Hardie-Tynes Co Inc v. SKF USA Inc

CourtDistrict Court, N.D. Alabama
DecidedDecember 27, 2022
Docket2:16-cv-01417
StatusUnknown

This text of Hardie-Tynes Co Inc v. SKF USA Inc (Hardie-Tynes Co Inc v. SKF USA Inc) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardie-Tynes Co Inc v. SKF USA Inc, (N.D. Ala. 2022).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF ALABAMA SOUTHERN DIVISION HARDIE-TYNES CO., INC., ) ) Plaintiff, ) ) v. ) Case No.: 2:16-cv-1417-LCB ) SKF USA, INC., ) ) Defendant. )

MEMORANDUM OF DECISION

This case involves a dispute surrounding the construction of the Matlacha Bridge in Lee County, Florida. Prior orders of the Court laid out this case’s factual background in great detail. Thus, the Court will not devote substantial time to a recitation of those background facts but will reference them when necessary. The trial was split into three phases with the goal of conserving the time and resources of the Court and the parties. As more fully discussed in previous orders and filings, see, e.g., (Docs. 166 and 171), Phase I of the trial was held to determine whose terms and conditions applied to the underlying transaction. The resolution of Phase I was to determine whether Phase II was necessary, and the resolution of Phase II will determine the plaintiff’s burden of proof on its common law indemnity claim in Phase III. Phase III will also encompass the trial of the plaintiff’s remaining claims. Hardie-Tynes (“HT”) alleged four counts in its amended complaint: (1) breach of contractual indemnity clause; (2) common law indemnity; (3) breach of

warranty; and (4) fraudulent suppression. (Doc. 50). After Phase I of trial, the Court found in favor of SKF on Count 1 when it determined that HT’s breach of contractual indemnity claim must fail because neither party’s terms and conditions

controlled the underlying transaction. The Court also found in favor of SKF on Count III insofar as that count alleged a breach of any written warranties contained in HT’s terms and conditions.1 Thus, Counts 2, 4, and a portion of Count 3 remain.

Phase II of these proceedings was to determine “whether SKF made an effective/appropriate acceptance of [HT]’s tender of defense and indemnity.” (Doc. 171 at 1). As originally envisioned by the parties and the Court, Phase II

would be necessary only if HT’s terms and conditions controlled to the exclusion of SKF’s. However, given the holding in Phase I, the parties found themselves at a disagreement about whether Phase II was necessary. The Court ultimately found that it was and set Phase II for trial. Even though the Court determined that neither

party’s terms and conditions applied, Phase II was still necessary because of HT’s common law indemnity claim.

1 Count III remains pending insofar as it alleges SKF breached certain implied warranties. (Doc. 220 at 7). As will be discussed below, a Court deciding a common law indemnity claim must make various findings, one of which is whether an alleged indemnitor,

like SKF, refused to participate in the settlement or prosecution of a case involving its alleged indemnitee, like HT, despite being notified by the indemnitee that it intended to settle. This is because an indemnitee’s burden of proof for a common

law indemnity claim is dependent on the answer to that question. Thus, the question of whether SKF effectively and appropriately accepted HT’s tender of defense and indemnity was still relevant even in the absence of a valid contractual indemnity clause.

I. Findings of Fact At the bench trial of Phase II, the Court heard testimony from Charles Debardeleben, HT’s president and general counsel. The parties also offered

several exhibits that were admitted into evidence, and many other facts were not in dispute. The evidence revealed that HT was hired by Archer Western (“AW”), the general contractor for the Matlacha Bridge Project, to supply structural steel and machinery for the project. As part of its work on the project, HT purchased two

bearings from SKF for the purpose of raising and lowering a leaf of the bridge. According to AW, the project was delayed because of a loud noise emanating from the bridge during the raising and lowering of the leaf. AW believed that SKF’s bearings were to blame and sued HT2 in a Florida state court for, among other things, failing to provide SKF bearings and installation services that were free from

defects and fit for their intended purposes. Debardeleben testified that HT sent SKF a series of letters demanding that SKF defend and indemnify HT in the Florida litigation. The first letter, sent on

August 15, 2016, from HT’s attorney to SKF’s assistant general counsel, informed SKF about AW’s counterclaim in the amount of 1.7 million dollars. The letter referenced a clause contained in HT’s terms and conditions requiring SKF to indemnify HT against AW’s counterclaim. The letter stated HT’s belief that AW’s

claims had “substantial merit,” that HT had little money and was unable to defend itself against AW’s claims and demanded “that SKF take immediate steps to defend and indemnify [HT].” (HT Ex. 64).3 The letter noted HT’s response

deadline in the Florida case and requested that SKF respond to the demand within 10 days. Id. The letter concluded by stating that HT would construe SKF’s silence on the matter as an indication that SKF was refusing HT’s request for defense and

2 HT was the original plaintiff in that case having sued AW for the return of its retainage. AW’s claims were asserted in a counterclaim. 3 The Court will cite to the trial exhibits by identifying the offering party and corresponding exhibit number. The exhibits for Phase II of the trial are found in the Court’s CM/ECF system at (Doc. 241) and (Doc. 242). indemnification. Id. According to Debardeleben, SKF did not respond within that 10-day window.4

Debardeleben testified that HT sent SKF a second letter on September 6, 2016, in which it noted that, although SKF appeared to have turned the matter over to its insurer, that was not a sufficient response to HT’s demand. Therefore, HT

said, it had filed the present lawsuit against SKF in this Court. HT again asked SKF to accept its defense and indemnify it in the Florida case within seven days. HT concluded the letter by stating that if SKF failed to accept, HT would “likely have to ask Archer Western to consider an early mediation instead of protracted

litigation.” (HT Ex. 67). Over the next few weeks, the parties exchanged a series of emails and had discussions about mediating the case. Ultimately, HT, AW, and SKF mediated the

case on October 28, 2016, but were unable to reach a resolution. However, and relevant here, SKF does not dispute that it attended the mediation. As part of its case during Phase II, HT introduced a series of slides from a Microsoft Power Point presentation that were shown during the mediation. (HT Ex. 73). The fifth

slide from that presentation, entitled “Summary of Claim,” laid out a summary of the damages claimed by AW totaling nearly two million dollars. Id.

4 Debardeleben testified that HT did receive a letter on or about August 22, 2016, from SKF’s insurer, Liberty Mutual, requesting various documents related to the Florida case. Debardeleben stated that HT responded to those requests. However, nothing more was said about Liberty Mutual and whether and to what extent it participated in the case. During the same time the parties were discussing mediation, there were also emails between them regarding HT’s indemnity demand. In one email, counsel for

SKF told HT that it would move to intervene in the Florida case and “provide a defense as to all claims related to SKF’s work.” (SKF Ex. 31). In response, HT sent SKF a letter explaining that SKF’s proposed intervention would not be the

same as an unconditional acceptance of HT’s defense and indemnification. (HT. Ex. 68). This was because intervention, according to HT, served the purpose of protecting SKF’s interests, not necessarily HT’s. The letter referenced statements by SKF’s counsel as well as internal SKF emails, which were seen during

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mulhall v. Unite Here Local 355
618 F.3d 1279 (Eleventh Circuit, 2010)
Stubblefield v. St. Paul Fire & Marine Insurance
517 P.2d 262 (Oregon Supreme Court, 1973)
Bendall v. White
511 F. Supp. 793 (N.D. Alabama, 1981)
Stone Bldg. Co. v. Star Elec. Contractors, Inc.
796 So. 2d 1076 (Supreme Court of Alabama, 2000)
Watts v. Talladega Federal Sav. & Loan Ass'n
445 So. 2d 316 (Court of Civil Appeals of Alabama, 1984)
Jones v. Crawford
361 So. 2d 518 (Supreme Court of Alabama, 1978)
Travelers Indemnity Co. v. Firestone Tire & Rubber Co.
360 F. Supp. 1328 (S.D. Alabama, 1973)
Allstate Insurance Co. v. Amerisure Insurance Companies
603 So. 2d 961 (Supreme Court of Alabama, 1992)
Armstrong v. Alabama Power Co.
667 F.2d 1385 (Eleventh Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Hardie-Tynes Co Inc v. SKF USA Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardie-tynes-co-inc-v-skf-usa-inc-alnd-2022.