Bank of Nigeria
461 U.S. 480 (Supreme Court, 1983)
Republic of Philippines v. Pimentel
553 U.S. 851 (Supreme Court, 2008)
Robbins v. United States Bureau of Land Management
438 F.3d 1074 (Tenth Circuit, 2006)
Hewlett-Packard Co. v. Berg
61 F.3d 101 (First Circuit, 1995)
Europcar Italia, S.P.A. v. Maiellano Tours, Inc.
156 F.3d 310 (Second Circuit, 1998)
NML Capital, Ltd. v. Republic of Argentina
699 F.3d 246 (Second Circuit, 2012)
Zeiler v. Deitsch
500 F.3d 157 (Second Circuit, 2007)
Glass v. LaHood
786 F. Supp. 2d 189 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Hardy Exploration & Production (India), Inc. v. Government of India, Ministry of Petroleum and Natural Gas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardy-exploration-production-india-inc-v-government-of-india-dcd-2018.